Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Highway works preliminary estimate (budget) site construction fee: base to which percentage rates are applied = norm-based cost of works − special costs, progressive percentage rates per Table 3.1.11 (JTG 3830-2018 clause 3.1.11)

Per clause 3.1.11 of JTG 3830-2018 'Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects': the site construction fee is calculated on the 'site construction base to which percentage rates are applied = norm-based cost of works − special costs' at the percentage rates in Table 3.1.11 using the progressive bracket-excess method (5.338% for 5 million yuan and below, stepping down band by band to 1.118% above 10,000 million yuan, 15 bands); special costs = site construction fee + statutory work safety levy (earmarked funds). Distinguish it from the statutory work safety levy (earmarked funds) in the same clause: statutory work safety levy (earmarked funds) = cost of works (construction and installation) (excluding the levy itself) × percentage rate (not less than 1.5%) — the base is different and the two must not be mixed.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.11条及Table 3.1.11
  • JTG/T 3832-2018 · Budget Quota of Highway Engineering
  • JTG/T 3831-2018 · Estimate Quota of Highway Engineering

Topic Positioning

This card explains clause 3.1.11 'site construction fee' of JTG 3830-2018 'Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects': how the base to which percentage rates are applied is determined, the banded percentage rates of Table 3.1.11 (progressive bracket-excess), the fee content, and its distinction from the statutory work safety levy (earmarked funds) in the same clause — for direct application in highway works preliminary estimate/budget compilation and review.

Core Conclusions

1. Base (per the measures): site construction base to which percentage rates are applied = norm-based cost of works − special costs, where norm-based cost of works means costs calculated at quota-norm base-period prices (excluding the adjustment for price differentials of labour, materials and plant at compilation-period market prices, so the percentage rate application is unaffected by price movements); special costs = site construction fee + statutory work safety levy (earmarked funds) (i.e. both items are deducted from the base). The site construction fee is calculated on the site construction base to which percentage rates are applied using the progressive bracket-excess method per Table 3.1.11.

2. Table 3.1.11 site construction fee percentage rates (base unit: 10,000 yuan):

Site construction base to which percentage rates are applied (10,000 yuan) Percentage rate (%)
≤500 5.338
500-1000 4.228
1000-5000 2.665
5000-10000 2.222
10000-30000 1.785
30000-50000 1.694
50000-100000 1.579
100000-150000 1.498
150000-200000 1.415
200000-300000 1.348
300000-400000 1.289
400000-600000 1.235
600000-800000 1.188
800000-1000000 1.149
>1000000 1.118

3. Worked examples (from the measures): base 5 million -> 500 × 5.338% = 26.69; base 10 million -> 26.69 + (1000−500) × 4.228% = 47.83; base 50 million -> 47.83 + (5000−1000) × 2.665% = 154.43 (progressive bracket-excess: full amount at the lower band's percentage rate plus the excess at the higher band's percentage rate).

4. Content (clause 3.1.11 item 1): (1) contractor's premises and site laboratories, and office, living and production housing required for centralised rebar processing, centralised mixing and centralised precasting; (2) yard levelling (excluding earth/rock works in mountainous heavy-hill terrain), hardening, drainage, greening, sewage treatment, hoarding; (3) temporary working access roads (including motor-vehicle and manual lanes), pedestrian footpaths, water pipe branch lines and electrical branch lines for temporary site water and electricity, temporary structures and other minor temporary works — costs of erection, maintenance, removal and clearing (excluding temporary roads within the red line leading to and from the site, and traffic-maintenance bypass roads); (4) depreciation, amortisation or rental of fixed-asset test equipment and instruments of the site laboratory; (5) dust-pollution prevention measures (dust nets, watering or dust suppressants, vehicle covering and washing, hoarding); (6) mandatory health, safety and environmental (HSE) provisions and staff health and living costs. Excludes: rebar processing machinery, mixing plant, precast plinths, precast prestressing equipment, lifting and curing equipment, and temporary-works costs already included in the preliminary estimate/budget quota norms.

5. Distinction from the statutory work safety levy (earmarked funds) (same clause, item 2): the statutory work safety levy (earmarked funds) = cost of works (construction and installation) (excluding the levy itself) × percentage rate (not less than 1.5%) — a different base; never mix. Both are 'special costs' within the 8-item composition of the cost of works.

Applicable Boundaries

  • Applies to highway works preliminary estimate/budget compilation with the 2018 highway quota-norm system (JTG/T 3832-2018 etc.).
  • The site construction fee is a 'special cost'; its base 'norm-based cost of works' excludes compilation-period price differentials — do not apply bases that include them (e.g. statutory levies and fees on compilation-period labour cost).
  • Where the province supplements the fee (some adjust percentage rates or methods), the local documents govern.
  • Not for railway (TB 10801-2024/TB 10811-2024, which have their own heavy temporary works basis), building/municipal or water sectors — each has its own special-cost rules.
  • The percentage rate figures come from an OCR edition verified band by band against the worked examples; for formal deliverables, check the figures against the official print/electronic edition.

Further Reading

  • JTG 3830-2018 clause 3.1.11 and Table 3.1.11 (bands and example column); content in item 1, statutory work safety levy (earmarked funds) in item 2 of the same clause.
  • Related clauses: 3.1.1 (composition of the 8 items and definition of norm-based cost of works), 3.1.10 (taxes and duties formula (VAT under the current standard)).
  • Companion quota manuals: JTG/T 3832-2018 Highway Works Budget Quota Manual, JTG/T 3831-2018 Highway Works Preliminary Estimate Quota Manual.