Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Highway permanent land-occupation fee composition and the five classes of land-use and demolition compensation costs (JTG 3830-2018 section 3.2)

Per clause 3.2.2 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", the permanent land-occupation fee has 5 items: land compensation, resettlement subsidy for requisitioned arable land, arable-land reclamation fee, forest-vegetation restoration fee, and pension insurance for land-lost farmers; clause 3.2.1 defines land-use and demolition compensation costs as 5 classes: permanent land-occupation fee, temporary land-occupation fee, demolition compensation, soil-and-water conservation compensation, and other costs. Each is computed per state and provincial (works-location) government provisions.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.2节
  • 国办发〔2018〕16号《跨省域补充耕地国家统筹管理办法》

Topic Positioning

The composition and computation of "land-use and demolition compensation costs" under section 3.2 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects" (the basis of the 2018 highway quota system), focusing on the 5 items of the permanent land-occupation fee — for splitting and checking acquisition/demolition-type costs in highway estimates, budgets and investment estimates.

Core Conclusions

Per clause 3.2.1, land-use and demolition compensation costs comprise permanent land-occupation fee, temporary land-occupation fee, demolition compensation, soil-and-water conservation compensation, and other costs (5 classes).

Per clause 3.2.2, the permanent land-occupation fee comprises 5 items:

  1. Land compensation: acquisition compensation, crop compensation on requisitioned land, the vegetable-land development fund for requisitioned suburban vegetable land, arable-land occupation tax, and land-map compilation and boundary-survey fees.
  2. Resettlement subsidy for requisitioned arable land: subsidies for resettling the agricultural population displaced by arable-land requisition.
  3. Arable-land reclamation fee: where a highway project occupies arable land, the project legal person (owner) is responsible for replacing it; where replacement is impossible or the replacement land fails requirements, the statutory reclamation fee is paid. For cross-provincial replacement under state coordination, follow the "Notice on printing and issuing the measures for state-coordinated cross-provincial arable-land replacement and cross-provincial transfer of saved quotas from urban-rural construction land increase-decrease linkage" (Guo Ban Fa [2018] No. 16); for intra-provincial cross-region replacement, follow provincial provisions.
  4. Forest-vegetation restoration fee: where forest land is occupied or requisitioned, after review/approval by the forestry authority at county level or above, the project legal person (owner) prepays the fee to that authority per provincial government provisions.
  5. Pension insurance for land-lost farmers: insurance contributions per state provisions to secure pensions for legally land-lost farmers, computed per provincial (location) provisions.

The other four classes (for cross-checking): clause 3.2.3 temporary land-occupation fee — temporary land requisition (compensation for all temporary land and attachments for contractor premises, precasting yards, mixing yards, warehouses, processing sheds, stockpiles, borrow/spoil areas, access roads and temporary bridges) and rehabilitation (restoring temporarily occupied arable land and fish ponds to original standard after handover); clause 3.2.4 demolition compensation — demolition, excavation and relocation compensation for buildings and appurtenant structures above and below ground, public facilities, relics etc.; clause 3.2.5 soil-and-water conservation compensation per relevant state laws; clause 3.2.6 other costs — acquisition/demolition-related costs set by State Council departments and provincial governments.

Computation (clause 3.2.7): land-use and demolition compensation costs are computed from the permanent and temporary land areas and attachments determined by the design documents and the actual cost items, per state provisions and the works-location provincial regulations and standards; the forest-vegetation restoration fee from the approved forest-land types and areas; interference with existing power/telecom facilities, pipelines, water works, railways etc. — consult the authorities concerned, agree a solution and compensation, or have them compile the costs per provisions; soil-and-water conservation compensation per provincial charging standards.

Applicable Boundaries

  • Only for highway estimate/budget compilation (JTG 3830-2018, with JTG 3831-2018/JTG 3832-2018 quotas).
  • Rates and standards depend heavily on the works-location provincial provisions (pension insurance, conservation compensation, reclamation fees etc.) — use the province's current rules; no cross-province copying, no national flat-rate estimating.
  • Permanent vs temporary occupation are different accounts: borrow/spoil areas, precasting and mixing yards etc. go under temporary occupation (temporary requisition + rehabilitation) — classify correctly, avoid duplication or omission.
  • Arable-land replacement has two policy paths (cross-province state coordination vs intra-provincial) — determine which applies before selecting the provisions.

Further Reading

  • Standard text: JTG 3830-2018 section 3.2 (clauses 3.2.1-3.2.7), being Part 2 "land-use and demolition compensation costs" of the total cost composition.
  • Policy link: Guo Ban Fa [2018] No. 16 (cross-provincial arable-land replacement and quota transfer measures).
  • Extension: section 3.1 construction-installation costs (clause 3.1.1's 8 items) — also part of the total cost composition; check each part when compiling the total cost table.