Whether curing is priced separately when applying quotas to cement-concrete pavement: Beijing DB11/T 2382-2024, Shenzhen SJG 181.1-2024, and the highway quota all include curing
Cement-concrete pavement is priced by the surface-course sub-item; curing is already in the quota work content — no separate computation, no separate curing BOQ item. Beijing DB11/T 2382-2024 sub-item D2-2-20 "cement concrete surface course, 18 cm thick" work content verbatim includes "placing, vibrating, troweling, texturing, curing, etc."; Shenzhen SJG 181.1-2024 states expressly "cement-concrete pavement placing comprehensively considers pavement curing, not computed separately"; the highway system's sub-item 2-3-8 work content also includes "texturing and curing". Three calibers, one verdict.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准(北京)第7.2节道路工程、附录D子目D2-2-20
- SJG 181.1-2024 市政工程消耗量标准 第一册 道路工程
- JTG/T 3832-2018 公路工程预算定额(北京市普通公路大中修工程预算定额)子目2-3-8水泥混凝土路面
Topic Positioning
For cement-concrete pavement in municipal/highway budgets and BOQ compilation: which quota sub-item applies, whether curing is comprehended in the quota work content, and whether it must be listed separately. Covers three calibers: Beijing's municipal consumption standard, Shenzhen's, and the highway budget quota.
Core Conclusions
1. Beijing caliber (DB11/T 2382-2024, municipal works)
- Cement-concrete pavement surface applies the "cement concrete surface course" sub-item: D2-2-20 cement concrete surface course, 18 cm thick, unit 100 m2;
- Its work content verbatim: "placing, vibrating, troweling, texturing, curing, etc." — curing is in the quota work content, not to be listed separately in budgets/BOQs; the standard's municipal part sets no independent "concrete pavement curing" sub-item;
- Sub-item consumptions (per 100 m2): composite labor class II 8.2760 workdays; ready-mixed concrete C30 18.18 m3; nylon disc D100 1.5%; other tools 2%.
- Companion rules: surface-course quantities by design dimensions in area, not deducting manholes, but deducting flush channels where present; bridge-deck asphalt overlay does not deduct expansion joints (Clause 7.2.3). Formwork quantities are computed by contact area between concrete and formwork (Clause 7.2.21); formwork, grooving, etc., follow their own sub-items.
2. Shenzhen caliber (SJG 181.1-2024 municipal consumption standard, Vol. 1: roads)
- Verbatim: "Cement-concrete pavement placing comprehensively considers pavement curing, not computed separately."
3. Highway caliber (JTG/T 3832-2018 system; Beijing ordinary highway major/minor repair budget quota)
- Sub-item 2-3-8 cement concrete pavement, work content verbatim includes: "... manual placing of concrete, placing, compacting, vacuum dewatering, leveling, texturing, curing; 4) grooving, filling sealant." Curing is likewise included;
- The sub-item is listed by ordinary/fiber concrete, paver vs manual placement (rail, slipform), thickness 20 cm and each +/-1 cm.
4. General verdict When compiling, first read the work-content column of the applied sub-item: if it contains "curing", curing is not counted again — Beijing, Shenzhen, and the highway caliber agree that routine curing of cement-concrete pavement is comprehended in the placing sub-item.
Applicable Boundaries
- "Included" means the routine curing methods considered by the quota (water spraying, covering for moisture retention); where the design or codes require special curing processes, handle per the applied quota's notes and the contract;
- Municipal and highway are two quota systems with different sub-item numbers and units: the verdict is the same but application follows the project's system; other provinces must check their local standards — the sub-item numbers here map only to their own standards;
- The conclusion targets the cement-concrete surface placing sub-item itself; grooving, sealant, texturing, formwork, etc., follow each standard's sub-items or rules;
- Quantity rules follow the project location's standard (e.g., Beijing: no manhole deduction, flush-channel deduction).
Further Reading
- DB11/T 2382-2024 Consumption Standard for Construction Works, municipal works, Section 7.2 "road works" (7.2.3 surface measurement, 7.2.21 formwork) and Appendix D sub-item D2-2-20;
- SJG 181.1-2024 municipal consumption standard, Vol. 1: roads, 3.1.7 road surface courses;
- JTG/T 3832-2018 Budget Quota for Highway Works and Beijing ordinary highway major/minor repair budget quota, sub-item 2-3-8 cement concrete pavement.
Keywords
- 水泥混凝土路面
- 养护
- 养生
- 定额套用
- 水泥混凝土面层
- DB11/T 2382-2024
- SJG 181.1-2024
- JTG/T 3832-2018