JTG/T 3832-2018 highway budget quota: suspension-bridge main cables and steel box girders measured by mass in t, and measurement units of suspension-bridge work items
Per Section 10 steel structures (lower volume) of JTG/T 3832-2018 "Highway works budget quota": the main cable (parallel-wire strands, hangers, ties, strand bundles, etc.) and the steel box girder are both measured by mass in t, quota tables compiled per 10 t; the cable mass excludes anchorages and PE/sleeve protection materials (their costs are in the finished-product price); steel box girder mass = box girder (incl. internal diaphragms) + deck plates (incl. transverse ribs) + cross beams + steel anchor boxes; within the suspension-bridge system cable clamps/saddles/cable casings/anchorages are in t, hauling/catwalk/wrapping in m (single-side length), saddle housings per set (1 set per main saddle) — each item must be distinguished when compiling.
Applicable Codes
- JTG/T 3832-2018 公路工程预算定额(下册 第十节 钢结构工程)
- JTG 3830-2018 公路工程建设项目概算预算编制办法
Topic Positioning
This card covers the measurement units and quantity rules for suspension-bridge main cables (strands) and steel box girders, and the unit distinctions among suspension-bridge work items (cable clamps, wire wrapping, hauling/catwalk systems, saddles, saddle housings, anchorage systems), in "Section 10 steel structures", lower volume, of JTG/T 3832-2018 "Highway works budget quota" — for direct application in highway estimate/budget compilation and review.
Core Conclusions
The main cable and the steel box girder are both measured by mass in "t", quota tables per 10 t.
1. Main cable (suspension bridge)
- Notes item 7 (1), verbatim: "Parallel-wire stays, hangers, ties, strand bundles, etc. are in t, measured by the mass of parallel wire, wire rope, or strand, excluding the mass of anchorages and PE or sleeve protection materials; but the costs of anchorages and PE/sleeve protection shall be included in the finished-product price."
- Main-cable erection items (stepped by main-span length) are tabulated per 10 t, strand consumptions 10 t per table unit.
- Units differ across the suspension-bridge system — distinguish per the quantity rules:
- Cable clamps and hangers: in t. Clamp mass includes the clamp body, nuts, bolts, waterproof nuts, and spherical washers.
- Cable compaction and wire wrapping: in m. Wrapping is computed on the single-side cable length after deducting the anchor spans, tower-top zones, and clamp positions needing no wrapping.
- Hauling system and catwalk system: in m, both the single-side length required by the system.
- Main saddles, splay saddles, cable casings, anchorage systems (positioning steel frames, anchoring tie rods, epoxy strands): in t. Main saddle mass includes bearing plates, saddle body, mounting plates, keepers, trough covers, tie-rod diaphragms, anchor beams, and zinc fillers; splay saddle mass includes base plate, pedestal, bearing plate, saddle body, pressure beams, and diaphragms (tie rods, zinc fillers); the positioning frame mass is the sum of its sections, plates, and pipes; the tie-rod mass includes rods, couplers, nuts (locking and spherical), and washers (locking and spherical); the epoxy strands of the anchorage system are in t, the stressing working length already included; the tower-top gantry is in t by its section mass, the steel gratings by the sum of grating and reaction frame.
- Saddle housings: per set, one set per main saddle; corrosion protection and dehumidification systems are charged separately.
- The main saddle quota assumes 6 jackings; for other numbers adjust labor by 1.8 shifts per 10 jacking-operations.
2. Steel box girder
- Notes item 7 (3), verbatim: "Steel box girders, saddles, arch ribs, steel longitudinal/transverse beams, etc. are in t. The unit prices of steel box girders and arch ribs include on-site welding costs."
- Quantity rule (10), verbatim: "The steel box girder mass is the sum of the box girder (incl. internal diaphragms), deck plates (incl. transverse ribs), cross beams, and steel anchor boxes."
- The box-girder lifting items are tabulated per 10 t (consumptions 10 t per table unit).
3. Finished-product pricing caliber (notes item 7) Factory-made products not fabricated by the contractor are finished products entering the quota as material unit prices = ex-works price plus transport to site. The main cable enters as finished strands; anchorage and PE/sleeve protection costs are in the product price but not in the measured mass; on-site welding of the box girder is in its price — no separate welding item. Strand stay cables are measured by strand mass, the price including on-site socketing and anchorages; the epoxy strands of the suspension-bridge anchorage system include anchorages at both ends.
Applicable Boundaries
- Based on "Section 10 steel structures" (bridge works 4-10), lower volume, JTG/T 3832-2018; applies to quota quantity computation for suspension-bridge main cables, box girders, and companion items in highway estimates/budgets; not for railway or municipal works under other quota systems.
- The quota caliber uses "design mass" (box girder as sums; steel arch ribs as design mass excl. bearings and in-rib concrete), unlike BOQ measurement rules — compute quota and bill quantities under their own rules.
- The suspension-bridge items differ widely in units (t/m/set) — check each chapter note and rule; never put the whole system in t.
- The main saddle quota assumes 6 jackings; adjust per "1.8 shifts per 10 jacking-operations".
- Steel truss girder quotas assume on-site segment assembly with segment cantilever cranes; other methods are computed separately.
Further Reading
- Quota text: JTG/T 3832-2018, lower volume, "Section 10 steel structures", notes 1-8 and quantity rules (1)-(11) (main cable, saddles, anchorages, box girder, arch ribs); Chapter 4-10 items (main-cable erection, box-girder lifting, per 10 t).
- Fee basis: JTG 3830-2018 Section 3.1 (composition of the cost of works (construction and installation)).
- Technical background: JTG/T 3650-2020 "Technical specifications for construction of highway bridges and culverts", Chapter 8 steel structures.
- BOQ comparison: steel pipe arch ribs by design mass in kg, DB14/T 1319-2021 Section 412 Table 412, item 412-1-a — vs this section's t caliber.
Keywords
- JTG/T 3832-2018
- highway works budget quota manual
- 主缆
- 钢箱梁
- unit of measurement
- 悬索桥
- 钢结构工程
- method of measurement