Quota application for the erection cost of vertical storage tanks (metal oil tanks) built by the reverse jack-up method with hydraulic lifting: line-item selection by construction form and capacity class, measurement by shell metal weight in t, lifting gear and temporary stiffening to preliminaries, and NDT and the water filling test charged separately

The reverse jack-up method has no standalone line item in the erection consumption quota: the item is selected by 'tank type x shell construction form (lap-jointed / butt-jointed) x capacity class' and measured by shell metal weight in t (no deduction for the area of openings in the shell, and including bottom plates, shell plates, roof plates, curb angle, stiffening rings, wind girders, and shim and reinforcement plates); where only one tank is built on one site, labour and plant consumption is multiplied by 1.25 (materials not). Neither the plant schedule nor the work content of the items contains a lifting step, so the hydraulic lifting devices and the temporary stiffening of the reverse method are charged as preliminaries; the work content stops at 'leak testing' - shell weld NDT, the water filling test and foundation settlement monitoring are outside the items and must be listed separately.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第 6.3 章 静置设备与工艺金属结构制作安装工程(6.3.1~6.3.7、6.3.23~6.3.29)及App. C.3(Table C.3.16-1、C.3.16-2、C.3.17-1、C.3.17-2、C.3.17-3)
  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. C Table C.2.1(编码 030302)金属油罐制作安装
  • GB 50128-2014《立式圆筒形钢制焊接储罐施工规范》第 5.4.2 条、第 7.4.1 条
  • GB/T 50484-2019 第 9.2.10 条(倒装法提升柱与液压提升装置要求)
  • GB/T 51095-2015 第 5.3.12 条(定额缺项编补充单位估价表)

Positioning

For vertical cylindrical welded steel storage tanks (metal oil tanks) erected by the reverse jack-up method (hydraulic lifting or air raising): how the erection cost lands in the quota - by which classes the line items are selected, how the quantity is computed, whether the lifting gear and temporary stiffening sit inside the item or go to preliminaries, how weld NDT and the water filling test are charged, and how preliminaries are kept free of double counting between the reverse and conventional methods. Sampled on Beijing DB11/T 2382-2024 'Construction works consumption standard' chapter 6.3 and Annex C.3, with GB/T 50856-2024 Annex C table C.2.1 (code 030302).

Core conclusions

1. The application formula

The quota sets no parallel items for the 'reverse' and 'conventional' methods. Pricing of reverse-method erection lands in three places: (1) measured works - the item selected by 'tank type x shell construction form (lap-jointed / butt-jointed) x capacity class', measured by shell metal weight in t; (2) preliminaries - the erection, dismantling and amortisation of the hydraulic lifting devices and the temporary stiffening of the reverse method; (3) separate charges - shell weld NDT, the water filling test and foundation settlement monitoring.

Key judgement: the quota classes items by construction form, not by erection method. GB/T 50856-2024 Annex C table C.2.1 note 2: 'the construction forms of dome-roof tanks include lap-jointed and butt-jointed shell plates, and the work content shall include the tank bottom, shell plates, roof (including the centre plate), angle rings, stiffening rings, laps, shims, reinforcement plates and all required attachments and fittings'; note 3: 'the construction forms of floating-roof tanks include double-deck, single-deck and internal floating roof'; note 1: 'no deduction of the length of fittings for coil heater installation'; note 4: the work content of large metal oil tanks shall include the parts and components of the shell, the laps and butt shims of each part, and the sump, drain, nozzles and fittings, heating coils, floating-roof heaters, manhole fabrication and erection and other attachments, with the item description stating these attachments as shown on the design drawings.

Hence where the design is butt-jointed but erection is by the reverse method, the butt-jointed item still applies (the construction form follows the item description on the design drawings) and the lifting measure is charged separately as preliminaries; a lap-jointed item must not be taken on the ground of the 'reverse method', nor may both construction forms be applied to one shell.

2. Measurement and weight basis (DB11/T 2382-2024 clause 6.3.25, verbatim)

'The fabrication and erection quantity of the metal oil tank proper shall, by kind, capacity and construction form, be computed from the geometric dimensions shown on the design layout drawings; where there are no design layout drawings, from the geometric dimensions shown on the approved fabrication cutting and plate layout; no deduction is made for the area of the openings on the shell, and the quantity is the weight of the tank proper. The weight of the tank proper shall include the metal weights of the bottom plates, shell plates, roof plates (floating roof, lattice dome), curb angle, stiffening rings, wind girders, and the shim and reinforcement plates on the shell.'

That is, the permanent reinforcement and shim plates, curb angle and wind girders all enter the weight of the tank proper in t, with no separate items.

3. The single-tank factor (clause 6.3.24, verbatim)

'The consumption for oil tank fabrication and erection may assume two or more tanks of the same series built simultaneously on one site; where only one tank is built, the labour and plant consumption is preferably multiplied by 1.25.' - labour and plant only, materials not; nor do any preliminaries follow from this factor.

4. Item classes (Annex C.3, unit t)

Construction form (table) Capacity class, m3 Item codes
Lap-jointed dome-roof tank (table C.3.16-1) 100 / 200 / 300 / 400 / 500 / 700 / 1000 / 2000 / 3000 / 5000 / 10000 C3-3-1 ~ C3-3-11 (500 = C3-3-5, 700 = C3-3-6, 1000 = C3-3-7, 2000 = C3-3-8, 3000 = C3-3-9, 5000 = C3-3-10, 10000 = C3-3-11)
Butt-jointed dome-roof tank (table C.3.16-2) 500 / 700 / 1000 / 3000 / 5000 / 10000 C3-3-12 ~ C3-3-18 (500 = C3-3-12, 700 = C3-3-13, 1000 = C3-3-14, 3000 = C3-3-16, 5000 = C3-3-17, 10000 = C3-3-18)
Double-deck floating-roof tank (table C.3.17-1) 5000 / 10000 / 20000 / 30000 C3-3-19 ~ C3-3-22
Single-deck floating-roof tank (table C.3.17-2) 3000 / 5000 / 10000 / 20000 / 30000 C3-3-23 ~ C3-3-27
Internal floating-roof tank (table C.3.17-3) 500 / 700 / 1000 / 2000 / 3000 / 5000 / 10000 C3-3-28 ~ C3-3-34 (3000 = C3-3-32, 5000 = C3-3-33, 10000 = C3-3-34)

The item codes must be verified against the edition of the quota in use; provincial and municipal installation consumption (budget) quotas differ in coding, but the chapter structure and class logic share one origin.

5. Fittings and heaters (clauses 6.3.26~6.3.29)

The various tank fittings 'are computed by the quantities shown on the design, distinguished by kind, size and model of fitting'; heater fabrication and erection 'by the quantities shown on the design, distinguished by construction form and coil length'; heater connecting pipes 'by the quantities shown on the design, distinguished by header length'; heater supports 'by the quantities shown on the design, distinguished by construction form'. Fittings and heaters do not enter the weight of the tank proper in t - they are listed separately by count.

6. Lifting gear and temporary stiffening: inside or separate (three-step test)

  1. Check the plant schedule of the item: the plant of lap-jointed item C3-3-1 (100m3) is a 16t truck crane (1.285 machine-shifts/t), 10t cargo truck (0.343), semi-automatic cutter 100mm (0.638), guillotine shears 20x2500mm (0.162), plate rolls 30x2000 (0.048), vacuum pump (0.067), electrode drying oven 80x80x100cm (0.521), electrode constant-temperature oven (0.521), electric air compressor 6m3/min (0.590), other plant 3% - no hydraulic lifting device, no lifting columns, no jacking rings.
  2. Check the work content: the work content of C3-3-1 is 'stacking of plates, lofting and marking, cutting, bevelling, rolling, bending, hoisting, matching and welding, grinding, leak testing, etc.' - no lifting or raising step.
  3. Conclusion:
    • rental amortisation, erection and dismantling and no-load trials of the hydraulic lifting devices (hydraulic jacks, lifting columns, pump stations, position clamps) -> preliminaries (a preliminary not precisely measurable, priced per item against the approved project execution plan);
    • the permanent reinforcement and shim plates, curb angle and wind girders of the shell -> into the shell metal weight in t, not charged again;
    • reverse-method temporary stiffening (jacking rings, temporary props, the lifting-column tie rods fully welded to the tank bottom) -> preliminaries (GB/T 50484-2019 clause 9.2.10 requires the lifting-column tie rods to be fully welded to the bottom and the hydraulic lifting devices to rise and fall in synchrony - construction temporary works);
    • hoisting: the plant of the item already contains truck-crane machine-shifts - no separate 'reverse-method hoisting' plant charge.

7. The charging boundary of NDT, the water filling test and settlement monitoring

Item Included in the fabrication and erection item? How charged
Leak testing (kerosene, vacuum box) Yes (the work content lists 'leak testing') No separate charge
Shell weld NDT, RT/UT/MT/PT No (the work content has no NDT; this volume carries no standalone weld NDT item) Listed separately by the method and ratio specified in the design, measured by weld length (m) or number of films; where an item is missing, compile a supplementary unit-rate build-up schedule per GB/T 51095-2015 clause 5.3.12
Water filling test (bottom tightness; shell strength and tightness; fixed-roof strength, stability and tightness; travel and tightness of floating and internal floating roofs; floating-roof drain tightness) No ('leak testing' is not the water filling test) Test water, pressure-pump machine-shifts and test labour listed separately; per GB 50128-2014 clause 7.4.1, the completed tank shall undergo the water filling test with the above checks
Foundation settlement monitoring No Monitored alongside the water filling test; where the employer commissions third-party monitoring, charged under other items; where the contractor monitors itself, under preliminaries or other items - one or the other only

8. Six no-double-count rules

  1. One construction form: one tank takes lap-jointed or butt-jointed only, per the design drawings - never both.
  2. No hoisting double count: the item plant already contains truck-crane machine-shifts - no 'reverse-method hoisting plant' line.
  3. Mutually exclusive method preliminaries: once a lap-jointed (reverse) item is taken, the internal and external birdcage scaffolds and the shell-assembly working platforms of the conventional method must not be charged, and vice versa.
  4. Lifting devices charged once: rental amortisation and erection and dismantling may appear in preliminaries only - never again as plant machine-shifts inside the measured works.
  5. No double NDT: NDT must not sit both inside the all-in unit rate and again as inspection and testing costs; leak testing is already included - no separate leakage-test item.
  6. Water and factor: test water must not double with construction water or pipe pressure-test water; the single-tank x1.25 touches labour and plant only, not materials, and adds no preliminaries.

9. How the process difference enters pricing

Stage Reverse jack-up (hydraulic lifting / air raising) Conventional bottom-up
Assembly order Top shell course + curb angle + roof welded first; assembled and jacked course by course downward Bottom plate -> bottom course -> course by course upward
Shell connection Mostly lap-jointed (spares girth-butt matching; avoids overhead welding at height) Mostly butt-jointed
Weld position Girth welds mostly flat Girth welds include horizontal and overhead welding; much work at height
Temporary works Lifting columns (tie rods fully welded to the bottom), jacking rings, position clamps, hydraulic pump stations Internal and external scaffolds, working platforms, crane attendance

The process difference does not change the item selection (the design construction form governs); it changes only the content of the preliminaries; the temporary works of the two methods are mutually exclusive - one only.

10. Cross-volume interfaces (clauses 6.3.1~6.3.7)

'Pipework beyond the first flange of the equipment proper executes the corresponding items of the industrial pipework works'; electrical systems under electrical equipment installation works, instrument systems under automation and control instrument installation works, derusting, painting and insulation under the painting, anti-corrosion and insulation works, anchor-bolt grouting and fan installation under machinery equipment installation works, and equipment foundations under the building and decoration works - that is, pipework, electrical, instrumentation, anti-corrosion and insulation and foundations outside the tank proper must not be merged into the tank fabrication and erection items.

Application boundaries

  • The item codes and capacity classes are the Beijing DB11/T 2382-2024 Annex C.3 sample; projects in other provinces should apply the static equipment volume of their local installation consumption (budget) quota, with codes and factors per the local edition - the chapter structure and judgement logic share one origin (descending from the national unified installation quota system).
  • Applies to site fabrication and erection of vertical cylindrical welded steel storage tanks; spheres, cryogenic tanks and non-metallic tanks follow their own chapters.
  • This card gives the quota-application and cost-attribution judgement, without specific rates or consumption values; actual pricing must use the base prices of the edition in use and the market prices of the compiling period.
  • NDT must follow the design documents and the methods and ratios of GB 50128-2014 and NB/T 47013; different ratios mean different rates, which must be stated in the item description.

Further reading

  • DB11/T 2382-2024 chapter 6.3, 'fabrication and erection of static equipment and process steelwork': I, general rules, 6.3.1~6.3.7; IV, fabrication and erection of metal oil tanks, 6.3.23~6.3.29 (6.3.23 items by tank type and capacity; 6.3.24 single-tank factor; 6.3.25 measurement and weight basis; 6.3.26~6.3.29 fittings and heaters).
  • DB11/T 2382-2024 Annex C.3: table C.3.16-1 lap-jointed dome-roof tanks; table C.3.16-2 butt-jointed dome-roof tanks; table C.3.17-1 double-deck floating-roof tanks; table C.3.17-2 single-deck; table C.3.17-3 internal floating roof (work content example C3-3-1 above).
  • GB/T 50856-2024 Annex C table C.2.1 (code 030302), notes 1~4 on metal oil tank fabrication and erection.
  • GB 50128-2014 clause 5.4.2 (shell assembly tolerances): the level tolerance between the top ends of adjacent plates of the bottom course, or of the top course under reverse erection, no more than 2mm, and over the whole circumference between any two points no more than 6mm; shell plumbness no more than 3mm; the plumbness of the other courses no more than 0.3% of the course height; the shell plates shall be assembled flush on the inner face; for SMAW longitudinal welds, misalignment no more than 1mm at plate thickness no more than 10mm, and at over 10mm no more than 0.1 times the plate thickness and no more than 1.5mm; automatic welds no more than 1mm; for girth welds by SMAW, misalignment no more than 1.5mm where the upper course is no more than 8mm thick, and where over 8mm no more than 0.2 times the plate thickness and no more than 2mm; automatic welds no more than 1.5mm; longitudinal peaking checked with a 1m arc template and circumferential peaking with a 1m straight template; the distance from the outer face of the bottom course to the outer edge of the edge plates shall be no less than 50mm and preferably no more than 100mm.
  • GB 50128-2014 clause 7.4.1 (water filling test and check items); clause 7.3.1 item 4 (tank diameter / inner radius check).
  • GB/T 50484-2019 clause 9.2.10 (lifting-column tie rods fully welded to the bottom; hydraulic lifting devices rising and falling in synchrony).
  • GB/T 51095-2015 clause 5.3.12 (supplementary unit-rate build-up schedules compiled per the compiling principles where items are missing).