Charging boundary of material price differentials (construction-period adjustment): VAT only - no overheads or profit, and no participation in the charging bases of total-price preliminaries or statutory levies (GB/T 50500-2024 Article 3.3.5 paragraph 4, Article 8.7.6)
Differentials formed by construction-period material price settlement adjustments carry VAT only - no overheads or profit, and they do not join the charging bases of total-price preliminaries or statutory levies. Basis: GB/T 50500-2024 Article 3.3.5 paragraph 4 - differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT but not overheads or profit; Article 8.7.6 items 3 (preliminaries) and 7 (overheads and profit) are listed among fees not adjusted for cost fluctuation; and since total-price preliminaries charge on labour plus plant, and statutory levies on quota labour, material differentials - being material in nature - fall outside both bases anyway. Express contract terms prevail.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.5条、第8.7.6条、第8.7.2条、App. A.2.1、App. G.2Table G.2.1-1/Table G.2.1-2
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 Table 2.6.2
- 京建发〔2021〕404号
- 湖北省建筑安装工程费用定额(2024)
- 陕西省建设工程费用规则(配套 DB 61/T 5126-2025)
Scope of the question
Whether the differentials formed by construction-period material price adjustment (make-up payment) join the charging of total-price preliminaries and statutory levies - i.e. whether they enter those bases - with grounds at both the provisions level and the charging-base level.
Core conclusions
Answer: no. Differentials carry VAT only, entering neither the total-price preliminaries base nor the statutory levies base (save for express contract terms).
1. Positive boundary - GB/T 50500-2024 Article 3.3.5 paragraph 4
- Differentials of labour, materials and the fuel-power element of plant within all-in unit rates carry VAT, not overheads or profit.
- Differentials from cost changes carry VAT only; the risk on overheads and profit is priced by tenderers as risk fees in their offers. The clause makes a differential a pre-tax sum with a single VAT tail - no rate-derived fees on a labour-material-plant base (preliminaries, levies, overheads, profit) stack on it.
2. Negative prohibition - GB/T 50500-2024 Article 8.7.6 Save as agreed, the following fees of performing and completing the works do not adjust the total price or unit rates for cost changes: ... 3 preliminaries ... 7 overheads and profit ... Preliminaries being listed as non-adjusting, differentials can neither raise them nor enter their base; total-price preliminaries are themselves lump-sum and, save the few 7.3.1 exceptions, not re-measured - no basis-merging either.
3. The adjustment clauses compute differentials only GB/T 50500-2024 Article 8.7.2: where market prices of the agreed adjustable elements (labour, materials, fuel-power) move beyond the agreed band - or, absent one, beyond 5% - the price adjusts by one of the Appendix A methods. A.2.1's published-price method computes dP = sum(dC x Q) - a pure differential of adjustable factors, no rate-derived items; the adjustable factor list must be agreed in advance per Appendix G.2 Tables G.2.1-1 (price-information method) / G.2.1-2 (index method).
4. The charging-base logic (derivable even without 8.7.6)
- Total-price preliminaries (including mandatory HSE provisions and other total-price items) charge on labour + plant within work-item and unit-rate preliminaries (local cost norms, e.g. Hubei 2024: HSE provisions = (labour + plant) x rate).
- Statutory levies charge on quota labour (e.g. Beijing's sectoral levies at 14.5%-24.9% on labour per the budget consumption standard). Material differentials are material in nature - in neither the labour base nor the labour-plus-plant base - so they enter neither.
5. Railway parallel TB 10801-2024 Table 2.6.2: the material differential is item 7, differentials total item 9, merged into direct works cost; construction preliminaries and on-costs charge on base-period labour (1) + base-period plant (3) x rates - differentials enter neither base.
6. Local wording in the same direction Shaanxi cost rules (with DB 61/T 5126-2025): absent or unclear contract terms - adjusted parts of labour, materials and plant within all-in unit rates are treated as differentials carrying VAT only; provisional material sums likewise.
Applicability limits
- Precondition: the contract already provides for cost-fluctuation adjustment; 8.7.6 opens with save as agreed - express terms folding differentials into preliminaries or levies bases prevail.
- What does not join are the rate-derived fees (total-price preliminaries, levies, overheads, profit); VAT still accrues.
- Whether a differential arises at all follows the contractual band, the 5% rule (8.7.2) and Appendix A methods, with scope and quantities per Appendix G.2 and the contract.
- Industry and regional norms differ in rates and bases (railway preliminaries / on-costs, highway preliminaries); actual charging follows the current local (industry) cost norms and the contract - the rates cited here are illustrative only.
Further reading
- GB/T 50500-2024: Article 3.3.5 paragraph 4, Article 8.7.6, Article 8.7.2; Appendix A.2.1; Appendix G.2 Tables G.2.1-1 and G.2.1-2.
- Railway: TB 10801-2024 Table 2.6.2.
- Local: Hubei works cost norms (2024) total-price preliminaries procedure; Jing Jian Fa [2021] No. 404 levies base and rates; Shaanxi cost rules (with DB 61/T 5126-2025).
Keywords
- material price differential
- 价差结算补差
- 取费边界
- 总价措施项目费
- 规费计费基数
- 只计取增值税
- GB/T 50500-2024
- 措施项目费不因物价变化调整