Pricing rules for materials without published price information: market price enquiry + pre-purchase price approval + order of determination in dispute appraisal
Materials without published price information are priced by market price enquiry: enquire with no fewer than 3 suppliers, compare, and take a representative price; submit to the employer for approval of the material price before purchase (silence within the agreed period constitutes deemed acceptance) and keep a ledger for the record; awarded contract prices for similar works in the same period, market prices adopted in the tender price ceiling, and industry price information may serve for cross-validation; in dispute appraisal, prices are determined in the order approved-and-signed price > contractually agreed price > mutually agreed price. Market prices, published price information, and manufacturer quotations must be used by classification and strictly never mixed.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.6.3条、8.4.5条、App. A.2.1、A.2.5
- GB/T 51262-2017 建设工程造价鉴定规范 第5.6.4条
- GB/T 50875-2013 工程造价术语标准 第2.1.16条
- T/ZBD 100.1-2022 建设工程造价数据建设通用标准 第7.2.3条
Topic Positioning
How to price materials not covered by published price information (unlisted, missing issues, or no matching specification): pricing methods, mandatory procedures, and the order of determination in dispute appraisal.
Core Conclusions
Materials without published price information are determined by "market price enquiry + pre-purchase price approval with records":
- Pricing: enquire with no fewer than 3 suppliers, compare, and take a representative transaction/quoted price as the market price and keep a ledger; where no market information exists, determine per the contractor's purchase unit price confirmed by both parties or the all-in unit rate analysis details of similar billed (BOQ) items (GB/T 50500-2024 Clause 8.6.3).
- Alternative references: awarded contract prices published by the trading centre for similar works under similar conditions within the same period (within 1 month), market prices adopted in the tender price ceiling, and industry price information (Appendix A.2.1).
- Approval procedure: before purchase the contractor shall submit the quantity and unit price to the employer for verification and confirmation; silence within the agreed period constitutes deemed acceptance (Appendix A.2.5) — submit for approval before purchasing; the signed material price confirmation is the pricing basis.
- Dispute appraisal: approved-and-signed price > contractually agreed price > mutually agreed price (GB/T 51262-2017 Clause 5.6.4); for provisional sum for specified materials not subject to mandatory tendering, replace with the pre-tax price after the employer's confirmation (Clause 8.4.5).
Applicable Boundaries
Applies where published price information is unlisted / missing issues / without matching specification; where published price information exists, it or the contractual agreement still prevails. Market prices, published price information, and manufacturer quotations must be three classified channels, strictly never mixed (T/ZBD 100.1-2022 Clause 7.2.3); published price information is a reference-guidance price. This card excludes the budget-price composition formula and price adjustment (for fluctuation) calculations.
Further Reading
GB/T 50500-2024 Clauses 8.6.3, 8.4.5 and Appendices A.2.1, A.2.5; GB/T 51262-2017 Clause 5.6.4; GB/T 50875-2013 Clause 2.1.16; T/ZBD 100.1-2022 Clause 7.2.3.