Railway 2024 quotas — erecting concrete poles: item selection by pole type + pole height (TB/T 10829-2024 Volume 8 power works, DY-25~DY-35)

In TB/T 10829-2024 Volume 8, Chapter 1 overhead power lines, Section 2 pole and tower erection, concrete poles step by "pole type (tapered / uniform-diameter / strut) + pole height" (DY-25~DY-35), not by weight; quantities per design count in "poles". Pole main-material consumptions are bracketed — items carry no material cost or weight; book main materials separately per design. Heights beyond the steps (tapered >18 m, uniform-diameter >21 m) have no item — handle by the supplementary-quota procedure.

Applicable Codes

  • TB/T 10829-2024 · Budget Quota of Railway Engineering (Volume 8: Power Works) Ch. 1 架空电力线路 第二节 杆塔组立(DY-25~DY-35)

Topic Positioning

The application rules for the concrete-pole erection quota line items (DY-25–DY-35) in Chapter 1, Overhead Power Lines, Section 2, Pole and Tower Erection, of the railway 2024 quota manual Railway Works Budget Quota Manual (China Railway), Volume 8: Power Works, TB/T 10829-2024: stepping basis, quantity take-off (measurement), separate booking of main materials and companion quota line items, for direct use in preparing and auditing railway power-works estimates and budgets.

Core Conclusions

  1. Stepping basis: concrete-pole erection is stepped by "pole type + pole height", not by pole weight. Only angle-steel tower erection steps by mass per metre (angle-steel tower mass t ÷ total tower height m); steel-tube towers step by tower mass (from DY-36).
  2. Concrete-pole quota line items (unit "pole"; work content: correcting pit position, trimming the pit, inspecting the pole, sighting for straightness, erecting the pole, plumbing, backfilling and tamping):
  • Tapered poles: DY-25 pole height ≤10 m, DY-26 ≤12 m, DY-27 ≤15 m, DY-28 ≤18 m;
  • Uniform-diameter poles: DY-29 ≤12 m, DY-30 ≤15 m, DY-31 ≤18 m, DY-32 ≤21 m;
  • Strut poles: DY-33 ≤9 m, DY-34 ≤11 m, DY-35 ≤13 m. In selecting a line item, first determine the pole type (tapered / uniform-diameter / strut), then take the line item whose "≤" step contains the design pole height.
  1. Quantity take-off (measurement): the pole erection itself is counted in "poles" by the designed number of poles, one pole per unit, with no conversion.
  2. Separate booking of pole main materials: Chapter 1, note 2 of the volume notes states verbatim, "This chapter lists the consumption of main materials such as poles, steel-tube towers and conductors in brackets; such quota line items carry no 'material cost' or 'weight', and the materials actually adopted in the design shall be booked separately." The base prices of DY-25–DY-35 exclude the pole itself; the main-material cost must be booked separately according to the designed pole type and specification (e.g., tapered pole Φ190×10 m).
  3. Companion quota line items — omit none and double-book none: joints of sectional poles use DY-52 (steel-ring welding, gas welding) / DY-53 (steel-ring welding, electric welding) / DY-54 (flanged connection); pole-top sealing uses DY-55 (concrete pole capping); pit excavation (pole-pit excavation), stay-wire fabrication and erection, base and collar plate installation, cross-arm installation and conductor stringing all belong to quota line items in other sections of Chapter 1 and are booked separately according to the actual design content.
  4. Beyond steps: where the pole type or pole height exceeds the above steps (e.g., tapered poles >18 m, uniform-diameter poles >21 m), no direct quota line item exists; handle it under the supplementary quota items procedure rather than forcing a higher step.

Applicable Boundaries

  • Applies only to the concrete-pole erection quota line items in Chapter 1, Overhead Power Lines, Section 2, Pole and Tower Erection, of TB/T 10829-2024 Railway Works Budget Quota Manual, Volume 8: Power Works; steel-tube towers and angle-steel towers (from DY-36) are stepped differently (by tower mass / mass per metre), and this card's stepping must not be applied to them.
  • This card covers only the pole erection itself: pit excavation, stays, base and collar plates, cross-arms, conductor stringing and crossing of obstacles are all quota line items in other sections of Chapter 1 and must be booked separately per the design — they may be neither merged into the pole-erection line item nor double-booked.
  • The base prices of quota line items are quota base-period prices; compilation-period price differentials must be adjusted separately along the three lines of labour, materials and plant in accordance with the railway works estimate (budget) compilation measures, and the base price must not be used directly as the compilation-period all-in unit rate.
  • Pole-height steps have upper limits (tapered poles ≤18 m, uniform-diameter poles ≤21 m, struts ≤13 m); beyond the steps, no line item may be forced.

Further Reading

  • Quota text: TB/T 10829-2024 Railway Works Budget Quota Manual, Volume 8: Power Works, Chapter 1, Overhead Power Lines, Section 2, Pole and Tower Erection, quota line items DY-25–DY-35 (concrete-pole erection) and from DY-36 (steel-tube / angle-steel tower erection).
  • Notes to the same volume: note 1 (composition of the chapter's line items: pit excavation, pole and tower erection, cross-arm installation at 1 kV and below / 10 kV / 35 kV, conductor stringing, crossing of obstacles, stay-wire fabrication and erection, base and collar plate installation, ancillary facilities, etc.); note 2 (bracketed consumptions of main materials such as poles, steel-tube towers and conductors are booked separately); note 3 (angle-steel tower mass per metre = tower mass t ÷ total tower height m); note 5 (crossing-of-obstacle line items: 10 kV / 35 kV crossing quotas assume construction with the power line de-energized; where a live-line crossing is required, labour and machinery consumption are multiplied by a factor of 4.0; river crossings apply only to rivers (or lakes) that carry water, and rivers within 20 m are not considered crossings); note 6 (crossings are calculated in "spots": within one span, several obstacles of the same kind spaced ≤50 m apart count as one spot and >50 m as two; multiple kinds of obstacles are counted by number).
  • For the general decision path for line-item selection (matching the item description → direct application → adjusted application → supplementary quota items), the mechanism for adjusting base-period price differentials and the audit methods for pricing by applying quota line items, see the entries cited in this card.