Definition and pricing rules for preliminary items that cannot be measured precisely (Jing Jian Fa [2021] No. 11: class with issued management documents vs class without such documents)

Preliminary items that cannot be measured precisely = preliminary items whose quantities cannot be computed precisely from the dimensions shown on the construction drawings, whose cost is directly related to the construction method statement and/or the duration of input, and which are generally priced as a lump sum per item (Jing Jian Fa [2021] No. 11). Such items not covered by the "cost indicators" in the published construction cost information for Beijing fall into two classes: a) those with issued management documents (mandatory health, safety and environmental (HSE) provisions, acceleration measure increase costs, and off-site haulage and disposal of construction waste) are governed by those documents, and the cost must not fall below the floor cost standards; b) those without corresponding management documents (e.g. secondary handling, protection of completed works and equipment, night-work increase costs) should preferably be added as separately billed items with clearly defined scope of work and calculation rules, and reasonably determined by the contractor's own estimation on market-based pricing principles in accordance with the method statement. For protection of completed works: Beijing has no official percentage rate, so a percentage-rate approach has no documentary basis; the actual-cost method plus a separately billed item should be used.

Applicable Codes

  • 京建法〔2021〕11号
  • 京建发〔2021〕404号
  • 京建法〔2019〕9号
  • 京建法〔2019〕4号
  • 京建法〔2017〕27号
  • GB/T 50500-2024 第3.2.6条
  • GB/T 50875-2013 第2.2.56条
  • T/YJXB 0001-2023 第5.0.1条

Topic Positioning

This card covers the definition and pricing rules for "preliminary items that cannot be measured precisely": which preliminary items fall into this category, how Beijing (Jing Jian Fa [2021] No. 11) handles them in two classes, and the pricing basis and documentary source for each class. It applies to tender (priced offer) preparation, compilation of preliminaries and final account review for BOQ-priced works, and also serves as a framework for judging "whether a given preliminary cost has an official percentage-rate basis".

Core Conclusions

  1. Definition (Jing Jian Fa [2021] No. 11): preliminary items that cannot be measured precisely = preliminary items whose quantities cannot be computed precisely from the dimensions shown on the construction drawings, whose cost is directly related to the construction method statement and/or the duration of input, and which are generally priced as a lump sum per item.
  2. Beijing's two-class treatment of such items not covered by the "cost indicators" in the published construction cost information for Beijing: a) With issued management documents — the documents must be followed, and the cost must not fall below the floor cost standards:
    • Mandatory health, safety and environmental (HSE) provisions: Jing Jian Fa [2019] No. 9 + Jing Jian Fa [2021] No. 404;
    • Acceleration measure increase costs: Jing Jian Fa [2019] No. 4 (2018 duration quota norms);
    • Off-site haulage and disposal of construction waste: Jing Jian Fa [2017] No. 27 + Jing Jian Fa [2021] No. 404. b) Without corresponding management documents — e.g. secondary handling, protection of completed works and equipment, night-work increase costs: it is recommended to add these as separately billed items with clearly defined scope of work and calculation rules; determine them reasonably by the contractor's own estimation on market-based pricing principles in accordance with the method statement.
  3. Direct implication for protection of completed works (protection of completed works and equipment): Beijing has no official percentage rate, so applying a percentage-rate method has no documentary basis; the actual-cost method should be used (Σ protected quantity × protection unit price + guarding labour + removal and haulage, with protection materials amortised into the unit price on a turnover basis) together with a separately billed item, and the basis of determination should be stated in the explanatory notes of the estimate. Article 3.2.6 of GB/T 50500-2024 includes "protection of completed works, final cleaning and site clearance and demobilisation" within the scope of preliminary items; Article 2.2.56 of GB/T 50875-2013 defines protection of completed works as the costs of necessary protective measures taken for completed works and equipment before taking-over (completion acceptance).

Applicable Boundaries

The classification framework in this card comes from Jing Jian Fa [2021] No. 11 and applies to BOQ-priced works in Beijing (building works, municipal works and others under the Jing Jian Fa system); for other regions, local norms for on-costs and expenses and cost-management documents must be checked for a similar classification, and Beijing document numbers cannot be applied directly. Items with issued management documents (mandatory health, safety and environmental (HSE) provisions, etc.) are subject to the mandatory rule of compliance with the documents and no falling below the floor; items without management documents are estimated on market-based principles, but the method statement and calculation rules must be kept on record as the basis for settlement. Railway and other sectors follow their own sectoral pricing rules (e.g. the scope of railway preliminaries is set out in TB 10801-2024). This card contains no specific percentage-rate figures; actual determination follows the documents currently in force at the project location and the contract.

Further Reading

Jing Jian Fa [2021] No. 11 (pricing-management document of the Beijing Municipal Commission of Housing and Urban-Rural Development): definition of preliminary items that cannot be measured precisely and the two-class treatment rules; companion documents: Jing Jian Fa [2021] No. 404 (mandatory health, safety and environmental (HSE) provisions, statutory levies and fees, off-site haulage and disposal of construction waste), Jing Jian Fa [2019] No. 9 (mandatory health, safety and environmental (HSE) provisions), Jing Jian Fa [2019] No. 4 (acceleration measure increase costs, 2018 duration quota norms), Jing Jian Fa [2017] No. 27 (off-site haulage and disposal of construction waste). Related standards: GB/T 50500-2024, China national pricing standard for BOQ, Article 3.2.6 (scope of preliminary items); GB/T 50875-2013, Standard for Terminology of Construction Cost, Article 2.2.56 (protection of completed works); T/YJXB 0001-2023, Standard for Calculating Contractor's Costs during Suspension of Construction Works, Article 5.0.1 (actual-expenditure method / rule-standard method for protection of completed works). The estimation and allocation methods for protection of completed works are set out in the referenced cards.