Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Measurement units of highway subgrade site-clearing items: JTG/T 3832-2018 budget quota 1-1-1 tree felling and stump removal (10 trees), topsoil stripping (100 m3), and BOQ calibers

JTG/T 3832-2018 "Highway works budget quota", Chapter 1 Section 1, item 1-1-1 "tree felling, stump removal, grassing, topsoil stripping": felling/stump removal measured per 10 trees; topsoil stripping per 100 m3 (dozer power bands within 90 kW / within 135 kW); shrub clearing per 1000 m2 (under 220 shrubs per 1000 m2 sparse, above dense); grassing per 1000 m2; bamboo-root digging per 10 m3 (by pit volume). Section notes: topsoil stripping and grassing quotas must not be applied together; haul of stripped topsoil follows the earthwork haulage quota. BOQ measurement per the contract; DB14/T 1319-2021 Section 202 Table 202: 202-1-a site clearing (incl. topsoil) lump-sum, 202-1-b tree felling (breast-height diameter over 10 cm) per tree.

Applicable Codes

  • JTG/T 3832-2018 · Budget Quota of Highway Engineering Ch. 1第一节 1-1-1
  • JTG/T 3831-2018 · Estimate Quota of Highway Engineering
  • DB14/T 1319—2021 · Specification for Standard Bills of Quantities and Measurement of Highway Works (Shanxi) 第202节

Topic Positioning

This card covers the measurement units and application rules of highway subgrade "site clearing" items (tree felling, stump removal, shrub clearing, grassing, topsoil stripping, bamboo-root digging) under both the budget quota and the BOQ calibers — for construction-drawing budgeting, quantity take-off, and measurement payment.

Core Conclusions

(1) Quota caliber: JTG/T 3832-2018 "Highway works budget quota", upper volume, Chapter 1 subgrade, Section 1, item 1-1-1 "tree felling, stump removal, grassing, topsoil stripping", tabulated units:

  • Tree felling and stump removal: 10 trees — sub-items such as "manual felling and digging (tree diameter over 10 cm)" and "manual felling, excavator stump digging (by bucket capacity)";
  • Shrub clearing: 1000 m2 — sparse/dense (under 220 shrubs per 1000 m2 sparse, over 220 dense);
  • Grassing: 1000 m2 — manual cutting, manual sod digging, dozer sod clearing (by power);
  • Bamboo-root digging: 10 m3 — by pit volume;
  • Topsoil stripping: 100 m3 — dozer stripping and pushing beyond the subgrade, items by dozer power within 90 kW / within 135 kW.

Section notes (verbatim): 1. Bamboo-root digging is by pit volume; reed-root digging = bamboo-root x 0.73. 2. Shrub clearing: under 220 shrubs per 1000 m2 sparse, over 220 dense. 3. Topsoil stripping and grassing quotas must not be applied together; haul of stripped topsoil follows the earthwork haulage quota.

General volume rules (section notes): excavation is measured in natural in-situ (undisturbed) volume, fill in compacted volume, rock blasting in natural in-situ (undisturbed) volume; where fill compacted volume is the quantity and the quota is in natural in-situ (undisturbed) units, multiply the quota by the stated coefficients for spoil reused as fill, plus 0.03 loss for borrowed fill.

(2) BOQ caliber (measurement payment): per the contract's rules; DB14/T 1319—2021 "Standard bills of quantities and measurement for highway works", Section 202 Table 202 site clearing: 202-1-a site clearing (incl. stripping of 0-30 cm topsoil, refuse, etc.) lump-sum; 202-1-b tree felling (breast-height diameter over 10 cm) per tree. Note: ministry Section 203 is subgrade excavation — do not mis-file clearing items under 203.

(3) Conversion tips: topsoil stripping volume = stripping thickness x area (natural in-situ (undisturbed) volume, m3), / 100 for the 100 m3 quota unit; tree/stump counts / 10 for the 10-tree unit.

Applicable Boundaries

  • The quota caliber applies to construction-drawing budgets (JTG/T 3832-2018); design estimates use the corresponding JTG/T 3831-2018 items with that quota's tabulated units.
  • Topsoil stripping and grassing must not be combined; stripping includes only dozer excavation and pushing beyond the subgrade; further haul follows the earthwork haulage quota.
  • Bamboo roots by pit volume; reed roots x 0.73; shrub sparse/dense boundary 220 per 1000 m2.
  • BOQ and quota measurement are two calibers; payment follows the contract's BOQ rules; local lists (e.g., DB14/T 1319—2021) may differ slightly from the industry list.
  • Landscaping quotas of some regions may measure felling/stump removal per "tree" with diameter bands — different from this section's 10 trees/1000 m2; check the quota edition and specialty volume before applying.

Further Reading

  • JTG/T 3832-2018, upper volume, Chapter 1 subgrade, Section 1, item 1-1-1 tables, section notes, and footnotes.
  • JTG/T 3831-2018 corresponding chapters (estimate caliber).
  • DB14/T 1319—2021 Section 202 Table 202 (site-clearing measurement rules).

Keywords