Pricing when design sizes exceed the top band of budget quota items (quota gap / over-range): over-range is a gap, not a conversion; proportional extrapolation is banned; four steps - express note, top band, borrowing similar-workmanship quotas, supplementary build-up for approval

Design sizes above the quota's top band are a quota gap, not a quota conversion: no linear extrapolation by diameter, section area or capacity, and no self-invented unfounded coefficients (review reads up-rating). Order: 1 check the volume / chapter notes for express over-range provisions and follow them (e.g. stated adjustment coefficients); 2 absent them, the top band is the ceiling - apply it and record the design difference honestly in the notes, no equivalent-quantity conversion or self-set coefficients; 3 borrow similar-workmanship quotas (cross-volume / discipline / region allowed), listing the borrowing basis, charging following the borrowed volume's rules; 4 compile a supplementary unit-rate build-up per quota compilation principles and submit for approval (GB/T 51095-2015 Article 5.3.12; DL/T 5468-2013 Article 4.1.4). Sizes below the bottom band likewise bar interpolation.

Applicable Codes

  • GB/T 51095-2015 建设工程造价咨询规范 第5.3.12条
  • DL/T 5468-2013 输变电工程施工图预算编制导则 第4.1.4条
  • TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程 册说明

Scope of the question

For budget / estimate compiling where the design size exceeds the top band (or falls below the bottom band) of the quota items in use - the correct pricing route, why extrapolation by diameter / size ratio fails, and why review reads it as up-rating.

Core conclusions

1. Characterisation: over-range = quota gap, not conversion. Item size bands (DN100 / 125 / 150 / 160 etc.) are measured per step; consumptions per band are measured values, bands not linearly related - as diameters grow, trench earthworks, thrust blocks, joints, testing and machine-shifts do not scale evenly. Extrapolating by 200/160 or by section or capacity ratio has no quota basis whatever - it invents an item without the supplementary-quota procedure, ungrounded and unapproved; review reads it directly as up-rating (taking the higher), a frequent deduction point. The reverse holds too: below the bottom band, no interpolation - take the bottom band or follow the notes. Conversions (coefficients, substitutions, content edits) stand only where the volume / chapter notes expressly authorise them.

2. The four-step order

  1. Check the volume / chapter notes first (priority one). Notes often carry over-range clauses - beyond X apply Y, apply another volume / discipline item, or multiply coefficient X under conditions. Express text binds; no improvisation. A compliant example: TB/T 10832-2024 Volume 11, chapter notes Chapter 3 - drainage pipe concrete bedding compiled on the 120-degree standard drawing base: 90-degree designs x 0.8; 180-degree x 1.2 (pipes under d600) or x 1.57 (d600 and above) - note-authorised coefficients are grounded adjustments (the same notes: outdoor pipe laying excludes pipe and fitting material costs, listed parenthetically, charged per design specifications and quantities).
  2. No express text: stay in-band, never extrapolate. The top band (say DN160) is the ceiling: apply it and record the design difference in the notes; converting DN200 into equivalent DN160 quantities or multiplying self-set coefficients is barred.
  3. Borrow similar-workmanship quotas. Cross-volume, cross-discipline and cross-region borrowing is allowed but must list the basis (which volume, which item, why similar) and follow the borrowed volume's charging - never volume A's prices with volume B's rates. Basis: DL/T 5468-2013 Article 4.1.4 - gaps take similar-workmanship quotas first; absent those, supplementary quotas from similar budgets or settlements; absent data, supplementary quotas per the project's technical conditions; where the quota's technical conditions differ materially, adjust the application per the project's conditions and the quota's provisions.
  4. Compile a supplementary unit-rate build-up and submit. Where nothing borrows, compile per quota principles with full labour, material and plant analysis and all-in rate analysis, and submit to the industry quota authority. Basis: GB/T 51095-2015 Article 5.3.12 - for budget-quota gaps, compile supplementary unit-rate build-up schedules per the budget quota's principles and methods; the commentary: at budget stage indicator methods are generally dropped, gaps taking supplementary build-ups for L-M-P analysis and rate build-up tables. Effectiveness rides on approval - DL/T 5468-2013 Article 4.1.4 paragraph 3: supplementary quotas shall conform to current quota administration and be approved by the power quota authority before use.

3. Records and numbering. Borrowed items note their source; supplementary quotas carry their own numbers; converted items carry a conversion mark; electronic data list quantity and consumption side by side.

4. The BOQ-pricing difference. Under BOQ pricing the tenderer quotes the all-in rate freely - over-range sizes may price via the company's own quota or market enquiry (market prices, consumptions adjusted from analogous quotas), never forcing public-quota extrapolation; the four steps apply to quota-priced budgets and estimates.

Applicability limits

  • Applies to quota-priced budget / estimate compiling and review where design sizes exceed the volume's top (or fall below the bottom) band, or technical conditions differ materially from the quota's.
  • Precondition: the volume / chapter notes are confirmed to lack express over-range provisions; once present (dedicated clauses or authorised coefficients), they bind, not the top band.
  • Contents already comprehensively included (water pipe laying including testing, disinfection and flushing; drainage laying including watertightness test water) are not adjustable or re-chargeable for differing practice.
  • Supplementary quotas need conformity with current quota administration and approval / copying to the industry authority - authorities differ by industry.
  • This card is a general method; band steps, coefficients and approval requirements follow the executed volume's notes and the industry's quota administration.

Further reading

  • GB/T 51095-2015 Article 5.3.12 and commentary (supplementary build-ups at design stage).
  • DL/T 5468-2013 Guide for Compiling Construction-Drawing Budgets of Power Transmission and Transformation Works, Article 4.1.4 (adjustment, borrowing, supplementation, approval).
  • TB/T 10832-2024 Volume 11 chapter notes Chapter 3 outdoor pipe laying (bedding-angle coefficients 0.8 / 1.2 / 1.57, parenthetical material consumptions, indoor-outdoor boundaries).
  • The only lawful adjustment channel is the volumes' own clauses (beyond X apply Y, coefficient X, another volume's item); keep borrowing and supplementing marked and numbered.