Where pipe support and hanger costs sit for water supply and drainage (heating, gas) piping, and the boundary for billing them separately: three sets of tests - the BOQ measurement criterion, the Beijing consumption standard criterion, and the diameter gates of the national unified quota and the railway quota
Support and hanger costs cannot be answered wholesale as 'included' or 'not included'; they split by criterion. Under the BOQ measurement criterion, GB/T 50856-2024 clause 3.0.10, the work content of pipe installation items already covers fabrication and erection of supports, hangers and base structural steel plus painting, so no separate item is generally listed (yet rate build-up must still load the support line items into the all-in unit rate); Beijing DB11/T 2382-2024 clauses 6.10.29 and 6.10.35 require supports, pipe clips and hooks to be billed separately under 6.10.39-6.10.42, with no diameter gate; Jing Jian Fa [2021] No. 201 (Beijing), Volume 10, chapter 2 notes item 11 states 'pipe installation does not include pipe support erection', and the 2012 edition of the same note added '(plastic pipes excepted)', which the 2021 edition deleted. The Volume 8 family formula 'DN32 and below include clips and hooks, above that billed separately' of the national unified installation quota and the railway TB/T 10831-2024 'steel pipe below DN25 includes clips and hooks' are both volume-notes-level local or sector criteria, not a national rule. Supports are measured by design-shown mass in kg (quota unit 100kg); proprietary clips and proprietary seismic supports are counted by design-shown number, and seismic supports must be listed separately under the proprietary-support item code.
Applicable Codes
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.10章(6.10.1~6.10.46)
- 京建发〔2021〕201号 北京市建设工程预算消耗量标准 通用安装第十册 第二章、第四章说明
- 京建发〔2012〕538号 北京市建设工程预算定额 通用安装第十册 第二章、第四章说明
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services 第3.0.10条、App. N
- GB 50981-2014 · Code for Seismic Design of Building Mechanical and Electrical Engineering Ch. 8
- GB 55002-2021 · General Code for Seismic Resistance of Building and Municipal Engineering
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明Ch. 3
Topic positioning
Deciding where support and hanger costs sit for water supply, drainage, heating and gas piping: the BOQ measurement criterion and the quota pricing criterion give different 'included or not included' answers, plus the boundaries that force separate billing (proprietary clips, seismic supports, outdoor supports, overweight support groups, sleeves and holes, support painting), with an item-by-item checklist that prevents double counting and omission.
Core conclusions
1. Two criteria, two answers - never blend them
- BOQ measurement (GB/T 50856-2024 clause 3.0.10): 'The work content of the installation items for equipment, piping and accessories in this standard includes the fabrication, erection and painting of supports, hangers and base structural steel; where special design requirements exist, list them under the corresponding items of Annex N, other and ancillary works, or Annex M, painting, corrosion protection and insulation works.' - The all-in unit rate of a pipe item must contain support fabrication and erection, and the BOQ lists no separate item. 'No separate item' does not equal 'no separate charge': quota rate build-up must still load the support line items into the pipe's all-in rate - the most common source of omissions and double charges.
- Beijing DB11/T 2382-2024: clause 6.10.29 'Erection of indoor pipe supports shall follow clauses 6.10.39-6.10.42 of this standard.' Clause 6.10.35 (gas piping): 'Fabrication and erection of pipe supports, clips and hooks shall follow clauses 6.10.39-6.10.42 of this standard; erection of gas leak-detection pipes follows the corresponding pipe installation items; erection of tracer wires follows the warning-tape installation item.' - Pipe line items carry no support content; supports, clips and hooks are all billed separately, and the standard contains no 32mm diameter gate.
- Jing Jian Fa [2021] No. 201, general installation works, Volume 10, chapter 2 notes item 11: 'Pipe installation does not include pipe support erection; apply the corresponding line items of chapter 4, fabrication and erection of pipe supports.' Jing Jian Fa [2012] No. 538, same chapter notes item 11: 'The pipe installation quotas in this chapter do not include pipe supports (plastic pipes excepted); apply the corresponding line items of chapter 4, fabrication and erection of pipe supports.'
- Diameter gates are volume-notes-level rules and their thresholds are not uniform: TB/T 10831-2024 Volume 10 building works, volume notes: 'steel pipe below DN25 includes fabrication and erection of clips and hooks'; 'nominal diameter within 32mm includes clips and hooks, above that billed separately' is the usual wording of the Volume 8 family of the National Unified Installation Works Budget Quota and must not be applied as a national rule (see 'Applicability boundaries').
2. Plastic pipe (PPR/PVC-U) criteria
- The 2012 volume notes carry '(plastic pipes excepted)', i.e. plastic pipe supports were treated as included; the 2021 edition deleted the bracket - projects from 2021 on may no longer invoke 'plastic pipes excepted' to claim that plastic pipe supports are included; bill them separately under chapter 4, fabrication and erection of pipe supports. Cross-edition citation is a classic error source.
- The Beijing 2024 standard, clause 6.10.29, admits no material exception; proprietary clips are counted by design-shown number under 6.10.40, and proprietary seismic supports likewise by number.
- What pipe line items aggregate is 'fittings', not 'supports': the 2021 edition notes item 4 lists steel pipe (welded), stainless steel pipe, copper pipe, water-supply plastic pipe (fusion), buried water-supply plastic pipe, drainage plastic pipe (fusion joint), steel-plastic composite pipe and aluminium-plastic composite pipe installation as all 'including fitting erection; fitting contents may be computed from the fitting content reference table in the annex, or from the quantities on the design drawings'; the 2012 edition notes item 4 matches. Fittings aggregated into plastic pipe items are same-material fittings; steel or copper to plastic transition couplings of all kinds are excluded and the principal material is computed separately.
- 2024 standard clause 6.10.28: indoor water supply or drainage plastic pipe (electrofusion joint) follows the corresponding fusion-joint item for water supply or drainage plastic pipe; electrofusion machine consumption equals fusion machine consumption.
3. Measuring supports billed separately per 100kg, and the content values
- Clause 6.10.39: pipe support fabrication and erection quantities are computed by design-shown mass; where the design is silent, by Table 6.10.39 'reference support usage for indoor steel and cast-iron pipe' (kg/m) - water supply, heating and air-conditioning water: DN15 uninsulated 0.627 / insulated 1.07; DN50 uninsulated 0.797 / insulated 1.167; DN100 uninsulated 1.142 / insulated 1.586; DN125 1.014 / 1.311; DN150 0.869 / 1.440; DN200 2.234 / 2.788; DN250 2.409 / 2.986; DN300 2.524 / 3.087; cast-iron pipe is split by main, riser and suspended runs (e.g. DN100 main 1.129, riser 1.305, suspended 1.194).
- Support fabrication and erection line items take 100kg as the quota unit; every 100kg of supports consumes a combined 105kg of section steel (fabrication wastage is already inside the consumption and is not added again). Conversion examples: DN50 insulated pipe 120m - 1.167x120 = 140.04kg - 1.40 quota units; DN100 uninsulated 200m - 1.142x200 = 228.4kg - 2.284 quota units.
- Split rules: proprietary seismic supports and proprietary clips are counted by design-shown number (6.10.40); equipment support fabrication and erection is measured by design-shown mass per support-group weight class (6.10.41); where outdoor piping uses above-ground section-steel supports, follow the corresponding items of static equipment and process metal structure fabrication and erection, and where a single pipe support group exceeds 50kg, follow the equipment support fabrication and erection items (6.10.42; the 2021 edition Volume 10 chapter 4 notes item 4 is the same criterion).
4. Double-count and omission checklist when supports are billed separately
| Content | Attribution | Basis |
|---|---|---|
| Pipe supports, clips, hooks | Not in pipe line items; billed separately (2024, all materials; 2012 edition excepted plastic pipes) | 6.10.29, 6.10.35; volume notes item 11 |
| Hydraulic test, water flushing | Already inside pipe installation consumption; not separately chargeable | 6.10.25; 2021 edition notes item 12 |
| Disinfection flushing (where the design requires) | No separate line item; by coefficient: indoor pipe labour x1.05, other materials rate +0.10%, other plant rate +0.15%; grooved-connection pipe labour x1.04, other materials rate +0.10%, other plant rate +0.15%; stainless pipe welding labour x1.05, other materials rate +0.15%, other plant rate +0.20% | 6.10.30; 6.10.9 |
| Ball-passing test (where the design requires) | Labour x1.10, other materials rate +1.00%, other plant rate +0.05% | 6.10.30 |
| Reserved holes, hole sealing | Billed separately: by number per position and hole perimeter (6.10.45); by the volume of hole filling (6.10.46). But sleeve erection already includes reserving and sealing holes - do not double count | 6.10.31, 6.10.43; 2021 edition chapter 4 notes item 9 |
| Sleeves | Billed separately, by number per main pipe diameter; sleeves through walls and slabs on insulated pipe follow the insulation outer diameter; sleeve packing is based on oil hemp | 6.10.43 |
| Fire-stop collars, waterproof leak couplings (water-stop joints) | Billed separately, by number per main pipe diameter | 6.10.44 |
| Support painting, corrosion protection, insulation | Billed separately under the quota criterion (corresponding painting, corrosion protection and insulation works items); included under the BOQ criterion within the 3.0.10 work content | 6.10.4 |
| Holing and chasing | Follow the electrical equipment installation works items | 6.10.6 |
| Grooved-connection piping | Follow the fire protection works items | 6.10.9 |
| Principal materials | Consumption of pipes, valves and other principal materials appears as bracketed additions and is not a base for other materials costs | 6.10.14 |
| Construction condition corrections | Work inside pipe or equipment floors (rooms) with clear height under 1.60m: labour consumption x1.15; labour efficiency deduction for erection above 6m per clause 6.1.2 | 6.10.12, 6.10.13 |
5. Outdoor and volume boundaries (what decides whether supports and blocks enter the water and drainage volume)
- 6.10.1 heating and water supply or drainage piping is bounded at 1.50m outside the building face; underground gas entry is bounded at the first valve inside, above-ground entry at the tee outside the wall.
- 6.10.2 the boundary with municipal piping is the meter chamber, valve chamber and junction chamber (those chambers follow the corresponding municipal works items); gas piping is bounded at the valve chamber before the pressure regulating installation.
- 6.10.3 industrial piping, shared production and domestic piping, and equipment connections within station (pump, machine) rooms and boiler rooms follow the industrial piping works items; where such rooms sit inside a building, the boundary is the outer face of their walls.
- 6.10.10 drainage pipe erected along the building face, earthwork for buried pipe, base treatment, sand filling, earthwork for gas regulator boxes, foundations and beds follow the building and decoration works items; heating trenches and brickwork of all chambers follow the structures works items - outdoor concrete blocks and brick piers are civil or structures work and take no support line item from the water and drainage volume.
- 6.10.11 foundation casting follows building and decoration works; secondary grouting follows mechanical equipment installation. 6.10.5 pump erection follows mechanical equipment installation (VFD pump sets per 6.10.85); 6.10.7 plate heat exchangers follow static equipment and process metal structure fabrication and erection; 6.10.8 water distribution and collection manifolds, medical gas system piping and pipe blinds follow industrial piping works.
6. Seismic supports and ordinary supports must be listed separately
- BOQ: GB/T 50856-2024 Annex N, 'seismic supports are listed under the proprietary support item code', counted in sets, never merged with ordinary supports and hangers; support lining pads and painting are noted and listed separately under Annex N.2.4 and Annex M.
- Beijing 2024: proprietary seismic supports and proprietary clips are counted by design-shown number (6.10.40) - a different unit of measurement from supports by mass (kg); the two must not be mixed.
- 2021 edition Volume 10 chapter 4 notes item 5: proprietary seismic support erection splits into single-pipe lateral support erection and portal lateral support erection; combined longitudinal-and-lateral support erection applies the corresponding lateral support erection items with labour x1.05; the principal material seismic support (incl. anchor bolts) contains anchors and undercut anchors.
- Seismic support quantities are fixed by the seismic layout design (GB 50981-2014 chapter 8) and must not be converted from the ordinary support reference values of Table 6.10.39 - that table serves only ordinary supports on indoor steel and cast-iron pipe.
Applicability boundaries
- The three criteria must not be mixed: the BOQ criterion (GB/T 50856-2024) decides 'is a separate item listed'; the quota criterion decides 'is a separate line item charged'. Within one estimate, 'included in the BOQ' and 'charged separately under the quota' can legitimately coexist; but double-loaded and unloaded rates are both errors. First fix item attribution under the BOQ, then confirm under the quota whether the pipe line item's work content covers the process.
- Diameter gates (25mm / 32mm) are local or sector volume-notes rules, not national practice: the Beijing 2024, 2021 and 2012 volumes carry no gate; the railway gate is DN25; 'DN32 and below include clips and hooks' is the Volume 8 family wording - verify against the quota volume notes actually used before citing; do not transfer it to other regions.
- The 2012 and 2021 volume notes differ substantively on 'plastic pipes excepted'; cross-edition citation omits supports (from 2021 on, everything is billed separately under the 2021 or 2024 criteria).
- Table 6.10.39 is a reference 'where the design is silent'; where the design gives support drawings or calculations, measure by design-shown mass - never force the reference table.
- The mandatory basis for judging seismic provisions has passed to GB 55002-2021 (the former GB 50981-2014 clause 1.0.4 is superseded); spacing and layout still follow GB 50981-2014 chapter 8.
- Specific consumption line item numbers and labour and material coefficients follow the current quota and supporting on-cost norms of the project location; they vary by region.
Further reading
- DB11/T 2382-2024 'Construction works consumption standard', chapter 6.10 water supply, drainage, heating and gas works: I general rules 6.10.1~6.10.14; III indoor piping 6.10.24~6.10.32; IV gas piping 6.10.33~6.10.38; V supports, sleeves and others 6.10.39~6.10.46 (incl. Table 6.10.39 reference support usage for indoor steel and cast-iron pipe).
- Jing Jian Fa [2021] No. 201 'Beijing construction works budget consumption standard', general installation works, Volume 10: chapter 2 notes items 4, 11, 12, 13, 14; chapter 4 notes items 2~9 and the calculation rules. Jing Jian Fa [2012] No. 538, same volume: chapter 2 notes items 4, 11; chapter 4 notes items 2~10.
- GB/T 50856-2024 'Standard for quantity take-off of general installation works', clause 3.0.10; Annex N other and ancillary works (N.2.3 seismic supports listed under the proprietary support item code; N.2.4 support lining pads and painting).
- GB 50981-2014 'Code for seismic design of building services engineering', chapter 8: 8.2.3 (spacing formula l = l0 x aEk x k and the maximum spacing table), 8.3.6, 8.3.10, 8.3.14, 8.3.15.
- GB 55002-2021 'General code for seismic resistance of building and municipal works' (current mandatory basis for seismic design).
- TB/T 10831-2024 'Railway works budget quota manual, Volume 10, building works', volume notes, chapter 3 building services engineering, section 1 water supply, drainage and fire protection (indoor-outdoor boundary; steel pipe below DN25 includes fabrication and erection of clips and hooks).
Keywords
- 支吊架
- 管道支架制作安装
- 管道安装子目工作内容
- 管卡托钩
- 100kg
- 塑料管支架
- 抗震支架单独列项
- 防重复计费