Highway estimate/budget "other works construction costs": nine items and the project management fee rules (JTG 3830-2018 section 3.3)
Per clause 3.3.1 of JTG 3830-2018, the nine items of "other works construction costs" are: project management fee, research and test fees, project preliminary-stage fees, special appraisal (assessment) fees, combined trial-run fees, production-preparation costs, works traffic-maintenance management fees, works insurance, and other related costs. Project management fee (clause 3.3.2) has 5 sub-items: owner management fee, project informatization fee, supervision fee, design-document review fee, completion/acceptance testing fee; the owner management fee is computed progressively on quota construction-installation costs at Table 3.3.2-1 rates. Note: "land-use and demolition compensation costs" is a separate item in the 2018 edition (section 3.2), not among the nine.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.1 条、第 3.3.2 条及Table 3.3.2-1
- JTG 3830-2018 第 3.2 节(土地使用及拆迁补偿费单独成项)
Topic Positioning
This card answers what "project costs other than the works (land, consents, supervision, etc.)" comprise in highway works estimate and budget compilation: the nine-item list set out in clause 3.3.1 of JTG 3830-2018, Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects; the sub-items of the "project management fee" (clause 3.3.2); the base and method for calculating the owner's (employer's) management fee; and the account boundary against "land-use and demolition compensation costs". It applies to the compilation and review of highway works estimates and budgets.
Core Conclusions
- Nine items (clause 3.3.1 verbatim): project management fee, research and test fees, project preliminary-stage fees, special appraisal (assessment) fees, combined trial-run fees, production-preparation costs, works traffic-maintenance management fees, works insurance, and other related costs.
- Project management fee (clause 3.3.2) comprises the owner's (employer's) management fee, project informatization fee, supervision fee, design-document review fee, and taking-over (completion acceptance) testing fee. The owner's (employer's) management fee, the project informatization fee and the supervision fee are all costs of implementing project management, and may be used flexibly according to the work content and workload actually borne by the owner (employer), the contractor and the supervisor.
- Owner's (employer's) management fee: costs incurred by the owner (employer) for project initiation, preparation, construction, taking-over (completion acceptance) and summary work. They cover: staff wages, wage-related allowances and site allowances, social insurance contributions (basic pension, basic medical, unemployment and work-injury), housing provident fund, staff welfare, trade union funds, labour protection, office expenses, meeting expenses, travel and transport, use of fixed assets (depreciation, repair or rental of office and living buildings, vehicles, communication equipment, survey and testing equipment and instruments), purchase of minor fixed assets, recruitment of production workers, technical books and documentation, staff education and training, tendering management, contract notarization, legal counsel, consulting, temporary works and site establishment costs, completion cleanup, taking-over (completion acceptance) fees (including acceptance fees required by other industries or departments and the owner's preparation of taking-over documents), various taxes and levies (property tax, vehicle and vessel tax, stamp duty, etc.), audit fees for auditing the whole process of preliminary work, project implementation and final accounts, domestic and overseas financing costs (excluding construction-period loan interest), business hospitality, works quality and safety management costs, and other administrative expenditure.
- Calculation rule: the owner's (employer's) management fee is calculated on the base of the norm-based cost of works, at the rates in Table 3.3.2-1, using the progressive method.
- Account boundary (error-prone): in the JTG 3830-2018 cost composition, "land-use and demolition compensation costs" is a separate item (section 3.2), standing alongside the cost of works (construction and installation), project costs other than the works, contingency and construction-period loan interest, and is not among the nine items; this differs from the 2007 edition of the rules (JTG B06-2007, which included land acquisition and demolition compensation within other costs), so do not group it among the nine items when compiling estimates and budgets under the 2018 system.
Applicable Boundaries
- Applies to the compilation of estimates and budgets for highway works construction projects (JTG 3830-2018 pricing system); railway (TB 10811-2024) and building/municipal (GB/T 50500 BOQ-based pricing) cost compositions follow different rules and cannot be applied by analogy.
- The nine-item list reflects the 2018 edition of the rules; use this new basis when compiling budgets under the 2018 system and do not mix it with the old cost items of earlier highway compilation rules.
- The specific rate values and progressive bands for the owner's (employer's) management fee are governed by the text of Table 3.3.2-1; this card contains no specific rates or project amounts. The project informatization fee and supervision fee may be pooled for use, but must not be listed again under other headings.
Further Reading
See Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects, JTG 3830-2018: clause 3.3.1 (the nine items of project costs other than the works), clause 3.3.2 and Table 3.3.2-1 (five sub-items of the project management fee; rate table for the owner's (employer's) management fee), the remaining clauses of section 3.3 (definitions and listing rules for research and test fees, project preliminary-stage fees, special appraisal (assessment) fees, combined trial-run fees, production-preparation costs, works traffic-maintenance management fees, works insurance and other related costs), and section 3.2 (land-use and demolition compensation costs, a separate item); section 3.1 (composition of the cost of works (construction and installation)) can be read alongside the dedicated card on that composition.
Keywords
- project costs other than the works (land, consents, supervision, etc.)
- JTG 3830-2018
- compilation rules for highway estimates and budgets (JTG 3830)
- 九项费用
- 建设项目管理费
- 建设单位(业主)管理费
- 土地使用及拆迁补偿费
- 概预算费用构成