Highway works preliminary estimate (budget) employer's (owner's) management fee: computed progressively on the norm-based cost of works per JTG 3830-2018 table 3.3.2-1 rates (with full rate table and worked example)
Per clause 3.3.2 of JTG 3830-2018, the employer's (owner's) management fee is computed progressively by the banded rates of table 3.3.2-1 on the base of the norm-based cost of works. The norm-based cost of works (clause 3.1.1 caliber) = norm-based direct cost + 40% of norm-based permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties (VAT under the current standard) + special fees — at norm-based base prices, excluding compilation-period price differences. Rates decrease band by band from 4.858% (<=5 million yuan) to 1.057% (1,000-1,500 million yuan), progressive like income tax; e.g. at a base of 1,500 million yuan the fee = 22.57515 million yuan.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.3.2 条、Table 3.3.2-1
- JTG 3830-2018 第 3.1.1 条(定额建筑安装工程费构成口径)
Topic Positioning
This card explains the charging rules of the "employer's (owner's) management fee" in highway works preliminary estimate and budget compilation: computed progressively by the banded rates of table 3.3.2-1 of JTG 3830-2018 on the norm-based cost of works base, with the full rate table and band-by-band worked example — directly usable for fee computation and checking.
Core Conclusions
Per JTG 3830-2018 clause 3.3.2: the employer's (owner's) management fee is computed progressively per the rates of table 3.3.2-1 on the norm-based cost of works.
Base definition (clause 3.1.1 caliber): norm-based cost of works = norm-based direct cost + 40% of norm-based permanent equipment procurement cost + preliminaries + overheads (company and site) + statutory levies and fees + profit + taxes and duties (VAT under the current standard) + special fees. Note this is the "quota" caliber — at norm-based base prices, excluding compilation-period price differences; only 40% of permanent equipment procurement cost enters, not the full amount.
Table 3.3.2-1 rates and progressive example (base unit: 10,000 yuan):
| Norm-based cost of works (10k yuan) | Rate (%) | Progressive example (10k yuan) |
|---|---|---|
| <=500 | 4.858 | 500 x 4.858% = 24.29 |
| 500-1000 | 3.813 | 24.29 + (1000-500) x 3.813% = 43.355 |
| 1000-5000 | 3.049 | 43.355 + (5000-1000) x 3.049% = 165.315 |
| 5000-10000 | 2.562 | 165.315 + (10000-5000) x 2.562% = 293.415 |
| 10000-30000 | 2.125 | 293.415 + (30000-10000) x 2.125% = 718.415 |
| 30000-50000 | 1.773 | 718.415 + (50000-30000) x 1.773% = 1073.015 |
| 50000-100000 | 1.312 | 1073.015 + (100000-50000) x 1.312% = 1729.015 |
| 100000-150000 | 1.057 | 1729.015 + (150000-100000) x 1.057% = 2257.515 |
(Above 1,500 million yuan there are further bands with decreasing rates; compile per the full table 3.3.2-1 in the standard.)
Algorithm essentials: progressive by bands, like personal income tax — fill each lower band at its rate, then apply the falling band's rate to the excess over the previous cap, and sum. Rates decrease as the base grows (4.858% -> 1.057%), reflecting scale effect; a base falling in a band is never the whole base times that band's rate.
Applicable Boundaries
- Applies to highway works preliminary estimate and budget compilation, as part of project costs other than the works (land, consents, supervision, etc.).
- The base must be the norm-based cost of works (the "quota" caliber): at norm-based base prices, excluding compilation-period price differences; only 40% of permanent equipment procurement cost — never use total cost of works or total investment.
- Progressive ≠ flat rate on the whole base: at 300 million yuan the fee is 7.1815 million yuan (previous bands 1.65315 million + (30000-5000) x 2.562%), not 30000 x 2.125%.
- Amounts are in 10,000 yuan; rates in percent; examples are verification values from the standard's table.
Further Reading
- JTG 3830-2018 clause 3.3.2 and table 3.3.2-1 (full table incl. bands above 1,500 million yuan); base caliber: clause 3.1.1 "norm-based cost of works" composition.
- Neighbouring fee rules: site transfer fee (table 3.1.6-9), auxiliary works allowance (table 3.1.6-8), statutory work safety levy (earmarked funds) (clause 3.1.11), material purchasing and custody charges (clause 3.1.2).
- Always verify rates against the current valid edition of the standard.