Computation procedure and cost make-up of item-wise estimates (budgets) for railway works of construction and installation, including the equipment item-wise procedure - TB 10801-2024 Section 2.6 Tables 2.6.2 and 2.6.3

Per TB 10801-2024 Article 2.6.2 Table 2.6.2, the item-wise estimate (budget) for works of construction and installation runs: quota direct works cost = base-period labour + base-period materials + base-period plant; direct works cost = quota direct works cost + price-exclusive freight and handling + price differentials total (labour, material and plant differentials) + fill material cost; construction preliminaries = [(1)+(3)] x preliminaries rate, indirect costs = [(1)+(3)] x on-costs rate (the base being base-period labour + base-period plant, excluding materials); direct cost = direct works cost + construction preliminaries + special-construction increases; item estimate value = direct cost + indirect costs. The equipment item estimate (Table 2.6.3) = equipment cost + equipment freight and handling (equipment cost x rate).

Applicable Codes

  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第2.6节(Table 2.6.2、Table 2.6.3)
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额

Scope of the question

The cost make-up and item-wise computation (charging) procedure of design estimates under TB 10801-2024 Compilation Rules for Design Estimates and Budgets of Railway Capital Construction Works, Section 2.6 - covering the step-by-step build-up and review of item-wise estimate values for works of construction and installation and for equipment procurement.

Core conclusions

1. Item-wise computation for works of construction and installation (Article 2.6.2, Table 2.6.2):

No. Cost item Method
1 Base-period labour design quantities x base-period prices
2 Base-period materials design quantities x base-period prices
3 Base-period plant design quantities x base-period prices
4 Quota direct works cost (1)+(2)+(3)
5 Price-exclusive freight and handling separately listed items per the material supply plan in the execution plan and this rule
6 Labour differential base-to-compilation period, per this rule
7 Material differential base-to-compilation period, per this rule
8 Plant differential base-to-compilation period, per this rule
9 Differentials total (6)+(7)+(8)
10 Fill material cost design quantities x surveyed prices
11 Direct works cost (4)+(5)+(9)+(10)
12 Construction preliminaries [(1)+(3)] x rate
13 Special construction increases on compilation-period labour and plant
14 Direct cost (11)+(12)+(13)
15 Indirect costs [(1)+(3)] x rate
16 Item estimate value (14)+(15)

2. Equipment item-wise computation (Article 2.6.3, Table 2.6.3):

No. Cost item Method
1 Equipment cost design equipment quantities x ex-works prices
2 Equipment freight and handling (1) x rate
3 Item estimate value (1)+(2)

3. Procedure points:

  1. Construction preliminaries and indirect costs both charge on base-period labour + base-period plant (items (1)+(3)), excluding base-period materials - of the three resources only labour and plant enter the base;
  2. price-exclusive freight and handling, the three differentials and fill material cost sit before charging: they enter direct works cost but never the (1)+(3) charging base;
  3. special construction increases charge not on (1)+(3) but on the corresponding compilation-period labour and plant;
  4. the vertical make-up (Figure 2.6.1): works cost = direct cost (direct works cost + construction preliminaries + special construction increases) + indirect costs.

Applicability limits

  • Applies to design estimates of large and medium railway capital construction projects (Article 1.0.2); works and equipment follow Tables 2.6.2 and 2.6.3 respectively.
  • Rates are not in this document; use with TB 10811-2024 cost norms (Article 1.0.6); base- and compilation-period prices and differential methods follow the relevant chapters.
  • Table 2.6.2 is the item-wise works procedure only; the assembly of comprehensive and overall estimates follows Sections 2.5 and 2.3.
  • The make-up and charging bases of highways (JTG 3830-2018) and building / municipal works (GB/T 50500 series) differ; this procedure must not be applied to them.

Further reading

  • TB 10801-2024: Article 2.6.1 (Figure 2.6.1 cost make-up), Article 2.6.2 (Table 2.6.2 works item procedure), Article 2.6.3 (Table 2.6.3 equipment item procedure).
  • Rates and values: TB 10811-2024 (preliminaries and on-cost rates, equipment freight and handling rates, labour / material / plant differential rules).
  • Companion system: the four-part seventeen-chapter estimate system and six-class static investment split, and the make-up and rates of preliminaries and on-costs - see the referenced cards.