Amortisation formulas for formwork and turnover materials: the three railway-quota bases and the traditional turnover-use / recovery / make-up-rate basis
Per TB/T 10821-2024 Chapter 9, three classes: 1 steel formwork, timber and other track materials - per-use amortisation = first-use quantity / amortisation cycles; 2 combined-steel-formwork fittings and supports, plastic formwork and metal materials - per-use amortisation = first-use quantity / amortisation cycles + first-use quantity x site handling and operation wastage rate; 3 metal members and piping, rails and turnouts - amortisation = total used mass x per-erection loss rate + total used mass x annual charge rate x years of use (part-quarters rounding up to a quarter). The traditional basis computes separately: turnover use = first-use quantity x [1 + (cycles - 1) x make-up rate] / cycles; recovery = first-use quantity x (1 - make-up rate) / cycles; amortisation = turnover use - recovery x recovery discount rate.
Applicable Codes
- TB/T 10821-2024 Ch. 9
- TB/T 10821-2024 Ch. 2 说明第四~六条
- TB/T 10821-2024 Ch. 10
- JGJ/T 222-2011 第5.2.3条
Scope of the question
The amortisation-quantity formulas for formwork and turnover materials - the three quota bases (by cycles; by cycles plus handling wastage; by per-erection loss and annual charge rates) and the traditional turnover-use / recovery / make-up-rate basis. Per TB/T 10821-2024 Railway Works Basic Quota Chapter 9 etc., for quota compilation and construction cost estimating.
Core conclusions
- TB/T 10821-2024 Chapter 9 notes (three formulas):
- Two: steel formwork, timber and other track materials amortise by cycles - per-use amortisation = first-use quantity / amortisation cycles.
- Three: combined-steel-formwork fittings and supports, plastic formwork and metal materials amortise by cycles and the site handling and operation wastage rate - per-use amortisation = first-use quantity / cycles + first-use quantity x wastage rate (the metal wastage rate is in Chapter 10 of the volume).
- Four: metal members and piping, rails and turnouts amortise by the per-erection loss rate and annual charge rate - amortisation = total used mass x per-erection loss rate + total used mass x annual charge rate x years of use (counted by quarters, part-quarters up to one).
- Amortisation cycles are not fixed freely but taken from the quota tables. Chapter 9 values - timber: cast small-member formwork 5, formwork supports 8, scaffolding 12, bamboo-plywood 5, precast small-member formwork 20, sleeper stacks and skidways for steel beams 16, auxiliary packing 4; metal: nails 1 (one-off), fittings 5-25 (by cast / precast position), tie bolts and hangers 8-25, wire rope 40, steel (rebar, plate, section, tube, couplers) 50.
- Timber formwork values (Chapter 9 Section 3, unit 10 m2 contact area): cast-in-place small members - cycles 8, sawn timber 0.613 m3; precast small members - cycles 20, sawn timber 1.370 m3.
- Traditional quota basis (building and municipal, parallel to the railway one): turnover use = first-use quantity x [1 + (cycles - 1) x make-up rate] / cycles; recovery = first-use quantity x (1 - make-up rate) / cycles; amortisation = turnover use - recovery x recovery discount rate (without netting residual value, amortisation approximates turnover use). Example: first use 100 m2, 5 cycles, 15% make-up rate - turnover use = 100 x [1 + 4 x 0.15] / 5 = 32 m2; recovery = 100 x 0.85 / 5 = 17 m2; at 50% recovery discount, amortisation = 32 - 17 x 0.5 = 23.5 m2.
- JGJ/T 222-2011 Article 5.2.3: turnover-material consumption Q_Ui = Q_Di / n - Q_Ui the consumption of material of class i, Q_Di total demand, n rated cycles; i.e. per-cycle use x cycles on this project.
- Railway Chapter 2 notes: formwork erection and removal items are per 10 m2 of formwork-to-concrete contact area; professional quotas citing timber-formwork fabrication compute amortisation on YY-23 per the cycles (formulas in Chapter 9), YY-24 cited directly; timber-structure fabrication likewise on YY-25, YY-26 directly.
Applicability limits
- Railway flavour: steel formwork, timber and track materials carry no wastage rate - first use / cycles straight; only combined-formwork fittings and supports, plastic formwork and metal materials add first use x handling and operation wastage. Do not mix the railway basis with the building one (make-up rate / recovery).
- The traditional turnover-use / recovery / make-up basis mainly serves building and municipal consumption quotas and cost estimating; where quotas have already amortised per adopted cycles and make-up rates into item contents, budgets apply the quota directly without re-computation - recompute only for construction cost estimating with actual cycles.
- Cycles, first-use quantities and make-up rates are adopted table values (consumption quota appendix tables typically list, per 100 m2 contact area, formwork / support types, concrete volume, first-use quantity, cycles and make-up rate); check each system's own tables - values are not interchangeable.
- Rented turnover materials do not follow amortisation formulas; prices take the quota base-period or compilation-period market price.
Further reading
- TB/T 10821-2024 Railway Works Basic Quota: Chapter 9 auxiliary structure materials and semi-finished amortisation (Section 1 steel formwork, 2 plastic formwork, 3 timber - cycle and quantity tables, 4 metal materials); Chapter 2 formwork and auxiliary structures notes 4-6 (YY-23 to YY-26 citation rules, unit 10 m2 contact area); Chapter 10 (metal handling and operation wastage rates).
- Cycle and per-cycle cost determination: card card_6b929902; amortised vs rental bases and one-off amortisation: companion cards.
- JGJ/T 222-2011 Standard for Sustainability Assessment of Building Construction, Article 5.2.3.
Keywords
- 摊销量计算公式
- 一次使用量
- number of reuses (amortization cycles)
- 周转补损率
- 回收量
- 周转使用量
- TB/T 10821-2024
- 模板摊销