Claims for late delivery of employer-supplied (free-issue) plant in EPC projects: the claim basis under Civil Code Articles 803/804 plus the cost, time and reasonable-profit rules of GF-2020-0216 General Conditions 6.2.1/8.7.1(4)/8.9.1, an affirmative/negative scenario matrix and the limits of compensation
Yes. Where employer-supplied plant is delivered late for reasons attributable to the employer, the contractor may claim extension of time and recovery of suspension and idle-cost losses: under Civil Code Article 803, 'where the employer fails to provide raw materials, plant, site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the construction period and claim compensation for suspension, idling and other losses'; GF-2020-0216 General Conditions 6.2.1 provides that where delivery dates are delayed or delivery places changed for reasons attributable to the employer, 'the employer shall bear the resulting additional costs and/or delay and pay the contractor a reasonable profit', and 8.7.1 item (4) lists 'the employer's failure to provide the materials and plant as agreed under item 6.2.1, causing delay and/or additional cost' among the events for which the employer bears time and cost and pays a reasonable profit. Conversely, where the plant is procured by the contractor itself (contractor supply), the delay is due to force majeure, or the contractor failed to submit the free-issue delivery plan 28 days in advance as agreed so that the interface slipped, the claim fails or the loss stays with the contractor; suspension and idle-time losses are payable in suit but enjoy no priority right to payment out of the works proceeds (Fa Shi [2026] No. 12 Article 17(2)).
Applicable Codes
- 《中华人民共和国民法典》第八百零三条、第八百零四条、第五百八十四条、第五百九十条、第五百九十一条、第四百六十五条
- 住建部、市场监管总局《建设项目工程总承包合同(示范文本)》GF-2020-0216(建市〔2020〕96号)通用合同条件 6.1、6.2.1、6.2.2、6.2.3、8.7.1、8.7.4、8.9.1、8.9.2、第13条、第15条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.6.1、3.6.5、8.11.3、8.11.5、8.11.9、8.11.10条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第二十三条(2026年6月30日施行)
Issue and scope
EPC design-build turnkey projects: where employer-supplied (free-issue) plant is delivered late for reasons attributable to the employer, can the contractor claim extension of time, suspension and idle-cost losses, or even reasonable profit? The card gives the statutory claim basis (Civil Code Articles 803/804), the model-text clauses of the EPC contract GF-2020-0216 (General Conditions 6.2.1, 6.2.2, 6.2.3, 8.7.1, 8.9.1), an affirmative/negative scenario matrix and the compensation limits, for claim strategy, settlement negotiation and dispute defence.
Core conclusions
1. Conclusion and core reasoning Yes. Plant (permanent works equipment) ranks with raw materials among the items the employer must supply at the agreed time and to the agreed requirements; the employer's breach triggers the statutory extension and compensation, and the EPC model text at contract level further allocates the cost, time and reasonable profit consequences of 'delayed delivery dates' to the employer.
2. Statutory claim basis (text)
- Civil Code Article 803: 'Where the employer fails to provide raw materials, plant, site, funds or technical data at the agreed time and to the agreed requirements, the contractor may extend the construction period and claim compensation for suspension, idling and other losses.'
- Civil Code Article 804: 'Where the works are stopped or slowed mid-course for reasons attributable to the employer, the employer shall take measures to remedy or mitigate the loss and compensate the contractor for the suspension, idling, re-handling, plant relocation, stockpiling of materials and components and other losses and actual costs thereby caused.'
- Compensation cap and mitigation: Civil Code Article 584 - damages 'shall be equivalent to the loss caused by the breach, including the benefit obtainable on performance of the contract; but they may not exceed the loss the defaulting party foresaw, or should have foreseen, at the time of contracting'; Article 591 - 'where a party breaches, the other party shall take appropriate measures to prevent aggravation of the loss; failure to take such measures bars recovery of the aggravated part.'
- Privity of contract: Civil Code Article 465 - 'a contract formed in accordance with law is binding only on the parties'. Late delivery of contractor-procured plant (contractor supply) is a sale-contract breach against the supplier, which alone can be sued; the employer bears no liability for time or cost.
3. EPC contract basis (GF-2020-0216 General Conditions, issued with Jian Shi [2020] No. 96)
- 6.2.1 Employer-provided materials and plant: where the employer supplies itself, the particular-conditions annex 'Schedule of Employer-Supplied Materials and Plant' shall state the variety, specification, model, main parameters, quantity, unit rate, quality grade and handover place; 'the contractor shall notify the engineer in writing 28 days in advance of the delivery plan for the materials and plant according to the programme'; 'the employer shall notify the contractor 7 days before arrival, and the contractor, jointly with the engineer, shall inspect at the delivery place within the agreed time'; 'where the employer needs to change the delivery plan, the contractor may not refuse, and the change is handled under Clause 13 [Variations and Adjustments], the employer bearing the contractor's additional costs and the resulting delay'; the core liability clause: 'where the specifications, quantity or quality of the employer-provided materials and plant do not conform to the contract, or the delivery date is delayed or the delivery place changed for reasons attributable to the employer, the employer shall bear the resulting additional costs and/or delay and pay the contractor a reasonable profit.'
- 8.7.1 (employer-caused delay): 'where during performance of the contract the following cause delay and/or additional cost, the employer bears the resulting delay and/or additional cost and shall pay the contractor a reasonable profit...(4) the employer's failure to provide the materials and plant as agreed under item 6.2.1 [Employer-provided materials and plant], causing delay and/or additional cost'; the same item also lists 'suspension of the works for reasons attributable to the employer' and 'any delay, obstruction or hindrance caused or occasioned by the employer, the employer's representative, the engineer or any third party engaged by the employer'.
- 8.9.1 (suspension by the employer): 'the additional costs and/or delay caused to the contractor by complying with a notice of suspension are borne by the employer, which shall also pay the contractor a reasonable profit, except where the employer's suspension is caused by the contractor.'
- 6.2.3(1) (custody and inspection of free-issue plant): 'employer-supplied materials and plant, once counted and received by the contractor, are kept properly by the contractor, at the contractor's custody cost... before use the contractor conducts the necessary inspection, the inspection cost being borne by the employer; non-conforming items may not be used.'
4. Affirmative / negative scenario matrix
| Scenario | Conclusion | Basis |
|---|---|---|
| Plant listed in the Schedule of Employer-Supplied Materials and Plant; late delivery attributable to the employer affecting the programme | Extension of time + additional cost + reasonable profit | Civil Code 803; GF-2020-0216 General 6.2.1, 8.7.1(4) |
| Employer changes the free-issue delivery plan, delivery place or delivery mode | Additional cost and delay borne by the employer | GF-2020-0216 General 6.2.1; GB/T 50500-2024 Clause 3.6.5 |
| Suspension notice by the employer or engineer issued while awaiting free-issue plant | Additional cost and delay borne by the employer, plus reasonable profit | GF-2020-0216 General 8.9.1 |
| Inspection on arrival of free-issue plant; non-conforming plant may not be used | Inspection cost borne by the employer; non-conforming plant barred from use | GF-2020-0216 General 6.2.3(1) |
| Late plant, but no signed extension record obtained | Extension still claimable if the contractor proves it applied to the employer or the supervisor within the contract period on contractual grounds | Fa Shi [2020] No. 25 Article 10 |
| Plant procured by the contractor itself (contractor supply); supplier delivers late | Claim fails; sue the supplier only; the employer bears no time or cost | Civil Code 465; GF-2020-0216 General 6.2.2 |
| Contractor failed to submit the free-issue delivery plan 28 days in advance as agreed, causing interface friction | That delay and cost stay with the contractor (causal chain broken) | GF-2020-0216 General 6.2.1 |
| Delay due to force majeure | Exemption in whole or in part as affected; time extendable but suspension and idle losses not compensable | Civil Code 590; GF-2020-0216 General 8.9.3 |
| Delay not on activities affecting the programme (alternative work fronts exist) | No time claim; cost losses must be proven actual with causation | Civil Code 803; GB/T 50500-2024 Clause 8.11.9 |
| Contractor failed to take appropriate measures, aggravating the loss | The aggravated part is not compensable | Civil Code 591 |
| Asserting a priority right to payment out of the works proceeds for suspension and idle losses | Unsupported (the debt is payable in suit but carries no priority ranking) | Fa Shi [2026] No. 12 Article 17(2) |
5. Compensation scope and pricing-standard basis
- GB/T 50500-2024 Clause 3.6.5: 'where the employer-provided materials (e.g. specification, model, quality) do not conform to the contract or fail to meet the delivery plan, or the delivery date is delayed or the delivery place or mode changed for reasons attributable to the employer... where the contractor's time is thereby extended, the affected duration shall be reasonably extended under Clause 8 of this standard and the contractor's losses compensated, including profit.'
- Clause 8.11.9: for suspension, waiting, reduced efficiency or extension of time not caused by the contractor, the claimable items include 'idle labour costs of personnel already on site and unable to work', 'loss costs of materials already on site and unable to be used', 'standing costs of construction plant already on site and unable to work', other cost losses, and the reasonable time delayed.
- Clause 8.11.10: where the employer is responsible (including 'unqualified quality, late provision or changed delivery place of employer-provided materials' and 'employer-caused delay, suspension, or failure to resume on time after suspension'), then beyond the losses claimed under Clause 8.11.9, profit is also claimable.
6. Procedure and old/new cut-over
- Claim procedure (GB/T 50500-2024 Clause 8.11.3, absent agreement): submit a written Notice of Claim within 28 days of the event; submit the claim report within a further 28 days of the notice (causes, the contractual grounds relied on, the cost or days claimed, supporting records and the cost build-up sheets); claim cost and time together; for continuing effects, further notices at intervals no longer than 28 days, with the final report within 28 days after the event ends. A prejudiced party that fails to claim within the agreed time is, save for contrary agreement or provision of laws and regulations, deemed to have waived the claim.
- Cut-over: Fa Shi [2026] No. 12 Article 23 - 'this interpretation takes effect on 30 June 2026 and applies to first-instance construction contract disputes newly accepted after that date'; the divide runs by the date of acceptance, not the date of the underlying conduct.
Boundaries of application
- The plant must genuinely be 'employer-supplied': listed in the particular-conditions annex Schedule of Employer-Supplied Materials and Plant or otherwise agreed in writing. A bare assertion of 'free issue' without a schedule, delivery plan or arrival records is treated as contractor supply, with the time and cost risk on the contractor.
- GF-2020-0216 is a model text; its general conditions bind only through incorporation in the contract (or serve as interpretive reference for gaps); where the particular conditions provide otherwise, they prevail.
- The claim basis for profit lies in the contract (General Conditions 6.2.1, 8.7.1(4), 8.9.1) and the pricing standard (GB/T 50500-2024 Clauses 3.6.5, 8.11.10); the text of Civil Code Articles 803/804 itself lists only extension of time and loss compensation, not profit; where the contract does not incorporate those texts, a profit claim lacks basis.
- Compensation is limited to what is 'actually incurred, provable, not aggravated by failure to mitigate, and not beyond the foreseeable'; idle labour is measured by the personnel actually stranded on site, plant standing by rental fee or depreciation - it may not be back-calculated from normal construction output value.
- GB/T 50500-2024 is a recommended national standard; its claim-procedure and cost clauses bind the parties only after contractual incorporation.
- Article 17(2) of Fa Shi [2026] No. 12 is subject to the Article 23 time limit (newly accepted first-instance cases only).
Further reading
- Civil Code Articles 803, 804, 584, 590, 591, 465, 807.
- Jian Shi [2020] No. 96, Model Contract for EPC Turnkey Execution of Construction Projects, GF-2020-0216 General Conditions: Clause 6.1 (method of execution), item 6.2.1 (employer-provided materials and plant), item 6.2.2 (contractor-provided materials and plant), item 6.2.3 (custody of materials and plant), item 8.7.1 (employer-caused delay), item 8.7.4 (exceptionally adverse climate), items 8.9.1/8.9.2 (suspension of work), Clause 13 (variations and adjustments), Clause 15 (force majeure).
- GB/T 50500-2024 Clauses 3.6.1, 3.6.5, 8.11.3, 8.11.5, 8.11.9, 8.11.10.
- Fa Shi [2020] No. 25 (Interpretation (I)) Article 10 (extension claimable without a signed extension record); Fa Shi [2026] No. 12 (Interpretation (II)) Article 17 (suspension and idle losses carry no priority right), Article 23 (effective date and acceptance divide).
- Item-by-item computation of suspension and idle losses (idle labour, plant standing, time-related overheads during suspension, profit during suspension) and the evidence checklist: see the companion card on the same topic.