Item description vs method of measurement in the BOQ: the item description column must not stipulate the method of measurement; supplementary rules belong in the BOQ calculation-rules statement and apply as contractual agreement
Item description and method of measurement are two parallel, independent elements of the bill of quantities (BOQ): the item description must be drafted in accordance with the annexes to the measurement standard and the actual works, its function being to fix the all-in unit rate; quantities must be computed under the method of measurement prescribed in the annexes (mandatory provisions of codes) — the item description column must not stipulate the method of measurement. Where supplementary rules are genuinely required, they must be set out in the BOQ calculation-rules statement (naming the national and industry standards adopted, with their titles and numbers, or setting out the detailed supplementary rules) and made part of the tender documents/contract documents, applying as "contractual agreement". Hierarchy of measurement bases: contractual agreement -> national standard matching the contract type -> industry/local standard.
Applicable Codes
- GB 50860-2013 · Code for Measurement of Quantities of Structures Works 第4.2.1、4.2.4、4.2.5条(强制性条文)
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第4.2.6条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第4.1.7条、第7.1.1条、App. D D.4.1
- T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.3.1条
- GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.5.1条
- GB/T 50875-2013 · Standard glossary of project costs 第2.1.14条
Topic Positioning
This card answers a common question in BOQ preparation and measurement disputes: may the method of measurement be stipulated directly in the item description of a BOQ? The conclusion is: item description and method of measurement are two parallel, independent elements of the BOQ; the item description column is not the place to write measurement rules; where supplementary rules are genuinely required, their legally prescribed location is the "BOQ calculation-rules statement (preparation notes)", which must be made part of the tender documents/contract documents and applies as "contractual agreement".
Core Conclusions
1. Item description and method of measurement stand apart, each with its own source
The five elements of a work-section BOQ. GB 50860-2013, clause 4.2.1 (mandatory provisions of codes): "A bill of quantities shall be prepared in accordance with the item codes, item names, item descriptions, units of measurement and method of measurement prescribed in the annexes." The commentary makes clear: the five elements constituting a work-section BOQ — item code, item name, item description, unit of measurement and quantity — "are indispensable to the composition of a work-section BOQ".
Function and drafting requirements of the item description. GB 50860-2013, clause 4.2.4 (mandatory provisions of codes): "The item description in a bill of quantities shall be drafted in accordance with the item descriptions prescribed in the annexes, combined with the actual circumstances of the proposed works." Commentary: the item description is "an indispensable and important basis for fixing the all-in unit rate of a billed item" and must be accurate and complete; drafting principles: (1) the content shall follow the annexes, combined with the actual works, and be sufficient to fix the all-in unit rate; (2) where a standard atlas or the construction drawings fully or partly satisfy the description requirements, reference may be made directly to atlas No. ×× or drawing No. ××, and any part not so satisfied shall still be described in words. GB/T 50875-2013, clause 2.1.14 defines: "Item of Description: the essential features constituting the value of a work-section item or preliminary item."
Source of the method of measurement. GB 50860-2013, clause 4.2.5 (mandatory provisions of codes): "Quantities listed in a bill of quantities shall be computed in accordance with the method of measurement prescribed in the annexes." GB/T 50854-2024, clause 4.2.6: "Quantities listed in a bill of quantities shall be computed in accordance with the method of measurement prescribed in Annexes A to Q of this standard." In other words, the legally prescribed carrier of the method of measurement is the annexes to the measurement standard, not the item description column.
2. The lawful path where a special measurement basis must be agreed: calculation-rules statement + contractual agreement
- GB/T 50500-2024, clause 7.1.1: "Contract works shall be measured as the works completed by the contractor in accordance with the contract requirements and due to be measured. Quantities shall be computed in accordance with the national and industry quantity calculation standards for the relevant works agreed by the employer and the contractor, together with any supplementary method of measurement."
- GB/T 50500-2024, Annex D, clause D.4.1 (BOQ calculation-rules statement), table note: "Where national and industry quantity calculation standards are adopted, the titles and numbers of the corresponding national and industry standards shall be specified; where the calculation rules are supplemented and refined in light of the characteristics of the works, the detailed calculation rules for the bill of quantities shall be set out." — supplementary rules go into the "calculation-rules statement", not the item description column.
- GB/T 50500-2024, clause 4.1.7: whether a re-measurable (unit-rate) contract or a lump-sum contract is adopted, the item codes, item names, item descriptions, units of measurement and work contents of the work-section BOQ shall be prepared in accordance with the national and industry quantity calculation standards and the supplementary BOQ calculation rules; the item codes, item names and work contents of the bill of preliminaries shall be prepared in accordance with the national and industry quantity calculation standards; where the item description cannot be drafted for the bill of preliminaries or the bill of provisional sums and other charges, the work contents and item names may be listed.
3. Hierarchy of measurement bases (contractual agreement takes precedence)
- T/ZBD 100.4-2023, clause 4.3.1: "Where the parties have expressly agreed the method of measurement in the contract, the expert shall measure the works in accordance with the method of measurement agreed in the contract. Where the parties have not expressly agreed the method of measurement in the contract, the expert shall measure the works in accordance with the corresponding measurement standard issued as a national standard matching the contract type; where no national standard provides for it, measurement shall be in accordance with the corresponding method of measurement in the current industry or local standard." (The commentary to this clause gives an example: in a dispute over the gross floor area (GFA) calculation rules, the contract type must first be determined — construction contracts follow GB/T 50353, and real-estate sale contracts follow GB/T 17986.)
- GB/T 51262-2017, clause 5.5.1: "Where the drawings of the subject of the expert assessment are complete and the parties dispute the measurement basis, the expert shall measure in accordance with the method of measurement prescribed in the current relevant national measurement standard; where there is no national standard, measurement shall be in accordance with the industry or local standard. This does not apply where the parties have agreed measurement rules in the contract."
4. Why it should not be written into the item description column
- The description is confined to the characteristics prescribed in the annexes and is required to be "standard, concise, accurate and complete", its function being to fix the all-in unit rate; rule wording is not a "characteristic", and where it conflicts with the standard annexes it does not automatically have the effect of excluding the application of the standard;
- An incomplete item description constitutes "errors and omissions in the BOQ", whose risk is allocated under GB/T 50500-2024 (under a re-measurable (unit-rate) contract the employer bears it, and the all-in unit rate is re-rated and the contract price adjusted according to the actual characteristics; under a lump-sum contract the contractor bears it); stuffing calculation rules into the description column readily gives rise to disputes over "mismatch of item description / BOQ errors or omissions";
- The only acceptable exception: where the standard annex itself requires a measurement basis to be clarified in conjunction with the characteristics, a clarifying statement consistent with the standard may be included in the description, but it must not contradict the rules in the annexes to the calculation standard.
Applicable Boundaries
- Applies to the preparation of the bill of quantities, tendering, settlement and construction cost expert assessment (judicial appraisal) for building and decoration works, structures and similar construction works; the core bases are GB 50860-2013, GB/T 50854-2024 and GB/T 50500-2024.
- The "contractual agreement takes precedence" hierarchy applies to the resolution of disputes over the measurement basis; a contractual agreement must not violate mandatory provisions of laws and regulations, nor depart from the substantive content of the tender documents.
- In construction cost expert assessment (judicial appraisal), the contract type (construction contract / real-estate sale contract, etc.) must first be determined before the applicable standard is chosen.
- This card does not address the numerical computation of quantities for specific work sections; for the detailed calculation rules, see the corresponding items in the annexes to each measurement standard.
Further Reading
- GB 50860-2013, Standard for measurement of structures, Chapter 4 "Preparation of the bill of quantities", clauses 4.2.1, 4.2.4 and 4.2.5 and their commentary;
- GB/T 50854-2024, Standard for measurement of building and decoration works, clause 4.2.6 and Annexes A to Q;
- GB/T 50500-2024, China national pricing standard for BOQ, clauses 4.1.7 and 7.1.1, and Annex D (D.4.1 BOQ calculation-rules statement);
- T/ZBD 100.4-2023, Guidelines for construction cost expert assessment practice, clause 4.3.1;
- GB/T 51262-2017, Code for construction cost expert assessment, clause 5.5.1;
- GB/T 50875-2013, Standard for construction cost terminology, clause 2.1.14.