Highway works have no separate "engineering instruments and meters use fee" account: non-fixed-asset instruments go into the construction auxiliary fee (Table 3.1.6-8 rates), quota shift prices per JTG/T 3833-2018, and comparison with the railway and housing/municipal calibers

The highway JTG 3830-2018 system has no separate "engineering instruments and meters use fee" account: (1) purchase, amortization, and repair of non-fixed-asset instruments are inside the construction auxiliary fee (production tools and utensils use fee), computed on each class of works' quota direct cost per Table 3.1.6-8 rates, construction monitoring costs included with no separate charge; (2) instrument shifts consumed within the budget quota are priced per the JTG/T 3833-2018 shift-cost quota (one of its 13 classes, 972 items; 7-component shift price) and enter the quota plant cost; (3) the employer-listed tools and instruments purchase fee (Clause 3.3.7) belongs to other construction costs and must not be mixed. Railway lists a separate "construction instruments use fee"; housing/municipal merges it into "construction plant and instruments use fee" — calibers differ, no cross-application.

Applicable Codes

  • JTG 3830—2018 公路工程建设项目概算预算编制办法(第3.1.6条第6款、Table 3.1.6-8、第3.3.7条)
  • JTG/T 3833—2018 公路工程机械台班费用定额(总说明)
  • JTG 3820—2018 公路工程建设项目投资估算编制办法
  • JTG/T 3831—2018 公路工程概算定额
  • JTG/T 3832—2018 公路工程预算定额

Topic Positioning

A full account of the fact that the highway system (JTG 3830-2018) has no separate "engineering instruments and meters use fee" account — how the costs are attributed along three lines — and the distinction from the railway (TB 10801-2024) and housing/municipal (Jian Biao [2013] No. 44) calibers, to prevent cross-industry misapplication.

Core Conclusions

  1. Highway estimates (budgets) have no separate "engineering instruments use fee" account; the railway or housing/municipal calibers must not be applied directly.
  2. Purchase, amortization, and repair of non-fixed-asset instruments -> merged into the "construction auxiliary fee" (JTG 3830-2018 Clause 3.1.6 item 6):
    • Verbatim: "The construction auxiliary fee covers production tools and utensils use fee, inspection and testing fee, and the costs of setting out and re-checking, handover, and site clearing. It is computed on the quota direct cost of each class of works at the Table 3.1.6-8 rates."
    • Verbatim: "The production tools and utensils use fee means the purchase, amortization, and repair costs of production tools, inspection and testing utensils, instruments, and meters not forming fixed assets, and the subsidies paid to workers for their own tools."
    • Formula: construction auxiliary fee = quota direct cost of each class of works x Table 3.1.6-8 rate; quota direct cost = quota labor + quota material + quota plant costs (all at quota base-period prices, unaffected by compilation-period market prices).
    • Note: construction monitoring costs — high-fill soft-foundation settlement monitoring, high-slope stability monitoring, bridge construction monitoring, tunnel monitoring and profiling, advance geological forecast, etc. — are already in the construction auxiliary fee and must not be charged again.
  3. Instrument shifts consumed within the budget quota -> priced per the plant shift-cost quota: JTG/T 3833-2018 companions JTG 3820-2018, JTG 3830-2018, JTG/T 3821-2018, JTG/T 3831-2018, and JTG/T 3832-2018, with 13 classes and 972 items including an "engineering testing instruments and meters" class; quota instrument shifts x shift price enter the quota plant cost (itself part of the auxiliary-fee base). The shift price has 7 components: depreciation (incl. smart information-management equipment), overhaul, maintenance, erection/dismantling auxiliary, labor, fuel/power, and others (e.g., vehicle and vessel tax). All machines work 8 h per shift (vessels included) except diving equipment (6 h) and transformers/switchgear (one day-and-night).
  4. Tools and instruments purchase fee (Clause 3.3.7 "production preparation fee"): the cost of the first set of non-fixed-asset equipment, instruments, meters, tools, and utensils needed for initial operation after handover — an employer-listed item of other construction costs, different in nature from items 2 and 3 (contractor costs); do not mix them in a budget.
  5. Cross-industry comparison (against misapplication):
    • Highway (JTG 3830-2018): no separate account — non-fixed-asset instruments into the construction auxiliary fee (rate-charged); quota shifts into the plant shift price;
    • Railway (TB 10801-2024): separate "construction instruments use fee = sum of quota shift consumptions x shift price", the price of 4 components (depreciation, maintenance, calibration, power);
    • Housing/municipal (Jian Biao [2013] No. 44 system): merged into "construction plant and instruments use fee" (= plant use fee + instruments use fee).

Applicable Boundaries

  • Applies to highway estimate and budget compilation (JTG 3830-2018 with JTG/T 3833-2018) and investment estimates (with JTG 3820-2018).
  • The Table 3.1.6-8 auxiliary-fee rates are banded by works class; values must be taken from the table — this card carries none.
  • Not for railway (TB 10801-2024) or housing/municipal (GB/T 50500 / Jian Biao [2013] No. 44) calibers.
  • Construction monitoring costs are inside the auxiliary fee; the tools purchase fee is an employer cost — no mixing in contractor budgets.

Further Reading

  • JTG 3830-2018 Clause 3.1.6 item 6 (construction auxiliary fee, production tools and utensils) with Table 3.1.6-8; Clause 3.3.7 (production preparation fee, tools purchase).
  • JTG/T 3833-2018 general notes (13 classes 972 items, shift hours, 7 components), the "engineering testing instruments and meters" class being the pricing basis.
  • Companion chain: JTG 3820-2018, JTG/T 3821-2018, JTG/T 3831-2018, JTG/T 3832-2018 (Appendix IV base prices).