Highway 2018 quota system works classification: the 10 classes of JTG 3830-2018 clause 3.1.4 (Structures II = minor, medium, major and super-major bridges) and their use as fee-band selectors
Per clause 3.1.4 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", the 2018 highway estimate/budget system classifies works into 10 classes (earthwork, rockwork, haulage, pavement, tunnels, Structures I, Structures II, Structures III, technically complex bridges, steel and steel structures), with Structures II meaning minor, medium, major and super-major bridges; the main spans of steel pipe-arch, cable-stayed and suspension bridges and of major bridges with single span >=120 m (inclusive) and foundation water depth >=10 m (inclusive) form the separate class "technically complex bridges"; steel and steel structures of all works fall in class 10. Clause 3.1.5: purchased subgrade fill, greening seedlings, commercial cement concrete, commercial asphalt and stabilized mixes, and purchased concrete components are excluded from the bases of preliminaries and overheads (company and site). Works class is the banding basis for preliminaries and overheads (company and site) rates.
Applicable Codes
- JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.4~3.1.6 条
- JTG/T 3831—2018 · Estimate Quota of Highway Engineering
- JTG/T 3832—2018 · Budget Quota of Highway Engineering
Topic Positioning
This card covers the "works classification" of clause 3.1.4 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects": the 10 classes shared by the 2018 estimate/budget quota system and their scope, focusing on what "Structures II" covers, and the use of works class as the fee band for preliminaries and overheads (company and site) — for assigning works classes and rates to BOQ items in highway estimate/budget compilation.
Core Conclusions
Per clause 3.1.4 "works classification" (shared by the 2018 estimate and budget quota systems), 10 classes with the key wording:
- Earthwork: manual and mechanical earthworks, subgrade lime admixture, subgrade replacement and abutment-back backfill.
- Rockwork: manual and mechanical rockworks.
- Haulage: hauling earth/rock, pavement base and surface mixes, cement concrete and precast components, greening seedlings etc. by truck, tractor, tipper, vessel etc.
- Pavement: all pavement structural layers, pavement appurtenant works, access roads and special-subgrade treatment (excluding masonry structures within special-subgrade treatment).
- Tunnels: tunnel civil works (excluding tunnel steel and steel structures).
- Structures I: tree felling and stump removal, demolition, drainage, protection, masonry structures within special-subgrade treatment, culverts, traffic safety facilities, mixing plant erect/dismantle, temporary bridges and culverts, temporary power and telecom, temporary track, temporary wharves, greening works etc.
- Structures II: minor, medium, major and super-major bridge works.
- Structures III: placing commercial cement concrete, paving commercial asphalt and stabilized mixes, purchased concrete components, equipment installation works etc.
- Technically complex bridges: foundations, substructure and superstructure of the main spans of steel pipe-arch, cable-stayed and suspension bridges and of major bridges with single span over 120 m (including 120 m) and foundation water depth over 10 m (including 10 m) (excluding the bridge's steel and steel structures).
- Steel and steel structures: steel and steel structures of all works.
Key readings:
- Ordinary bridges (minor through super-major) are wholly Structures II; the main-span parts (foundation, substructure, superstructure) of steel pipe-arch, cable-stayed and suspension bridges and of major bridges with single span >=120 m and foundation water depth >=10 m form "technically complex bridges"; steel and steel structures of all works fall in class 10.
- Clause 3.1.5: purchased subgrade fill, greening seedlings, commercial concrete, commercial asphalt and stabilized mixes, and purchased concrete components are excluded from the preliminaries and overheads (company and site) bases — note the base treatment for Structures III items (commercial concrete placing, purchased components).
- Clause 3.1.6: preliminaries comprise winter, rainy-season, night, special-region, traffic-interference additions, auxiliary works allowance and works-transfer fee.
- Use: works class is the band selector for preliminaries and overheads (company and site) rates; assign each BOQ item its class and rate.
Applicable Boundaries
- Applies to highway estimate/budget compilation (JTG 3830-2018 system, shared by the estimate and budget quotas); not for railway (TB 10801/TB 10811) or building/municipal systems — classifications and fee calibers differ, no mixing.
- The classification serves only to select fee bands; it does not alter the work content or quantity rules of quota items themselves.
- "Technically complex bridges" covers the main-span parts of major bridges meeting both "single span over 120 m (inclusive)" and "foundation water depth over 10 m (inclusive)" (pipe-arch/cable-stayed/suspension types enter directly regardless) and excludes the bridge's steel and steel structures; steel and steel structures in tunnels and bridges always go to class 10, not with the parent class.
Further Reading
JTG 3830-2018 clause 3.1.4 (classification), clause 3.1.5 (items excluded from preliminaries/overheads (company and site) bases), clause 3.1.6 (preliminaries composition and definitions) and the subsequent rate provisions; companion quotas JTG/T 3831-2018 (estimate) and JTG/T 3832-2018 (budget), both sharing this classification. Base calibers also in clause 3.1.1 and the Form 08 notes.