Whether one work content can apply multiple quota items: multi-sub-item rate build-up for BOQ items is allowed; duplicate application for the same process is prohibited
Determined in two layers: (1) one BOQ item applying multiple quota sub-items (pouring/formwork/rebar and other processes of different natures) is the normal practice of rate build-up — all-in unit rate = the sum of the sub-item amounts under the BOQ item divided by the BOQ quantity; (2) duplicate application for the same process or the same work content is prohibited — the quota work content is already complete, including all construction processes (preparation and finishing-up, on-site transport, small material handling, site cleaning, etc.), and applying separately for content already included is double counting; processes must not be split and separately listed. Judge by the nature of the process: processes of different natures may be applied separately; the same process only once.
Applicable Codes
- GB 50860-2013 构筑物工程工程量计算规范
- GB/T 50860-2024 构筑物工程工程量计算标准
- GB/T 50857-2024 市政工程工程量计算标准
- GB/T 51095-2015 建设工程造价咨询规范
- GB/T 50875-2013 工程造价术语标准
- DL/T 5468-2013 输变电工程施工图预算编制导则
- TB/T 10821-2024 铁路工程基本定额
Topic Positioning
Answers "whether one work content can simultaneously apply multiple quota items": distinguishing two layers — a BOQ item applying multiple quota sub-items (an allowed, normal practice in rate build-up) and duplicate application for the same process (prohibited).
Core Conclusions
Two layers. (1) Allowed: under BOQ pricing the all-in unit rate is built up from several quota sub-items — all-in unit rate = the sum of the sub-item amounts under the BOQ item divided by the BOQ quantity; a cast-in-place concrete member applying the three sub-items of pouring + formwork + rebar is standard usage; the rate build-up must be accompanied by an all-in unit rate analysis table (labour/material/plant consumption taken from the sub-items, unit prices taken as market prices at the time of preparation, and overheads, profit, statutory levies and fees and taxes per the matching norms for on-costs and expenses). (2) Prohibited: the quota work content is inherently complete and already covers all construction processes (preparation and finishing-up, on-site horizontal and vertical transport, small material handling, auxiliary and incidental labour, minor plant and tool repairs, site cleaning, etc.); applying separately for content already included is double counting, under the rule "what is not listed is not paid separately; ancillary works are deemed included; processes are not split". The criterion is the nature of the process: processes of different natures may each be covered by a sub-item; splitting the same process into separate items, re-applying for work already included, re-applying for content the BOQ already states as included, and breaking up combined quota items to apply them again are all prohibited. Where an item is missing in this industry, first apply the quota of a similar construction process (cross-industry or local quotas are permitted); if it is still missing, prepare a supplementary quota item and submit it to the quota administration agency for approval, with the fees charged following the basis of the quota item applied.
Applicable Boundaries
Applies to BOQ pricing and quota-based rate build-up under national, industry and local consumption quota standards; situations expressly permitted for conversion or adjustment by the quota provisions (marked "converted" after conversion for the record) are not subject to this; the notes to each volume differ on the scope of content already included (e.g. the scope of small on-site handling) — the notes to the quota volume applied prevail. After the rate build-up, check whether the work contents of the sub-items overlap — overlap means double counting, and is a frequent point of disallowance on final account review.
Further Reading
Work-content completeness: GB 50860-2013 Clause 3.0.5, GB/T 50860-2024 and GB/T 50857-2024 Clause 4.1.2, TB/T 10821-2024 general notes; all-in unit rate build-up: GB/T 51095-2015 Clause 5.3.9 and Appendix C; supplementary quota items for missing work: DL/T 5468-2013 Clause 4.1.4; composition of labour consumption: GB/T 50875-2013 Section 2.3.