Definition and classification system of construction quota norms (GB/T 50875-2013 §2.3, quota-related terms)

A construction quota norm = the quantity standard of labour, material and machine-shift consumption required to complete a unit of qualified building and installation output under rational labour organization and rational use of materials and plant (GB/T 50875-2013 §2.3.1). By production element: labour (consumption) quota norms, material consumption quota norms, machine-shift consumption quota norms. By purpose, from fine to coarse: construction quota norms → budget quota norms → preliminary estimate quota norms → preliminary estimate indicators → feasibility-stage cost estimate indicators; the latter four are jointly termed "engineering pricing quota norms" and are used directly for pricing. Distinct from GB/T 50851-2013 §2.0.4 "pricing basis" (the full set of documents: pricing standards + the various quota norms + norms for on-costs and expenses + unit-price tables + cost information + taxes and fees) — quota norms fix only "quantities".

Applicable Codes

  • GB/T 50875-2013 工程造价术语标准
  • GB/T 50851-2013 建设工程人工材料设备机械数据标准

Topic Positioning

The standard definition and system classification of "construction quota norms" (GB/T 50875-2013 section 2.3), distinguishing "quota norms" from the "pricing basis".

Core Conclusions

  • Definition (§2.3.1): the quantity standard of labour, material and machine-shift consumption necessary to complete a unit of qualified building and installation output under rational labour organization and rational use of materials and plant.
  • By production element: labour consumption quota norms (labour quota norms; time and output quota norms are reciprocals of each other), material consumption quota norms, construction machine-shift consumption quota norms.
  • Five levels by purpose: construction quota norms (finest items, for the contractor's own production organization) → budget quota norms (construction-drawing based budget (pre-tender estimate), all-in unit rates) → preliminary estimate quota norms (design estimate (approved cost ceiling)) → preliminary estimate indicators (measured by area/volume/unit) → feasibility-stage cost estimate indicators (feasibility-stage cost estimate).
  • Budget quota norms, preliminary estimate quota norms, preliminary estimate indicators and feasibility-stage cost estimate indicators are jointly termed "engineering pricing quota norms" (§2.3.2), used directly for pricing; contractor's in-house norms (§2.3.3) are for tender (priced offer) pricing and cost management.
  • A quota norm is a "quantity" standard; the "pricing basis" (GB/T 50851-2013 §2.0.4) is the full set — pricing standards + the various quota norms + norms for on-costs and expenses + unit-price tables + cost information + taxes and fees — of which quota norms are only a part.

Applicable Boundaries

General terminology, reusable across projects; not applicable to specific quota-norm values or single-point price lookups; a distinction must be drawn between contractor's in-house norms (the contractor's own level) and competent-authority consumption quota norms (the social-average baseline).

Further Reading

GB/T 50875-2013 section 2.3 (2.3.1–2.3.9, 2.3.15); for the pricing basis see GB/T 50851-2013 clause 2.0.4.