preliminary items
- 01
Cost attribution of lifting and positioning of HVAC (building services) equipment: included in the plant cost of the equipment erection line items vs itemised separately as preliminary items, and the charging and rate build-up connection of the super-height inefficiency coefficient where the erection height exceeds 6m
Lifting costs are attributed on two tests: routine lifting within the pl…
DB11/T 2382-2024 第6.1.2条及Table 6.1.2、第6.7.2条、第6.7.1条GB/T 50856-2024 第4.1.3条、App. P Table P.1.1(措施项目,编码 031401)2026-11-08 - 02
Distinguishing the super-height construction addition from the vertical transport charge, judging whether taking both on one project double-counts, and the two charging forms of the addition - the item method (super-height floor area) and the factor method (labour + plant x efficiency-loss coefficient)
Different cost objects: vertical transport carries only the large vertic…
TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1 第八节 垂直运输及超高增加(FY-1015~FY-1028)GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R Table R.1.1(code 011601)、R.2.3DB11/T 638-2016 房屋修缮工程工程量计算规范 App. B.9.22026-11-04 - 03
Definition, BOQ item (011601002) and cost composition of vertical transport: the pricing vehicle for machine-shifts of large vertical handling plant and their attending labour; a preliminaries item priced as a lump sum per item and held fixed; and its boundary against the plant costs of work items (concrete pumping, extra height for concrete placing)
Vertical transport cost is the price of BOQ item 011601002 'vertical tra…
GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. R(Table R.1.1 措施项目,编码 011601;R.2.3 垂直运输)GB/T 50860-2024 · Standard for Measurement of Quantities of Structures Works App. C(C.2.3 垂直运输)GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.2.1、3.2.6、3.3.7、4.2.5、6.2.6、7.3.1 条,App. E Table E.3.22026-11-01 - 04
Determining whether vertical transport preliminaries double count the machine-shift rates of tower cranes and builder's hoists: the BOQ item coding basis, the inclusion and exclusion boundaries in provincial consumption quota chapter notes, and a method of checking whether the plant rate is included or excluded via the machine-shift content and unit of measurement of quota line items
No double counting. The machine-shift running rates of tower cranes and…
GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R 第R.1.1条、第R.2.3条及Table R.1.1(措施项目,code 011601)GB 50854-2013 房屋建筑与装饰工程工程量计算规范 App. S Table S.3(垂直运输,code 011703)江苏省建筑与装饰工程消耗量定额(2026版)垂直运输工程 章说明2026-10-25 - 05
Deciding when large plant mobilisation and erection charges are priced separately, and the cost make-up (with quota item codes, trip counts and haul-distance rules)
Large-plant mobilisation and erection charges follow a three-type test…
GB/T 50500-2024 App. E Table E.3.4GB/T 50854-2024 App. R Table R.1.1(code 011601)GB 50860-2013 App. C Table C.4(code 070304)2026-10-11 - 06
Measurement and cost adjustment rules for changes to preliminary items caused by design changes (variations) under GB/T 50500-2024
Preliminaries take 'no adjustment' as the principle and 'change-induced'…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引GB/T 51262-2017 建设工程造价鉴定规范2026-09-25 - 07
Vertical transportation quantity calculation: buildings by floor area (incl. basements) x eave-height steps, structures by count/volume, rules for height-increase fees
Vertical transportation is a preliminaries (measures) item; the BOQ cove…
GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准GB/T 50860-2024 构筑物工程工程量计算标准TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程2026-09-25 - 08
Can a practice omitted from the BOQ (missing item) but mandatorily required by codes be deducted at the final account? - the judgment chain of contract type x pricing classification (GB/T 50500-2024) and the judicial approach to missing-item risk
A practice omitted from the BOQ but mandatorily required by codes is not…
GB/T 50500-2024 建设工程工程量清单计价标准(第3.1.8、4.1.4、6.1.5~6.1.7、8.2.1~8.2.3、8.9.1、10.3.13条)中华人民共和国建筑法(2019修正)第五十八条建设工程质量管理条例(2019修订)第二十八条2026-09-25