Quota basis of labor/material/plant consumption in highway estimate (budget) compilation: JTG 3830-2018 clause 2.1.1 adopts JTG/T 3831-2018 estimate quota and JTG/T 3832-2018 budget quota
Clause 2.1.1 of JTG 3830-2018 provides: when compiling estimates and budgets, the labor, material/equipment and plant-shift consumption follow the current "Highway Works Estimate Quota" (JTG/T 3831) and "Highway Works Budget Quota" (JTG/T 3832), and the labor/material/plant costs are computed at the project-location workday unit prices, material budget prices and plant shift prices fixed by the measures. Design estimates use the 3831 estimate quota, construction-drawing budgets the 3832 budget quota — the two must not be mixed; plant shift prices pair with the "Plant shift fee quota of highway works" JTG/T 3833-2018.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第2.1.1条
- JTG/T 3831-2018 · Estimate Quota of Highway Engineering
- JTG/T 3832-2018 · Budget Quota of Highway Engineering
- JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery
Topic Positioning
The quota basis for labor, material/equipment and plant-shift consumption when compiling highway estimates and budgets — the two companion quotas fixed by clause 2.1.1 of JTG 3830-2018, their stage applicability and version history.
Core Conclusions
Per clause 2.1.1 of JTG 3830-2018 (original text): "When compiling estimates and budgets, compute the labor, material and plant costs of the project from the labor, material/equipment and plant-shift consumption specified in the current Highway Works Estimate Quota (JTG/T 3831) and Highway Works Budget Quota (JTG/T 3832), at the project-location workday labor unit prices, material budget prices and plant shift unit prices for the estimate/budget compilation time fixed by these measures, and compute the various fees per these measures."
Directly reusable points:
- Design estimates use JTG/T 3831-2018; construction-drawing budgets use JTG/T 3832-2018. Stage-dedicated, never mixed — preliminary design stage estimates take 3831, construction-drawing stage budgets take 3832; there is no "budget quota decomposed into an estimate" practice.
- The estimate quota is synthesized and enlarged from the budget quota (including enlargement margins); consumption levels differ between stages.
- Clear division: consumption from the two quotas; unit prices per the measures at project-location workday/material/plant shift prices; plant shift prices pair with JTG/T 3833-2018 (governs "prices" not "consumption", but is a companion quota to be prepared together).
- Version history: the three quotas and the measures were published by MOT announcement, effective 1 May 2019, simultaneously abolishing JTG/T B06-01-2007 (estimate quota), JTG/T B06-02-2007 (budget quota) and JTG/T B06-03-2007 (plant shift fee quota).
Applicable Boundaries
- Applies to design estimates and construction-drawing budgets of highway construction projects (new-build and rebuild/expansion); railways, building/municipal etc. have their own quota systems — do not apply this card.
- The clause governs the pairing "consumption from quotas, prices at compilation-time project-location prices": compilation-time prices compute labor/material/plant costs, quota base prices (appendix prices) compute quota direct cost and some fee bases — different calibers, never conflate.
- The two stage quotas are not interchangeable; where the basis is missing or works exceed the quota items, supplement or adopt other pricing bases per the measures.
Further Reading
- Source: JTG 3830-2018 section 2.1 "Basic provisions", clause 2.1.1.
- Companion quotas: JTG/T 3831-2018, JTG/T 3832-2018, JTG/T 3833-2018.
- Extended: see the card on differences among consumption/budget/estimate quotas (estimate quota = budget quota synthesized and enlarged); section 3.1 of the measures gives the construction-installation cost composition and fee bases.
Keywords
- JTG 3830-2018
- compilation rules for highway estimates and budgets (JTG 3830)
- JTG/T 3831-2018
- JTG/T 3832-2018
- 公路工程概算定额
- highway works budget quota manual
- 工料机消耗量
- 第2.1.1条