Highway works estimate/budget works insurance fee rules: base = construction-installation cost (excluding equipment), rate 0.4% (JTG 3830-2018 clause 3.3.9)
Per clause 3.3.9 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", the works insurance fee is computed on the base of the construction-installation cost (excluding equipment cost) at a rate of 0.4%, covering contractor's all risks (CAR) and third-party liability insurance. The corresponding formula in summary table 36 is "works insurance fee = (construction-installation cost − equipment purchase cost) x rate", i.e. item (12) minus item (4), then the rate applied — the same at both estimate and budget stages.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.3.9条
- JTG 3830-2018 综表36
Topic Positioning
The charging rules for the works insurance fee within "other construction costs" of highway estimates (budgets): computation base, rate, fee composition (JTG 3830-2018 clause 3.3.9 and summary table 36).
Core Conclusions
Per JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", clause 3.3.9:
- Definition: the works insurance fee is the cost of insurances the construction enterprise arranges per the contract terms during contract execution, including contractor's all risks and third-party liability insurance.
- CAR: insurance for the permanent works, temporary works and equipment, and for materials and equipment already delivered to site for the permanent works.
- Third-party liability: insurance covering liability for loss of or damage to property (other than the works themselves) or death or injury of persons (other than the employer's and contractor's employees) caused by carrying out the contract works.
- Charging rule: the works insurance fee is computed on the base of the construction-installation cost (excluding equipment cost) at a 0.4% rate.
- The corresponding formula in summary table 36 is "works insurance fee = (construction-installation cost − equipment purchase cost) x rate", i.e. item (12) construction-installation cost minus item (4) equipment purchase cost, times the rate; rate 0.4%, common to the estimate and budget stages, regardless of works class.
Applicable Boundaries
- Applies to compiling estimates and budgets of highway construction projects (JTG 3830-2018 system); the works insurance fee is one of the nine components of "other construction costs" (clause 3.3.1), listed under item (14) other construction costs in summary table 36.
- The computation base is expressly the construction-installation cost (excluding equipment cost): equipment purchase cost does not participate; insurance already counted in equipment purchase cost must not be double-charged.
- This is a charging rule; the other "other construction costs" sub-items — production preparation fee (clause 3.3.7), traffic-maintenance management fee (clause 3.3.8) etc. — are listed separately and do not overlap.
Further Reading
- JTG 3830-2018 clause 3.3.9 (works insurance fee text), clause 3.3.1 (nine components of other construction costs), summary table 36 (fee formulas, incl. works insurance fee = (12) − (4) x rate).
- Clauses 3.3.2-3.3.10 of the same measures govern the other sub-items of "other construction costs" — consult for comparison.