Stages and charging of landscape greenery maintenance: the start points of construction-period, establishment and conservation (routine) maintenance, the period adjustment factors and the quantity measurement objects

Greenery maintenance divides into three non-overlapping stages: construction-period maintenance (planting to completion acceptance) is inside the planting items, never charged again; establishment maintenance runs in 'months', quantities by plant counts for trees, shrubs, climbers, standards and bamboos, length for hedges, area for lawns, flowers, colour bands, perennials and aquatics - Beijing counts from completion of planting, part months as whole months, and the part beyond one year at x 0.85 (Hunan: within one year of the planting unit works' passing acceptance - months 1-3 on establishment items, months 4-12 labour-material-plant x 0.8); conservation (routine) maintenance runs in 'years' from passing completion acceptance, its term per design or contract. Hence aquatics etc. 'plant by count, maintain by area'.

Applicable Codes

  • DB11/T 2382-2024 第8.2.27~8.2.33条
  • GB/T 50858-2024 App. A Table A.3.1 注2、注6
  • CJJ 82 园林绿化工程施工及验收规范

Positioning

The stage division and charging of landscape maintenance: the start points, term rules, quantity objects and adjustment factors of construction-period, establishment (survival-period) and conservation (routine) maintenance, and the Beijing versus Hunan differences. Choosing the unit by plant class (count / length / area) is a separate question - this card fixes 'how many stages, from when, adjusted how'.

Core conclusions

Three non-overlapping stages - stage first, then quantity:

  1. Construction-period maintenance - from planting to completion acceptance, already inside the planting items, never listed again (GB/T 50858-2024 Table A.3.1 note 2; Hunan 2025: 'greenery maintenance does not apply to the planting construction period; maintenance before the planting unit works pass completion acceptance (construction-period maintenance) is inside the planting items').
  2. Establishment maintenance (survival period) - from planting completion to a set term after passing acceptance, consumption in 'months'.
  3. Conservation maintenance (routine) - after passing acceptance (or expiry of establishment) to keep plants growing normally, consumption in 'years'.

Beijing DB11/T 2382-2024 essentials:

  • Clause 8.2.28: 'Greenery maintenance from completion of planting (seasonal flowers apart) to passing completion acceptance runs on the establishment items, consumption in months; quantities: 1 trees, shrubs, climbers, standard plants and bamboos by design count; 2 hedges by design length; 3 lawns, flowers, colour bands, perennials and aquatics by design area.'
  • Clause 8.2.29: 'The establishment period runs from completion of planting; part months count as whole months; beyond one year the excess takes x 0.85.'
  • Clause 8.2.30: 'Maintenance after passing completion acceptance runs on the conservation items, consumption in years', quantities on the same three bases.
  • Clause 8.2.31: 'The conservation period runs from passing completion acceptance; its length per design or contract.'
  • Clause 8.2.32: seasonal flowers (annual, woody, perennial) placed as such take the seasonal-flower items, in months, by design area; 8.2.33: from planting / setting / potting; part months as whole months; length per design or contract.
  • Clause 8.2.27 (changed watering): 'Where the site has no water source or piped supply cannot meet watering, the water-bowser items apply; their consumption is set by planting method and plant size on three waterings, trued to actual counts; quantities by design count, length or area per plant class, size and age.'

Hunan 2025 essentials (differing from Beijing):

  • Greenery maintenance covers the establishment period and the routine maintenance from its expiry to handover acceptance, not the construction period (inside the planting items).
  • Establishment maintenance: within one year of the planting unit works passing acceptance - months 1-3 on the establishment items; months 4-12 the same items with labour-material-plant x 0.8; where acceptance is delayed without the contractor's fault, from the contractor's application date.
  • Beyond that year: routine maintenance on the routine items.
  • Both establishment and routine consider manual and bowser watering; automatic-irrigation green areas take the manual items with labour x 0.8.
  • Excluding major repairs beyond warranty to water and irrigation systems and structural safety facilities (charged when occurring).
  • Single and single-row tree maintenance in establishment suits isolated and aligned trees and plaza arrays; the street-tree routine items suit only aligned street trees outside continuous green areas - trees inside continuous greenery are in the general green-area maintenance items, never charged alone.
  • Not for precious trees or extra-large trees over 40cm dbh (charged on actuals); routine maintenance must reach at least local grade-3 green-area standard before charging.
  • Unit examples (items mostly '100 plants / month', '100 clumps / month', '1000m2 / month', '100m2 / month'): trees, palms, bamboos, ground cover, flowers, aquatics and lawns by their own objects; vertical greenery by the outer frame area. Work content: loosening, weeding, pruning and disbudding, watering and feeding, pest control, tree righting, clearing dead wood, cleaning, patrol.

Decision order: (1) planting items include construction-period maintenance - no extra charge; (2) before / after acceptance decides establishment versus conservation; (3) by plant type choose the object (count / length / area) - aquatics, lawns, flowers, colour bands and perennials always by area, hedges by length, trees, shrubs, climbers, standards and bamboos by count; (4) then adjust by term rules (part month as month, beyond one year x 0.85, Hunan months 4-12 x 0.8).

Applicable boundaries

  • The three stages are mutually exclusive: one period, one stage; construction-period maintenance inside planting items is never listed; establishment and conservation differ in start point and unit (month versus year) - never swapped or stacked.
  • Start points differ regionally: Beijing 'from completion of planting' (8.2.29); Hunan 'from the planting unit works passing acceptance' - state the version and basis with every maintenance claim, avoiding duplication or omission.
  • Factors apply only on their own conditions: beyond one year x 0.85 (Beijing); months 4-12 x 0.8 and irrigation labour x 0.8 (Hunan) - never cross-applied.
  • Charging has quality preconditions (Hunan: routine maintenance at least grade-3); precious and over-40cm trees never take routine items.
  • Seasonal-flower maintenance and bowser watering are special-case items - only in their contract / design situations, never double-charged against routine establishment maintenance.

Further reading

  • DB11/T 2382-2024 clauses 8.2.27~8.2.33; GB/T 50858-2024 Appendix A Table A.3.1 notes 2 and 6; Hunan 2025 greenery maintenance chapter notes and rules; CJJ 82 (survival rates and acceptance basis).

Keywords

  • 成活养护
  • 保存养护
  • 日常养护
  • 施工期养护
  • 绿化养护费
  • 养护期起算
  • 季节性花卉养护
  • 浇水车浇水