Measurement unit rules for landscape greening maintenance: trees and single shrubs per plant, massed shrubs, ground cover, flowers and lawns by area, single and double hedges by extended metres, with item units as plant-months / 10 plants per month / 100 plants and the like
Maintenance measures by plant class: trees (evergreen / deciduous), single shrubs, palms and climbing plants count per plant on drawn quantity, items often converted to 100 plants, 10 plants / month or plant-months (railway LY-339 / 340 tree upkeep per 100 plants; Beijing E-2-547 establishment upkeep of evergreen trees in plant-months; Shaanxi 1-542 to 1-545 evergreen tree upkeep per 10 plants / month); massed shrubs, ground cover, open-ground flowers, lawns and vertical-wall greening by drawn area (massed shrubs often per 10 m2); single and double hedge upkeep by drawn extended metres (railway LY-343 / 344 per 100 m); water-truck watering by water volume or plant size.
Applicable Codes
- 陕西省2024年新编消耗量定额(征求意见稿)工程量计算规则第六、七、八、十、十一、十三条
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程 LY-339、LY-340、LY-343、LY-344
- DB11/T 2382-2024 建设工程施工消耗量标准 App. E Table E.2.3-8 成活养护(E-2-547)
- DB63/T 2013-2022 公路养护工程预算定额 App. F F.7.2(Table F.46~Table F.49 绿化工程日常养护)
- 湖南省2025版园林绿化工程消耗量标准(绿化养护章)
- http://zjt.hunan.gov.cn/zjt/xxgk/xinxigongkaimulu/tzgg/tzgg2jzjnykj/202512/t20251222_33877017.html
Scope of the question
The pricing basis of landscape maintenance is what unit measures what and which item applies. This card gives the source rules for maintenance units of trees, shrubs, hedges, massed shrubs, ground cover, flowers and lawns, the item-unit forms across quotas (plant-months, 10 plants / month, 100 plants, 100 m etc.) and the banding of irrigation modes and the highway upkeep system - for fixing maintenance BOQ / quota measurement.
Core conclusions
1. General unit rules (Shaanxi 2024 new consumption quota rules, source)
- Tree lifting and planting split by root ball / bare root count per plant on drawn quantity; upkeep split evergreen / deciduous counts per plant.
- Single shrubs likewise per plant; massed shrub lifting, planting and upkeep by drawn area; single and double hedges by drawn extended metres.
- Palms - lifting, planting and upkeep per plant.
- Climbing plants - likewise per plant.
- Ground cover, open-ground flowers and lawns - lifting, planting and upkeep by drawn area; potted arrangements per pot ...
- ... vertical-wall greening (carrier frames, green walls, edge planters, sculptural greening) by drawn area; its upkeep likewise by drawn area.
- Water-truck watering may compute by water volume or plant size; by size - trees and single shrubs per plant; hedges by extended metres; massed shrubs by area ...
2. Item-unit forms on the ground (local quotas)
- Trees: railway TB/T 10822-2024 Volume 1 LY-339 (deciduous) / LY-340 (evergreen) tree upkeep, unit 100 plants, work content: cultivating and weeding, clearing, top dressing, pruning, pest control, watering; Beijing DB11/T 2382-2024 E-2-547 establishment upkeep of evergreen trees, unit plant-months, work content: watering, pest control, fertilising, pruning, weeding, clearing; Shaanxi 1-542 to 1-545 evergreen tree upkeep banded by breast / trunk diameter (up to 6 / 8, 10 / 12, 16 / 18, 20 / 24 cm), unit 10 plants / month; Hunan 2025 tree upkeep per 100 plants / month.
- Shrubs: Shaanxi 1-575 to 1-579 single deciduous shrub upkeep banded by crown (up to 250, 300, 350, 400, over 400 cm), unit 10 plants / month, work content: cultivating and feeding, weeding, pest control, pruning, loosening, irrigation and drainage, clearing; massed shrubs, climbers and hedges itemise by height (massed and climbers per 10 m2, single hedges per 10 m), work content covering cultivation, feeding, weeding, pruning and bud removal, pest control, deadwood removal, irrigation and drainage, clearing.
- Hedges: railway LY-343 (single) / LY-344 (double) hedge upkeep, unit 100 m.
- Whole-green-space upkeep (Hunan 2025): work content - pruning, topdressing, irrigation and drainage, pest control, blank replanting, litter and weed clearing, tidying, patrolling; unit 1000 m2 / month; establishment / routine upkeep split by manual and water-truck watering.
3. Highway operation-stage upkeep (a different system from landscape works quotas) DB63/T 2013-2022 highway maintenance budget quota, Appendix F F.7.2 routine upkeep, Tables F.46 to F.49 set the labour, material and machine-shift consumptions of greening routine upkeep (patrol, whitewashing street trees, watering, feeding and pest control). Compiled for class-II highways and adjustable: expressways x 2.5, class I x 1.5, class III and below x 0.8; manual water carrying and watering applies within 200 m hauling; shrubs follow the tree items under 10 cm breast diameter.
Applicability limits
- Per plant / per metre / per area is the measurement basis; item units are mostly count x months composites (10 plants / month, 100 plants / month, plant-months) - matching plant class, size band (breast / trunk diameter, crown, height) and upkeep months together; crossing a band changes the item.
- Upkeep items serve only establishment and routine upkeep after acceptance; construction-stage upkeep sits inside the planting items and never re-charges (see the upkeep-period card).
- Bands and units differ regionally (100 plants, 10 plants / month and plant-months coexist); borrowing across regions checks the current local standard - the numbers here illustrate the basis only.
- Valuable trees and trees over 40 cm breast diameter take no general upkeep items - compute as executed.
- Highway upkeep quotas (operation stage) and landscape consumption standards serve different objects - no cross-application.
Further reading
- Shaanxi 2024 draft quota rules, items 6, 7, 10, 11, 13; items 1-542 to 1-545 and 1-575 to 1-579.
- TB/T 10822-2024 Volume 1 Chapter 4 slope protection: LY-339, LY-340, LY-343, LY-344.
- DB11/T 2382-2024 Appendix E landscape greening E.2.3-8 (E-2-547).
- DB63/T 2013-2022 Appendix F F.7.2 (Tables F.46 to F.49).
- Hunan 2025 landscape standard, greening upkeep chapter and rules: http://zjt.hunan.gov.cn/zjt/xxgk/xinxigongkaimulu/tzgg/tzgg2jzjnykj/202512/t20251222_33877017.html
Keywords
- 绿化养护计量单位
- 乔木养护
- 灌木养护
- 绿篱养护
- 成活养护子目
- 洒水车浇水
- 公路日常养护定额