auxiliary works allowance (railway estimate item)
- 01
Highway works have no separate "engineering instruments and meters use fee" account: non-fixed-asset instruments go into the construction auxiliary fee (Table 3.1.6-8 rates), quota shift prices per JTG/T 3833-2018, and comparison with the railway and housing/municipal calibers
The highway JTG 3830-2018 system has no separate "engineering instrument…
JTG 3830—2018 公路工程建设项目概算预算编制办法(第3.1.6条第6款、Table 3.1.6-8、第3.3.7条)JTG/T 3833—2018 公路工程机械台班费用定额(总说明)JTG 3820—2018 公路工程建设项目投资估算编制办法2026-09-25 - 02
Can high-slope monitoring, tunnel monitoring measurement and other construction-monitoring fees be listed separately in highway estimates/budgets? They are inside the construction-auxiliary fee and may not be computed separately (JTG 3830-2018 clause 3.1.6 item 6)
No. Per JTG 3830-2018 "Measures for compiling estimates and budgets of h…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条第6款、Table 3.1.6-8JTG/T 3832-2018 · Budget Quota of Highway Engineering2026-09-25 - 03
Highway estimate/budget construction-auxiliary fee base: quota direct costs x Table 3.1.6-8 rates (JTG 3830-2018 clause 3.1.6 item 6)
The highway construction-auxiliary fee is charged on the base "quota dir…
JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.1条、第3.1.6条第6款、Table 3.1.6-8JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25