Three-stage pairing of the highway 2018 pricing system: estimates with the "Highway engineering estimation indicators" JTG/T 3821-2018, design estimates with JTG/T 3831-2018, budgets with JTG/T 3832-2018, all sharing the plant shift-cost quota JTG/T 3833-2018
Per Ministry of Transport Announcement No. 86 (17 December 2018), the highway 2018 pricing system took effect on 1 May 2019: investment estimates use the "Highway engineering estimation indicators" JTG/T 3821-2018 (compiled per JTG 3820-2018); design estimates use the "Highway works estimate quota" JTG/T 3831-2018; construction-drawing budgets use the "Highway works budget quota" JTG/T 3832-2018 (estimates and budgets both per JTG 3830-2018); all three stages share the "Highway engineering plant shift-cost quota" JTG/T 3833-2018. JTG M20-2011, JTG B06-2007, JTG/T M21-2011, and JTG/T B06-01/02/03-2007 were abolished the same day.
Applicable Codes
- 交通运输部公告第86号(2018年12月17日)
- JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects
- JTG/T 3821-2018 · Estimate Indicators of Highway Engineering
- JTG/T 3831-2018 · Estimate Quota of Highway Engineering
- JTG/T 3832-2018 · Budget Quota of Highway Engineering
- JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery
Topic Positioning
This card covers which indicators/quotas pair with each of the three stages — investment estimate, design estimate, construction-drawing budget — in the highway 2018 pricing system, the measures of each stage, and the old-new standard succession (Ministry of Transport Announcement No. 86, effective 1 May 2019).
Core Conclusions
Per Ministry of Transport Announcement No. 86 (17 December 2018), verbatim: "The 'Measures for compiling investment estimates of highway engineering construction projects' (JTG 3820-2018) and the 'Measures for compiling estimates and budgets of highway engineering construction projects' (JTG 3830-2018) are hereby published as highway industry standards; the 'Highway engineering estimation indicators' (JTG/T 3821-2018), 'Highway works estimate quota' (JTG/T 3831-2018), 'Highway works budget quota' (JTG/T 3832-2018), and 'Highway engineering plant shift-cost quota' (JTG/T 3833-2018) as recommended highway industry standards, effective 1 May 2019."
Three-stage pairing:
| Cost-document stage | Companion consumption indicators/quotas | Measures |
|---|---|---|
| Investment estimate (project proposal / feasibility study) | "Highway engineering estimation indicators" JTG/T 3821-2018 | "Measures for compiling investment estimates..." JTG 3820-2018 |
| Design estimate (preliminary / technical design) | "Highway works estimate quota" JTG/T 3831-2018 | "Measures for compiling estimates and budgets..." JTG 3830-2018 |
| Construction-drawing budget (construction-drawing design) | "Highway works budget quota" JTG/T 3832-2018 | JTG 3830-2018 (as above) |
All three stages share the "Highway engineering plant shift-cost quota" JTG/T 3833-2018 (basis of plant shift prices).
Abolished by the same announcement: "Measures for compiling investment estimates of highway capital construction projects" (JTG M20-2011), "Measures for compiling estimates and budgets of highway capital construction projects" (JTG B06-2007), "Highway engineering estimation indicators" (JTG/T M21-2011), "Highway works estimate quota" (JTG/T B06-01-2007), "Highway works budget quota" (JTG/T B06-02-2007), "Highway engineering plant shift-cost quota" (JTG/T B06-03-2007).
JTG 3830-2018 Clause 2.1.1, verbatim: "When compiling estimates and budgets, the labor, material and equipment, and plant-shift costs of the project shall be computed from the consumptions stipulated in the current 'Highway works estimate quota' (JTG/T 3831) and 'Highway works budget quota' (JTG/T 3832) and the project-location labor shift price, material budget price, and plant shift price for estimate/budget compilation as stipulated by these measures, and each fee shall be computed as these measures provide."
Applicable Boundaries
- Applies to highway cost documents compiled from 1 May 2019; earlier projects follow the old (JTG B06-2007) system.
- At the estimate stage consumptions follow JTG/T 3821 per JTG 3820-2018 Clause 2.1.1; estimates and budgets use JTG/T 3831 and JTG/T 3832 respectively.
- The standards are managed and interpreted by the Ministry of Transport; routine interpretation and management rest with the chief-editing unit, the Ministry's Road Network Monitoring and Emergency Response Center.
- Two more boundaries in JTG 3830-2018: Clause 1.0.7 — for specialty works not covered by the measures and quotas, the cost of works (construction and installation) may follow the relevant industry quotas; Clause 1.0.8 — provincial transport authorities may issue supplementary provisions; local supplementary quotas and rates apply by project location.
- Version caution: the 1996 "Highway engineering estimation indicators" and earlier editions are abolished — historical reference only, never for current cost documents.
Further Reading
- Ministry of Transport Announcement No. 86 (17 December 2018) publishing the two measures and four quotas/indicators.
- JTG 3820-2018 Clauses 2.1.1 and 2.2.1; JTG 3830-2018 Clauses 1.0.7, 1.0.8, 2.1.1.
- Extensions: the estimate-stage consumption basis (JTG/T 3821) and the stage positioning of investment estimates and the "estimate -> estimate -> budget" control chain (estimate-stage cost <= investment estimate; budget <= estimate) have their own cards.
Keywords
- 公路工程2018计价体系
- 估算指标 JTG/T 3821
- 概算定额 JTG/T 3831
- 预算定额 JTG/T 3832
- 机械台班费用定额 JTG/T 3833
- 投资估算编制办法 JTG 3820
- 概算预算编制办法 JTG 3830
- 交通运输部公告第86号