Determining missing items not listed in the BOQ appendices and setting supplementary items: the three-element comparison search path, the discipline-code + B coding rule (from 01B001), the five required accompanying elements, the tender-document explanation / filing requirements, and the boundary of error when fitting near-match items
Under GB/T 50854-2024 Clause 4.1.4, for items not covered in Appendices A~R the compiler may add supplementary items, coded with this standard's code 01 plus B and three Arabic numerals, numbered sequentially from 01B001, and must attach the item name, item description, unit of measurement, quantity take-off rule and work content (for preliminaries that cannot be measured: name, work content and scope of inclusion). The determination is a three-element comparison (item description + work content + unit of measurement with calculation rule): so long as any element can be carried by an existing appendix item, the existing item must be applied forward and the difference expressed in the item description, and no supplementary code may be created; work content lists only principal operations, auxiliary content such as plant movement and material transport is deemed included, and operations may not be split out and listed separately unless specifically stated. The 2024 editions (GB/T series) say 'may add' and no longer require filing; instead GB/T 50500-2024 Clause 3.1.3 requires the supplementary basis to be explained in the tender and contract documents; the 2013 compulsory national standards required 'shall add + file with the provincial or industry construction cost administration institution', and local standards may still retain the filing requirement.
Applicable Codes
- GB/T 50854-2024 第4.1.4条(补充项目编码与应附要素)
- GB/T 50854-2024 第4.1.2条(项目特征描述与工作内容默示包含)
- GB/T 50854-2024 第4.1.3条(场内运输与材料供应已包括)
- GB/T 50854-2024 第4.2.2条(十二位项目编码设置规则)
- GB/T 50854-2024 第4.2.5条(计量单位按附录确定)
- GB/T 50854-2024 第3.0.3条(工程量汇总有效位数)
- GB/T 50500-2024 第3.1.3条(补充完善须在招标文件和合同文件说明)
- GB/T 50500-2024 第4.1.4条、第4.1.6条(单价/总价合同清单缺陷责任)
- GB/T 50500-2024 第2.0.27条(工程量清单缺陷定义)
- GB/T 50500-2024 第8.9.1条(变更或缺陷引起综合单价调整)
- GB 50860-2013 第4.1.3条(07B001编码、报省级或行业造价管理机构备案)
- GB 50860-2013 第4.2.4条(项目特征描述原则)
- DB11/T 638-2016 第4.1.4条(AB001/BB001/CB001编码与地方备案)
- T/ZBD 100.4-2023 第4.4.4条(项目特征不符与工程量偏差的综合单价调整)
Scope and purpose
This card deals with missing-item determination at the BOQ itemisation level: when no substantially matching item exists in the appendices of the quantity take-off standard, whether a supplementary item must or may be set, how its code is written, how the five elements (name / item description / unit of measurement / calculation rule / work content) are self-specified, the basis for explaining them in tender documents and for filing, and the boundary at which fitting a near-match item becomes an error. It does not cover pricing-level supplementary quota items (supplementary unit-rate build-up schedules).
Key conclusions
1. Conditions for determination and clause basis (GB/T 50854-2024 Clause 4.1.4, verbatim) 'When compiling the bill of quantities, if items not covered by Appendices A~R of this standard arise, the compiler may add supplementary items, which shall comply with the following: 1. The code of a supplementary item consists of this standard's code 01 together with B and three Arabic numerals, and shall be numbered sequentially from 01B001. 2. The supplementary bill of quantities shall attach the item name, item description, unit of measurement, quantity take-off rule and work content of the supplementary item. For preliminaries that cannot be measured, the item name, work content and scope of inclusion of the supplementary item shall be attached.' The commentary adds: new materials, technologies and processes keep emerging and the appendix items cannot cover everything; supplementary items shall attach the item coding, item name, item description, unit of measurement, quantity take-off rule and work content for work items, and the item coding, item name and work content for the bill of preliminaries.
2. The determination is in substance a three-element comparison, not a name comparison The three elements are: item description + work content (including implied auxiliary content) + unit of measurement and quantity take-off rule. If any element can be carried by an existing appendix item, the only route is 'apply the existing code forward + express the difference in the item description', and no supplementary code may be created. Only where 'no appendix item substantially corresponds and no existing item's work content can cover the operation' is the item judged missing and a supplementary item set. Where only the name fails to match but the work content covers it, the item merges into the existing one - not listed separately, not split.
3. Search path (five steps across three layers of text)
- Locate the discipline code and appendix classification: digits 1-2 are the discipline code (01 building and decoration works; 02 historic-style building works; 03 general installation works; 04 municipal works; 05 landscape and greening works; 06 mining works; 07 structures; 08 urban rail transit; 09 blasting works), digits 3-4 the appendix classification sequence code, digits 5-6 the sub-divisional works sequence code, digits 7-9 the work item name sequence code, and digits 10-12 the BOQ item name sequence code.
- The appendix item tables themselves: do not read the item name alone - read the item description column and the work content column on the same row; the work content column lists the principal operations and is the main basis for judging whether the item can carry the work.
- The include/exclude boundaries in the appendix or division notes (exclusion clauses): content expressly excluded must not be forced into the item, nor listed as a supplement for that reason - first check the other item that the exclusion points to.
- Catch-all interpretation clauses (whether unlisted content is deemed included; GB/T 50854-2024 Clauses 4.1.2 and 4.1.3, verbatim):
- Clause 4.1.2: 'The work content of items in Appendices A~R of this standard lists only the principal content; unless otherwise provided or stated, it shall be deemed to include the necessary work for completing the BOQ item.' 'The work content in the appendices of this standard lists only the principal construction content; auxiliary content inevitably arising during construction, such as plant movement and material transport, is included even though not listed. Construction operations corresponding to work content shall not be split and separately listed unless specially stated.'
- Clause 4.1.3: 'For BOQ items in Appendices A~R of this standard, unless otherwise stated, the work content includes the on-site transport of materials (semi-finished, finished), members or equipment.' 'Whether the BOQ is for manufacture-and-install or for installation only, unless specially stated, it shall include the supply and on-site transport of materials (semi-finished, finished), members or equipment.'
- No coverage at any of the four layers - judge the item missing and set a supplementary item.
4. Coding rules
- Supplementary items: discipline code + B + three Arabic numerals, numbered from 01B001 sequentially (building and decoration works, GB/T 50854-2024 Clause 4.1.4); structures works from 07B001 (GB 50860-2013 Clause 4.1.3); local refurbishment standards use the discipline appendix code A, B or C together with B and three numerals, numbered from AB001, BB001, CB001 (DB11/T 638-2016 Clause 4.1.4). All require that items within the same tendered works carry no duplicate codes.
- Ordinary BOQ coding is separate: GB/T 50854-2024 Clause 4.2.2 'The item code of the bill of quantities shall be expressed in twelve Arabic numerals; digits one to nine shall be set per the appendices, digits ten to twelve per the BOQ item names and item descriptions of the proposed works, and item codes within the same individual project of the same tendered works shall not duplicate. Where the same individual project contains several unit works and each unit work is a compilation object, digits ten to twelve shall not duplicate - for example, solid brick wall masonry with identical item description in three unit works is coded 010401002001, 010401002002 and 010401002003.'
5. Self-specification of the five elements (by reference to the nearest appendix item)
- Item name: named from the nearest appendix item plus qualifying process or material features, consistent with the terminology of the measurement standard.
- Item description: described item by item following the description columns of the nearest appendix item, combined with the actual proposed works, to the standard of 'standard, concise, accurate and complete' and sufficient for determining the all-in unit rate (Clause 4.1.2); where a standard drawing album or the construction drawings can meet the description requirement, the form 'see drawing album XX / drawing no. XX' may be used, and the parts that cannot be met are still described in words.
- Unit of measurement: for existing appendix items, per the units prescribed in Appendices A~Q (Clause 4.2.5); for supplementary items, follow the unit basis of the nearest item and match the calculation rule (no mismatch of unit against rule, e.g. measured by area yet calculated by volume rules).
- Quantity take-off rule: carry over the established rules and the basis of the nearest item, making clear the deduction boundaries, the dimension basis (dimensions shown on the design drawings) and whether ancillary quantities merge in; rounding of summaries per Clause 3.0.3 - three decimals for 't' (fourth rounded), two decimals for 'm', 'm2' and 'm3' (third rounded), integers for counting units such as pieces, roots, sets, bays and frames.
- Work content: extended from the nearest item's work content plus the implied inclusions of Clauses 4.1.2 and 4.1.3 (plant movement, material transport, on-site transport, supply of finished and semi-finished products); already-included auxiliary content must not be listed separately.
6. Explanation in tender documents and filing (divergent validity bases)
- 2024 edition: GB/T 50500-2024 Clause 3.1.3 'BOQ items shall be compiled per the design drawings, the technical standards, the relevant national and industry quantity take-off standards and Chapter 4 of this standard. Where the bill of quantities is supplemented or completed for the characteristics of the project, measurement methods separately agreed, or other BOQ forms adopted, the quantity take-off rules, units of measurement, scope of application and work content shall be explained in the tender and contract documents. For tendered works where, due to design or construction needs, the bill of quantities must be supplemented or completed, take-off rules separately agreed or other BOQ forms adopted, the tender documents (for non-tendered works, the enquiry documents) shall explain the quantity take-off rules, units of measurement and work content.' - the clause no longer requires supplementary items to be filed with cost administration institutions.
- 2013 compulsory national standard: GB 50860-2013 Clause 4.1.3 'Where items not covered by the appendices arise in compiling the bill of quantities, the compiler shall add supplementary items and file them with the provincial or industry construction cost administration institution, and the provincial or industry construction cost administration institution shall summarise and report to the Standards and Quota Institute of the Ministry of Housing and Urban-Rural Development.' (the basis is 'shall add' + filing)
- Local standards may retain filing: DB11/T 638-2016 Clause 4.1.4 'file the compiled supplementary items with the municipal construction cost administration institution'. Take the basis from the standard edition applicable to the project: compiling the BOQ under the 2024 edition but omitting the tender-document explanation, or following the 2013 basis but omitting the filing, is a procedural defect either way.
7. When fitting a near-match item goes wrong Three situations establish a mis-fit: (a) the unit of measurement or calculation rule basis differs yet the item is forced on (distorted quantity basis); (b) the item-description difference cannot be expressed by description, so the all-in unit rate cannot be determined from it (the difference materially affects the rate build-up); (c) no existing item's work content covers the operation, and the gap is patched by splitting operations into separately listed items (double counting / omissions). Conversely, a near name with consistent work content and measurement rules, and differences expressible in the item description, is legitimate fitting, not mis-fitting. Liability and adjustment after a mis-fit: GB/T 50500-2024 Clause 2.0.27 defines 'defects in the bill of quantities' as 'differences between the items listed in the work item list of the bill of quantities and the items required by the corresponding contract drawings and contract specifications, in item listing, item description or quantities, including over-listed items, erroneous or omitted items, non-matching item descriptions, quantity deviations and other like cases.' Liability splits by contract type. Lump-sum: 'where a tender BOQ compiled by the employer from the actual circumstances of the works is applied to a lump-sum contract, its items and quantities shall be deemed to conform to the tender drawings and technical standards; where defects in the bill of quantities exist, the contractor bears the responsibility of supplementing and completing them' (Clause 4.1.4); 'for a bill of quantities under a lump-sum contract, where defects in the bill of quantities exist, the price changes they cause shall be deemed included in the contract price and not adjusted during performance; but BOQ items and quantities stated in the work item list as provisional quantities shall be re-measured and determined under the unit-rate pricing rules of this standard' (Clause 4.1.6). Unit-rate: 'where defects exist in the work item list, the employer shall bear the liability for the defects, and the defects in the bill of quantities shall be adjusted under Section 8.2 of this standard' (Clause 4.1.4). For unit-rate contracts, where items increase or decrease due to variations or BOQ defects, or quantities change by no more than 15% (15% included), the all-in unit rate is set under the five tiers of Clause 8.9.1: identical construction conditions + identical item description, use the contract rate; identical conditions + similar description, or similar conditions + identical description, use the similar item's contract rate converted and adjusted; identical conditions + different description, or different conditions + identical description, negotiate by reference to the pricing rules and tendered rate levels of similar items; different conditions + different description, negotiate by reference to the all-in unit rates of similar BOQ items in comparable works; where a reduction or cancellation of items significantly changes the construction conditions, negotiate from the actual circumstances, market prices, the contractual pricing rules and the tendered rate levels.
Applicability boundaries
- Applies to item listing and supplementary items when compiling tender BOQs under the national quantity take-off standards (building and decoration; historic-style building; general installation; municipal; landscape and greening; mining; structures; urban rail transit; blasting); the supplementary code prefix varies with the discipline code (01Bxxx for buildings, 07Bxxx for structures) and must not be uniformly written as 01B.
- Take the basis from the standard edition applicable to the project: GB/T 50854-2024 and GB/T 50500-2024 are recommendatory ('may add'), while the 2013 measurement standards were compulsory national standards ('shall add' + filing); clause numbers must not be mixed across editions.
- This card resolves only whether to set a supplementary item at listing level; pricing-level items missing from the quota manuals require supplementary quota items (supplementary unit-rate build-up schedules) approved by the industry quota administration institution - a separate route not to be conflated with this one.
- A supplementary item is not a channel around the appendix calculation rules: where the work content covers the work, no supplementary item may be created, nor may a supplementary item be used to split operations into separate listings for double counting; only preliminaries that cannot be measured use the simplified elements 'name + work content + scope of inclusion'.
- The liability conclusions on contract price adjustment presuppose the contract type (unit-rate / lump-sum), the contract documents and the pricing standard clauses actually applicable to the project; non-tendered works follow the explanation in the enquiry documents.
Further reading
GB/T 50854-2024 Clause 3.0.3 (rounding of summaries), 4.1.2 (item description and implied work content), 4.1.3 (on-site transport and supply), 4.1.4 (supplementary items), 4.2.2 (twelve-digit coding), 4.2.5 (units of measurement), plus the include/exclude boundary clauses in the appendices and division notes from Chapter 5 on; GB/T 50500-2024 Clause 3.1.3 (supplementation explained in tender/contract documents), 4.1.4 and 4.1.6 (BOQ defect liability under lump-sum/unit-rate contracts), 2.0.27 (definition of defects in the bill of quantities), Section 8.2 (defect adjustment), 8.9.1 (five-tier all-in unit rate rule); GB 50860-2013 Clause 4.1.3 (07B001 coding + filing with the provincial or industry cost administration institution), 4.2.4 (item description principles, including the 'see drawing album / drawing no.' method); DB11/T 638-2016 Clause 4.1.4 (AB001/BB001/CB001 and local filing); T/ZBD 100.4-2023 Clause 4.4.4 (adjustment of all-in unit rates for non-matching item descriptions and quantity deviations in construction cost expert assessment).