Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-18

The twelve-digit rule for BOQ item codes: digits 1-9 unified per the appendices, digits 10-12 set by the compiler, the 01B supplementary code for gaps, the duplicate-check scope, and 2013 versus 2024 differences

BOQ item codes are twelve Arabic digits in five levels: discipline code (1-2), appendix class code (3-4), section code (5-6), work-item code (7-9), item-name code (10-12). Digits 1-9 must follow the appendices (national, no self-coding); 10-12 are set by the compiler from the item name and item description and may not duplicate within the same tendered works (GB 50854-2013 clause 4.2.2, mandatory; GB/T 50854-2024 clause 4.2.2 narrows to 'within the same single project of the tendered works'). Items absent from the appendices take supplementary codes 01B + three digits from 01B001 (the 2013 edition required filing with the provincial or industry cost authority; 2024 no longer requires it).

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 第4.2.2条、第4.1.4条、App. RTable R.1.1
  • GB 50854-2013 房屋建筑与装饰工程工程量计算规范 第4.2.2条(强制性条文)、第4.1.3条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第4.1.7条、第3.1.8条、第6.1.6条、第6.1.7条、第2.0.27条

Positioning

Whether BOQ item codes are nationally unified or self-set: the five levels of the twelve digits, which digits may be self-coded, how gaps are coded, the duplicate-check scope, how non-compliant codes are handled at tendering, and the 2013 / 2024 differences.

Core conclusions

1. Structure: twelve digits, five levels

GB/T 50854-2024 clause 4.2.2: "BOQ item codes shall be twelve Arabic digits; digits 1-9 are set per the appendices, digits 10-12 per the item name and item description of the proposed works, and codes shall not duplicate within the same single project of the same tendered works." Level meanings (commentary): 1-2 discipline code (01 building and decoration; 02 antique building; 03 general installation; 04 municipal; 05 landscape; 06 mining; 07 structures; 08 urban rail; 09 blasting); 3-4 appendix class code; 5-6 section code; 7-9 work-item code; 10-12 item-name code.

2. Unified versus self-coded digits

  • Digits 1-9: national, not self-set. All segments come from the appendices of the measurement standard; compilers may not alter them.
  • Digits 10-12: compiler-set, uniqueness-bound. From item name and description, numbered from 001, unique within the check scope.
  • Basis: GB/T 50500-2024 clause 4.1.7: "Whether unit-rate or lump-sum, the codes, names, item descriptions, units and work content of the work-item lists follow the national and industry measurement standards and supplementary rules; preliminaries codes, names and work content follow the national and industry standards." Codes are not free text or local codes.
  • Preliminaries coded too: GB/T 50854-2024 Appendix R Table R.1.1 codes them 011601 (scaffolds, vertical transport, large-plant mobilisation, drainage, dewatering, temporary facilities, site discipline, environment, safety, winter/rainy additions, night work, special-region additions etc.).

3. Same code across unit works

Commentary example: three unit works each with identical solid brick walls - codes 010401002001 / 002 / 003, quantities listed per unit works: the last three digits distinguish them; neither merge nor duplicate.

4. Duplicate-check scope: the two editions differ

  • GB 50854-2013 clause 4.2.2 (mandatory): "codes shall not duplicate within the same tendered works" - the whole tender (all unit works of a section / contract section combined); its commentary warns on multi-unit-works lists.
  • GB/T 50854-2024 clause 4.2.2: "within the same single project of the tendered works" - narrowed to the single project.
  • Practice: under 2013, check across unit works and sections; under 2024, per single project. Which applies follows the version cited in the contract and tender documents.

5. Gap items: the 01B code, never self-made first nine digits

GB/T 50854-2024 clause 4.1.4: "Where items not in Appendices A-R appear, the compiler may supplement: 1) the code combines this standard's code 01 with B and three digits, from 01B001; 2) the supplement carries item name, item description, unit, measurement rule and work content (non-measurable preliminaries: name, work content and scope)." GB 50854-2013 clause 4.1.3 adds filing: supplements are filed with the provincial or industry cost authority, which reports to the MoHURD standards institute; same 01B + three from 01B001, no duplicates in the tendered works. Key difference: 2013 has the filing duty, 2024 ("may supplement") drops it. Regions still requiring filing follow their local rules. The 01B + three is itself 9 digits; a full code still needs digits 10-12 (e.g. 01B001001), with no duplicates among supplements or against standard items.

6. Handling code errors

  • Altered digits 1-9, or non-01B self-invented codes used as standard, are non-compliant compilation.
  • At tendering: review - written request for clarification - employer correction - bid on the corrected list. Unit-rate: GB/T 50500-2024 clause 6.1.6 - tenderers question in writing, the employer corrects, bids price the corrected list; "the completeness and accuracy of the work-item list rests with the tenderer whether or not queried". Lump-sum: clause 6.1.7 - tenderers may supplement and price the defective list and answer for it; save unit-priced provisional-quantity items, the price does not adjust for list defects.
  • Liability (clause 3.1.8): unit-rate - the employer answers for list accuracy and completeness, tenderers may not alter; lump-sum - the contractor; preliminaries lists - the contractor either way.
  • Concept boundary: term 2.0.27 "BOQ errors" covers itemisation, description and quantity divergences (extra/missing items, description mismatch, quantity deviation and the like) - not code errors as such; fix codes through tender clarification (6.1.6/6.1.7), not the clause 8.2 adjustment machinery.

Applicable boundaries

  • The body clauses here are building and decoration (code 01); the level framework is common to all disciplines - other disciplines use their own codes (02-09) per their standards; never borrow 01 codes across disciplines.
  • While GB 50854-2013 (mandatory) and GB/T 50854-2024 (recommended) coexist, fix the version per contract / tender before judging duplicates, filing and supplements - no mixing.
  • "01B + three" replaces no digits 10-12; supplements still carry name, description, unit, rule and work content.
  • Self-coding is limited to digits 10-12, bound to name / description and uniqueness; the first nine are never self-made for want of an appendix entry.

Further reading

  • GB/T 50854-2024 clause 4.2.2 and commentary, clause 4.1.4, Appendix R Table R.1.1.
  • GB 50854-2013 clauses 4.2.2 and 4.1.3.
  • GB/T 50500-2024 clauses 4.1.7, 3.1.8, 6.1.6-6.1.7, term 2.0.27, clause 8.2.1; discipline codes 02-09 in each standard's general notes and appendices.