Highway completion (handover) acceptance test-and-inspection fee rates and rules: expressway 23,500 yuan/km etc. per table 3.3.2-5, chargeable length and lane corrections (JTG 3830-2018 clause 3.3.2 item 5; same caliber in JTG 3820-2018)

Per clause 3.3.2 item 5 and table 3.3.2-5 of JTG 3830-2018: completion (handover) acceptance test fees — expressway 23,500 yuan/km; class-I highway 17,000 yuan/km; class-II 11,500 yuan/km; class-III and below 5,750 yuan/km (covering subgrade, pavement, culverts, passages, section safety facilities and electromechanical, buildings, greening, environmental protection and other works). Roads charge on mainline subgrade length; bridges on the sum of mainline bridges + separated interchanges + ramp bridges; tunnels on single-bore length; expressway/class-I at four lanes, class-II and below at two lanes; each added lane raises road fees 10% and bridge/tunnel fees 15%; class-II-and-below bridge/tunnel works at 40% of the tabulated fee. JTG 3820-2018 investment estimation measures carry the same caliber.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.2 条第 5 款、Table 3.3.2-5
  • JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects 第 3.3.2 条

Topic Positioning

This card covers the charging standards and rules of the completion (handover) acceptance test-and-inspection fee for highway projects: the class rates of table 3.3.2-5 (yuan/km), the chargeable-length calibers, lane correction coefficients and bridge/tunnel reductions, plus the same caliber at the investment-estimation stage of JTG 3820-2018 — for taking this fee when compiling highway estimates, budgets and investment estimates.

Core Conclusions

The completion (handover) acceptance test fee is the cost, before completion (handover) acceptance, of qualified highway quality testing units commissioned by the employer (owner) or the quality supervision authority to test the project quality and issue test opinions per relevant provisions, and of bridge dynamic (static) load tests or other special tests (JTG 3830-2018 clause 3.3.2 item 5).

Table 3.3.2-5 completion (handover) acceptance test fee (road works, yuan/km):

  • Expressway: 23,500 yuan/km
  • Class-I highway: 17,000 yuan/km
  • Class-II highway: 11,500 yuan/km
  • Class-III and below: 5,750 yuan/km
  • Note: covering subgrade, pavement, culverts, passages, section safety facilities and electromechanical, buildings, greening, environmental protection and other works.

Chargeable length: road works on mainline subgrade length; bridges on the sum of mainline bridges, separated interchanges and ramp bridges; tunnels on single-bore length.

Lane corrections:

  • Roads: expressways and class-I at four lanes, class-II and below at two lanes; each additional lane adds 10% of the table 3.3.2-5 fee. Example: six-lane expressway = 23,500 x (1 + 2 x 10%) = 28,200 yuan/km (four-lane base, the 2 extra lanes each +10%).
  • Bridges and tunnels at bidirectional four lanes; each additional lane adds 15%.
  • Class-II-and-below bridge/tunnel works at 40% of the table 3.3.2-5 fee.

Fee attribution: a sub-item of the project management fee within other construction costs (clause 3.3.2), listed separately in the estimate (budget) other-costs table. The same caliber appears in JTG 3820-2018 "Measures for compiling investment estimates of highway construction projects" clause 3.3.2 — estimation-stage rates and rules match the estimate/budget stage; the two documents cross-confirm.

Applicable Boundaries

  • Applies to highway estimate, budget and investment-estimate compilation; the rates cover completion (handover) acceptance testing only, not in-construction testing.
  • Roads and bridges/tunnels are computed separately: bridge/tunnel works do not simply take the road rate — apply the lane corrections and reductions (class-II-and-below bridge/tunnel 40%).
  • Excludes the research and test fee (clause 3.3.3 — special studies verifying design data, S&T three-item fees and ordinary appraisals under construction auxiliary fees, listed separately); mind the fee boundaries to avoid double counting.
  • The tabulated rates are from the 2018 measures; compile per the current valid edition.

Further Reading

  • JTG 3830-2018 clause 3.3.2 item 5 and table 3.3.2-5 (road rates); JTG 3820-2018 clause 3.3.2 (same caliber).
  • Neighbouring fees: 3.3.3 research and test fee; 3.3.4 project preliminary-work fee (progressive on quota construction-installation cost per table 3.3.4); 3.3.5 special evaluation fee; 3.3.6 joint commissioning fee (quota construction-installation cost x 0.04%); 3.3.7 production preparation fee — mind boundaries when compiling other costs.
  • Related existing card: card_069ba94c (JTG 3830-2018 nine components of other construction costs and project management fee rules) gives this item's full positioning.