Highway 2018 system item-numbering rule for estimates and budgets: five levels - part (1 digit), item (2), sub-item (2), section (2), detail (2) (JTG 3830-2018 Clause 2.4.3; see Appendix B)

Per Clause 2.4.3 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway engineering construction projects", the estimate/budget item number consists of 5 levels: part (1 digit), item (2 digits), sub-item (2 digits), section (2 digits), detail (2 digits), expanded layer by layer in that order — see Appendix B. Clause 2.4.1 provides: the serial numbers and contents of parts 1-5 and of the "items" remain unchanged when compiling; missing sub-item content may be added nearby as needed and arranged in the order actually appearing at the level concerned, without keeping the serial numbers of missing items below "item" level.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.4节(第2.4.1~2.4.3条)及App. B

Topic Positioning

The composition rule of item numbers in the estimate and budget project tables of the highway 2018 system (JTG 3830-2018 "Measures for compiling estimates and budgets of highway engineering construction projects"): the digit widths of the five levels (part, item, sub-item, section, detail), and the compilation and arrangement rules when the project content does not fully match the project table.

Core Conclusions

  1. Levels and digit widths of item numbers (Clause 2.4.3, verbatim): "Item numbers consist of part (1 digit), item (2 digits), sub-item (2 digits), section (2 digits), detail (2 digits), expanded layer by layer as part, item, sub-item, section, detail; see Appendix B for the item numbering." A full number thus has the form X-XX-XX-XX-XX (part.item.sub-item.section.detail), 1+2+2+2+2 = 9 digits in all.

  2. Project-table compilation rule (Clause 2.4.1): estimates and budgets shall be compiled per the sequence and contents of the project table. Where the works and cost items actually arising do not fully match the table, the serial numbers and contents of parts 1-5 and of the "items" remain unchanged; sub-items below "item" keep their serial numbers and contents when cited; missing sub-item content may be added nearby as needed, arranged in table order at the level actually appearing, and the serial numbers of missing items below "item" are not kept.

  3. Five-part framework (Clause 2.4.2): Part 1 cost of works (construction and installation) (item 1 temporary works; item 2 subgrade works; item 3 pavement works; item 4 bridge and culvert works; item 5 tunnel works; item 6 intersection works; item 7 traffic engineering and route facilities; item 8 greening and environmental protection works; item 9 other works; item 10 special fees [1. construction site development fee; 2. statutory work safety levy (earmarked funds)]); Part 2 land use and demolition compensation cost; Part 3 project costs other than the works (land, consents, supervision, etc.); Part 4 contingency; Part 5 construction-period loan interest.

Applicable Boundaries

  • The numbering rule applies to compiling estimate and budget documents under the JTG 3830-2018 system; the detailed project-table contents are governed by Appendix B of the measures.
  • This "item number" attaches projects in the estimate/budget project table; it is not the same system as the quota item codes themselves (budget-quota item codes organized by chapter-section-item, used for pricing): the two are used in tandem — item numbers carry the project list, quota codes carry the pricing — do not mix them.
  • When contents do not fully match the table, the serial numbers and contents of the five parts and the "items" must not be altered; sub-items may only be added nearby below "item" level, arranged in table order at the level actually appearing, without keeping numbers for missing items.

Further Reading

See JTG 3830-2018 Section 2.4 (Clauses 2.4.1-2.4.3) and Appendix B "estimate and budget project table"; read together with Chapter 3 of the same measures for cost composition and charging rules (the project table and the cost-computation system share one origin).