Choosing the format of the all-in unit rate analysis sheet, its mandatory preparation requirements, and its roles across tendering, settlement and audit (GB/T 50500-2024 Appendix E, tables E.2.2-1 and E.2.2-2)
GB/T 50500-2024 Appendix E provides that detailed all-in unit rate analysis shall follow table E.2.2-1 and simplified analysis table E.2.2-2, the choice being fixed by the tender requirements and the contract; the rates in the analysis sheet and the prices of lump-priced items must be 'completely consistent' with the corresponding figures in the BOQ (clause 3.1.7); at tender the sheet, together with tables E.3.2, E.3.3 (which must list initial set-up, mid-term operation and final dismantling costs) and E.3.4, must be submitted in full, consistent with the priced BOQ (clauses 6.2.12 and 6.2.13). The all-in unit rate carries risk costs within the agreed scope and bands and excludes VAT (clauses 2.0.9 and 3.2.2), so the risk allowance sits inside the rate build-up rather than as a stand-alone charge. At settlement, clause 3.1.6 requires item-by-item checking that rates match the priced BOQ in the contract, with no adjustment except for variations and agreed matters; dayworks and additional works may draw on 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items' (clause 8.6.3; cost expert assessment guideline clause 4.8.4); audit examines whether new rate build-ups follow the quota pricing rules agreed in the contract, whether every line-item price is fixed, and whether common material prices are reasonable.
Applicable Codes
- GB/T 50500-2024 第2.0.9条
- GB/T 50500-2024 第3.1.7条
- GB/T 50500-2024 第3.2.2条
- GB/T 50500-2024 第6.2.12条
- GB/T 50500-2024 第6.2.13条
- GB/T 50500-2024 第8.6.3条
- GB/T 50500-2024 第8.9.1条
- GB/T 50500-2024 第12.1.5条
- GB/T 50500-2024 App. E Table E.2.2-1、Table E.2.2-2、Table E.3.2、Table E.3.3、Table E.3.4
- T/ZBD 100.5-2023 第3.1.6条、第5.0.13条
- T/ZBD 100.4-2023 第4.8.4条
- DBJ/T 15-145-2018 第6.1.4条
- 国税发〔1999〕90号 第八条
- 《关于审查建设工程预算管理暂行办法》第十三条
Scope and purpose
This card covers the all-in unit rate analysis sheet in Appendix E of GB/T 50500-2024, the China national pricing standard for BOQ (table E.2.2-1 detailed, table E.2.2-2 simplified): how the format is chosen, what hard requirements govern preparation and consistency, and what function the sheet serves in tender pricing, settlement tracing, and audit or expert assessment; it also gives the rounding basis of the all-in unit rate and the rules for fixing rates on variation.
Core conclusions
I. Choice of format (when simplified preparation is allowed) Appendix E table E.2.2, original text: 'According to the tender requirements of the works and the contract, where the divisional and sub-divisional works BOQ adopts detailed all-in unit rate analysis, the provisions of table E.2.2-1 shall be followed; where it adopts simplified all-in unit rate analysis, the provisions of table E.2.2-2 shall be followed.' That is, whether the simplified format may be used is decided by the tender requirements and the contract, not by the bidder's own preference; the exact columns and row order follow the original tables of Appendix E (the clause text merely cites them and enumerates no columns here).
II. Consistency is the highest-priority hard constraint
- Clause 3.1.7: 'The all-in unit rate analysis sheet shall make clear the cost make-up calculation method of each BOQ item's all-in unit rate and of each lump-priced item's price, and those rates and prices shall be completely consistent with the corresponding BOQ item all-in unit rates and prices in the bill of quantities. The analysis sheet shall explain the cost make-up of each BOQ item's all-in unit rate and lump-priced item price.'
- Clause 6.2.12: 'bidders shall, when submitting tender documents, submit in full the cost make-up detail sheets consistent with the all-in unit rates and prices in the priced BOQ'; the relevant sheets shall follow Appendix E's table E.2.2-1 or table E.2.2-2, table E.3.2 (make-up detail analysis of the preliminaries BOQ), table E.3.3 (breakdown of preliminaries costs) and table E.3.4 (make-up detail of large plant entry/exit and erection/dismantling costs).
- Clause 6.2.13: the four sheets shall be tendered together, and table E.3.3 shall list each preliminaries item's initial set-up cost, mid-term operation cost and final dismantling cost, for use after award in progress payment and claims pricing.
- Clause 12.1.5: bidders shall attach the BOQ all-in unit rate analysis sheets as required by the tender documents, to ease pricing during contract performance.
III. Cost scope (decides whether there is a stand-alone 'risk' line, and the tax treatment)
- Clause 2.0.9, all-in unit rate: 'the cost of completing one unit quantity of a BOQ item after comprehensively allowing for technical standards and codes, construction period, construction sequence, construction conditions, geography and climate, and risks within the agreed scope and bands. The all-in unit rate of a BOQ item includes labour cost, material cost, plant and small tools cost, overheads, profit and risk costs within a defined range, and excludes value added tax.'
- Clause 3.2.2: the all-in unit rate of divisional and sub-divisional BOQ items shall be a material procurement and related installation rate excluding VAT; item 5 expressly includes 'risk costs within the scope and bands agreed in the contract and fixed in clause 3.3 of this standard'; the same clause also lists the costs of meeting national and sector technical standards and codes, the cost of BOQ errors under lump-sum contracts, the costs of construction tasks indispensable for completion and delivery plus indispensable ancillary works, and the costs of construction sequence, construction conditions and climate effects. => Practical meaning: the risk cost is a component merged into the all-in unit rate; the standard does not set it up as a stand-alone charging line; VAT is a price-exclusive tax and does not enter the sheet. Overheads and profit must be shown so that rate and amount share one visible source and can be recomputed - that is the substance of clause 3.1.7's 'make clear the cost make-up calculation method'.
IV. Roles across the three stages
- Tender = explanation of the price make-up: submit cost detail fully consistent with the priced BOQ (3.1.7, 6.2.12); after award it becomes the rate basis of the contract prices; on the preliminaries side tables E.3.2/E.3.3/E.3.4 are tendered at the same time.
- Settlement = tracing the rate basis: T/ZBD 100.5-2023 clause 3.1.6 item 2: for the all-in unit rates within the contract BOQ at settlement, check item by item whether they match the priced BOQ in the contract; where variation changes priced BOQ items, adjust under the relevant provisions of the current national standard; save as the contract provides otherwise, no other adjustment is allowed. Where dayworks have no applicable rate, they may be priced from 'the detailed price make-up in the all-in unit rate analysis sheet of similar BOQ items in the contract BOQ' and the like (GB/T 50500-2024 clause 8.6.3) - the analysis sheet is the conversion basis for pricing dayworks and additional works.
- Audit / deliverable review = checking consumption and charging reasonableness: T/ZBD 100.5-2023 clause 5.0.13 approval points include 'whether the build-up of each new BOQ price follows the quota pricing rules agreed in the contract; whether the price of every line item has been fixed', 'whether common material prices in new build-ups are reasonable', and 'whether principal indicators are normal (rebar content, concrete content and the like)'. The sector review basis is the same: Guo Shui Fa [1999] No. 90, article 8, lists among audit report content 'whether quantity calculation, the application, conversion and charging of quota items and rates are correct and reasonable and follow the contract'; the Interim Measures for Review of Construction Budgets, article 13, lists 'whether quantity calculation and the application, conversion and charges of quota items are accurate' and 'whether the calculation of material price differentials is reasonable'.
- Cost expert assessment: T/ZBD 100.4-2023 clause 4.8.4 - where the original contract was priced on a BOQ basis, the assessor shall analyse on the basis of the originally applicable divisional and sub-divisional all-in unit rates and, on the facts and evidence, reasonably compute the various preliminaries costs arising from additional works; where a party claims adjustment of element consumption or rate levels in the analysis sheet, the assessor shall weigh the work quantities behind the original contract rates against the scale of the additional works, analyse the need and reasonableness of the adjustment and explain it.
V. Rate build-up (quota line items) and conversion requirements
- The all-in unit rate formula (local data-standard basis): P = Sum(Tn) / Q. P rounded to 2 decimal places; Tn is the total price of each quota line item applied under the BOQ item, computed at full precision (decimal places not rounded); Q is the BOQ item quantity, rounded to 3 decimal places (DBJ/T 15-145-2018 clause 6.1.4).
- Rates fixed for variation/BOQ errors (GB/T 50500-2024 clause 8.9.1; unit-rate contracts, item additions/deletions or quantity changes up to 15%, 15% inclusive): (1) same item description under the same construction conditions - adopt the corresponding contract rate; (2) similar item descriptions under the same conditions, or the same item description under similar conditions - adopt the all-in rate converted and adjusted from the contract rate of a similar BOQ item; (3) different item descriptions under the same conditions, or the same item description under different conditions - negotiate a market-reasonable all-in rate with reference to the pricing rules of similar items and the bid level; (4) different item descriptions under different conditions - negotiate with reference to the all-in unit rates of similar BOQ items in comparable works; (5) reductions or cancellations that materially change construction conditions - negotiate per actual execution, market prices, the contract pricing rules and the bid level. Price-influencing factors fall into two classes: item-description factors (material changes, construction method changes, effects on other divisional and sub-divisional items) and construction-condition factors (foundations, working heights, member sizes, construction season, protection of completed areas, site access restrictions, material transport modes, plant usage, coordination fees within the main contractor's attendance provisions, etc.). => A sheet 'traceable to the quota line items and their conversions (conversion marks left on record)' is the precondition of a reviewable build-up; what approval/review checks is precisely whether the build-up follows the quota pricing rules agreed in the contract and whether every line-item price is fixed.
Applicability limits
- This card rests on GB/T 50500-2024, the current edition replacing GB 50500-2013 (formerly titled Code for Valuation with Bill of Quantities of Construction Works); whether old columns such as 'quota number / quota name / quota unit' survive must be checked against the original tables of the new Appendix E - never format from memory of the old edition.
- The all-in unit rate here excludes VAT and suits general building and municipal BOQ pricing; highways, railways and other sectors use fully inclusive or partly inclusive bases, and cross-sector use needs conversion.
- The simplified sheet (E.2.2-2) may be used only where the tender requirements and the contract allow; it must not replace a required detailed analysis, nor does the analysis sheet replace the priced BOQ itself.
- The 15% line in clause 8.9.1 addresses quantity changes under unit-rate contracts only; adjustments beyond it follow chapter 7 of the standard.
- DBJ/T 15-145-2018's rounding rules (2 decimals / 3 decimals) apply only within its own administrative region.
- This card does not enumerate the columns of tables E.2.2-1/E.2.2-2 (the clause text cites them only); column names and order follow the original tables of Appendix E.
Further reading
- GB/T 50500-2024: clause 2.0.9 (term: all-in unit rate), 3.1.7 (analysis-sheet consistency), 3.2.2 (rate content and risk costs), 6.2.12 and 6.2.13 (sheets tendered), 8.6.3 (dayworks rates), 8.9.1 (rates on variation/BOQ errors), 12.1.5 (pricing deliverables and records), Appendix E tables E.2.2-1, E.2.2-2, E.3.2, E.3.3, E.3.4.
- T/ZBD 100.5-2023, Work Guideline for Final Account Review of Construction Projects, clauses 3.1.6 (fixed-rate settlement review) and 5.0.13 (approval work content and review record sheet).
- T/ZBD 100.4-2023, Work Guideline for Construction Cost Expert Assessment, clause 4.8.4 (assessment method for additional works).
- DBJ/T 15-145-2018, Cost Data Standard for Government-Invested Construction Projects, clause 6.1.4 (rate formula and rounding).
- Guo Shui Fa [1999] No. 90, Audit Provisions for Capital Projects of the State Taxation System, article 8 (audit report content); Interim Measures for Review of Construction Budgets, article 13 (review content).
Keywords
- 综合单价分析表
- 表E.2.2-1
- 表E.2.2-2
- 已标价工程量清单
- 费用构成明细表
- 措施项目费用分拆表
- 定额子目组价
- all-in unit rate