Can high-slope monitoring, tunnel monitoring measurement and other construction-monitoring fees be listed separately in highway estimates/budgets? They are inside the construction-auxiliary fee and may not be computed separately (JTG 3830-2018 clause 3.1.6 item 6)
No. Per JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects" clause 3.1.6 item 6 sub-item 3): "Construction-monitoring fees such as high-fill and soft-ground settlement monitoring, high-slope stability monitoring, bridge construction monitoring, tunnel construction monitoring measurement and advance geological forecast are contained in the construction-auxiliary fee and may not be computed separately." Correct practice: charge the construction-auxiliary fee on quota direct costs at Table 3.1.6-8 rates and describe the work content in the project execution plan; the JTG/T 3832-2018 budget quota system likewise has no standalone monitoring items.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.6条第6款、Table 3.1.6-8
- JTG/T 3832-2018 · Budget Quota of Highway Engineering
Topic Positioning
This card answers a frequent question in highway estimate/budget compilation: can high-slope stability monitoring fees, tunnel monitoring-measurement fees and other construction-monitoring fees be listed and charged separately? The conclusion rests on clause 3.1.6 item 6 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects".
Core Conclusions
No separate listing. JTG 3830-2018 clause 3.1.6 item 6 sub-item 3), verbatim: "Construction-monitoring fees such as high-fill and soft-ground settlement monitoring, high-slope stability monitoring, bridge construction monitoring, tunnel construction monitoring measurement and advance geological forecast are contained in the construction-auxiliary fee and may not be computed separately."
Correct charging (instead of "separate items"):
- The construction-auxiliary fee is charged on quota direct costs of each works class at Table 3.1.6-8 rates (stepped by works class — subgrade earth/rock, pavement, structures, tunnels etc.), not priced item by item.
- Its content: production tools and instruments use fees, inspection and test fees, positioning and re-measurement, handover, site clearing, and the above monitoring fees.
- The caliber is limited to "construction monitoring": this clause targets monitoring measurement performed by the contractor during construction. Third-party special testing commissioned separately by the owner belongs elsewhere (testing within supervision fees, or special studies within preliminary/research-test fees), but likewise may not be re-listed as "monitoring measurement"; clause 3.3.3 likewise bars technical-innovation research-test costs already covered by the construction-auxiliary fee from being repeated under research-test fees.
- Both the estimate and budget stages apply the same rule; no separate listing in either.
Boundary notes:
- No quota item exists: within JTG/T 3832-2018 there is no standalone "tunnel monitoring measurement / high-slope monitoring" item — consistent with "may not be computed separately"; do not hunt for a quota item or create a BOQ line.
- Inspection/test exclusions: tests of new structures and new materials, owner-demanded tests of certified materials, destructive component tests and other special inspections are outside the construction-auxiliary fee.
Applicable Boundaries
- Applies to highway estimate and budget compilation (JTG 3830-2018, both stages).
- "May not be computed separately" targets contractor construction monitoring within the construction-auxiliary fee caliber; owner-commissioned third-party special testing is outside it, but may not be re-listed as "monitoring measurement".
- The base is quota direct costs (quota labor + quota materials + quota plant cost at quota base prices), unlike other measures items (traffic-interference addition, works-transfer fee) on "quota labor + quota plant cost".
- This card does not touch work-safety costs, winter/rainy-season additions or other components of highway construction-installation costs.
Further Reading
- JTG 3830-2018 clause 3.1.6 item 6 (construction-auxiliary fee) and Table 3.1.6-8 (rates); the no-separate-listing detail is sub-item 3).
- The base definition is in clause 3.1.6 and the general notes ("quota direct costs"); quota items per JTG/T 3832-2018.
- The interface between research-test fees and the construction-auxiliary fee: clause 3.3.3.
- Related: the eight-item composition (clause 3.1.1) and the works-transfer fee (Table 3.1.6-9).
Keywords
- auxiliary works allowance (railway estimate item)
- 不得另行计算
- 施工监控费
- 高边坡监测
- 隧道监控量测
- 超前地质预报
- JTG 3830-2018
- separately billed item