Computation procedure and cost make-up of item-wise estimates (budgets) for railway works of construction and installation, including the equipment item-wise procedure - TB 10801-2024 Section 2.6 Tables 2.6.2 and 2.6.3
Per TB 10801-2024 Article 2.6.2 Table 2.6.2, the item-wise estimate (budget) for works of construction and installation runs: quota direct works cost = base-period labour + base-period materials + base-period plant; direct works cost = quota direct works cost + price-exclusive freight and handling + price differentials total (labour, material and plant differentials) + fill material cost; construction preliminaries = [(1)+(3)] x preliminaries rate, indirect costs = [(1)+(3)] x on-costs rate (the base being base-period labour + base-period plant, excluding materials); direct cost = direct works cost + construction preliminaries + special-construction increases; item estimate value = direct cost + indirect costs. The equipment item estimate (Table 2.6.3) = equipment cost + equipment freight and handling (equipment cost x rate).
Applicable Codes
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第2.6节(Table 2.6.2、Table 2.6.3)
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
Scope of the question
The cost make-up and item-wise computation (charging) procedure of design estimates under TB 10801-2024 Compilation Rules for Design Estimates and Budgets of Railway Capital Construction Works, Section 2.6 - covering the step-by-step build-up and review of item-wise estimate values for works of construction and installation and for equipment procurement.
Core conclusions
1. Item-wise computation for works of construction and installation (Article 2.6.2, Table 2.6.2):
| No. | Cost item | Method |
|---|---|---|
| 1 | Base-period labour | design quantities x base-period prices |
| 2 | Base-period materials | design quantities x base-period prices |
| 3 | Base-period plant | design quantities x base-period prices |
| 4 | Quota direct works cost | (1)+(2)+(3) |
| 5 | Price-exclusive freight and handling | separately listed items per the material supply plan in the execution plan and this rule |
| 6 | Labour differential | base-to-compilation period, per this rule |
| 7 | Material differential | base-to-compilation period, per this rule |
| 8 | Plant differential | base-to-compilation period, per this rule |
| 9 | Differentials total | (6)+(7)+(8) |
| 10 | Fill material cost | design quantities x surveyed prices |
| 11 | Direct works cost | (4)+(5)+(9)+(10) |
| 12 | Construction preliminaries | [(1)+(3)] x rate |
| 13 | Special construction increases | on compilation-period labour and plant |
| 14 | Direct cost | (11)+(12)+(13) |
| 15 | Indirect costs | [(1)+(3)] x rate |
| 16 | Item estimate value | (14)+(15) |
2. Equipment item-wise computation (Article 2.6.3, Table 2.6.3):
| No. | Cost item | Method |
|---|---|---|
| 1 | Equipment cost | design equipment quantities x ex-works prices |
| 2 | Equipment freight and handling | (1) x rate |
| 3 | Item estimate value | (1)+(2) |
3. Procedure points:
- Construction preliminaries and indirect costs both charge on base-period labour + base-period plant (items (1)+(3)), excluding base-period materials - of the three resources only labour and plant enter the base;
- price-exclusive freight and handling, the three differentials and fill material cost sit before charging: they enter direct works cost but never the (1)+(3) charging base;
- special construction increases charge not on (1)+(3) but on the corresponding compilation-period labour and plant;
- the vertical make-up (Figure 2.6.1): works cost = direct cost (direct works cost + construction preliminaries + special construction increases) + indirect costs.
Applicability limits
- Applies to design estimates of large and medium railway capital construction projects (Article 1.0.2); works and equipment follow Tables 2.6.2 and 2.6.3 respectively.
- Rates are not in this document; use with TB 10811-2024 cost norms (Article 1.0.6); base- and compilation-period prices and differential methods follow the relevant chapters.
- Table 2.6.2 is the item-wise works procedure only; the assembly of comprehensive and overall estimates follows Sections 2.5 and 2.3.
- The make-up and charging bases of highways (JTG 3830-2018) and building / municipal works (GB/T 50500 series) differ; this procedure must not be applied to them.
Further reading
- TB 10801-2024: Article 2.6.1 (Figure 2.6.1 cost make-up), Article 2.6.2 (Table 2.6.2 works item procedure), Article 2.6.3 (Table 2.6.3 equipment item procedure).
- Rates and values: TB 10811-2024 (preliminaries and on-cost rates, equipment freight and handling rates, labour / material / plant differential rules).
- Companion system: the four-part seventeen-chapter estimate system and six-class static investment split, and the make-up and rates of preliminaries and on-costs - see the referenced cards.
Keywords
- 铁路单项概预算计算程序
- 取费程序
- base to which percentage rates are applied
- cost of works (construction and installation)
- 施工措施费费率
- 间接费费率
- 价差
- TB 10801-2024