Summary and comparison requirements when highway estimates (budgets) are compiled in several sections: the summary estimate (budget) table (form 01-1), form 02-1, and comparison with the preceding stage's total cost (JTG 3830-2018 Clauses 1.0.6, 2.3.3, 2.3.5)

Per JTG 3830-2018, when a highway estimate (budget) is compiled in several sections, the principles shall be unified, the sectional costs summarized into the project total, and the total compared with the preceding stage's total (Clause 1.0.6); when compiled by sections or parts, a "summary estimate (budget) table" (form 01-1) must be compiled (Clause 2.3.5 item 3), with form 02-1 summarizing labor, main materials and equipment, and plant shifts; the explanations must contain the economic comparison of design alternatives and the comparison of quantities and costs with the preceding stage (Clause 2.3.3 items 6 and 7).

Applicable Codes

  • JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects
  • JTG 3820—2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects

Topic Positioning

This card covers the statutory summary forms for highway estimates (budgets) "compiled in several sections/parts" (form 01-1 summary estimate (budget) table, form 02-1 quantity summary) and the "inter-stage total-cost comparison" requirement of the "Administrative Compilation Rules for Estimates and Budgets of Highway Works Construction Projects" (JTG 3830-2018) — for practical compilation and document review.

Core Conclusions

  1. Clause 1.0.6 (general provisions, mandatory): "Where the design estimate or construction-drawing based budget cost documents of a highway project are compiled in several sections, the compilation principles shall be unified and the sectional costs summarized into the project total cost. The total cost shall be comparatively analyzed against the preceding stage's total cost to aid cost control." Also: connecting lines, branch lines, and larger access and connector works shall have separate cost documents summarized into the total.
  2. Clause 2.3.5 item 3: "Estimates and budgets shall be compiled per one construction project [e.g., one route or one independent large (medium) bridge or tunnel]. Where a project must be compiled by sections or parts, compile separately as needed, but a 'summary estimate (budget) table' must be compiled."
  3. Forms to be summarized (group-A documents, Appendix A + Figure 2.3.6):
    • Form 01-1 summary estimate (budget) table (mandatory): when a project's estimates (budgets) are compiled per several individual works, this table summarizes all amounts; it shows each cost component, the estimate (budget) total, and technical-economic indicators of the project; BOQ item coding, works/cost names, units, total quantities, and amounts are carried over from each individual works form 01; parts, items, and sub-items are retained; the "whole-route technical-economic indicator" = each summarized amount divided by the corresponding total quantity; "proportion of each cost" = each summarized project cost divided by the highway basic cost total.
    • Form 02-1 summary of labor, main materials, and machine-shift quantities: summarizes the labor, main materials and equipment, and machine-shift quantities of the whole project; data are carried from each form 02; the compilation scope means the individual or unit works.
    • Form 00 project attributes and technical-economic information, the inter-stage cost comparison table (item 2 of the group-A contents), and the explanatory notes of the estimate complete the set.
  4. Mandatory contents of the explanatory notes of the estimate (Clause 2.3.3): total estimate/budget amount, total labor, steel, cement, asphalt, etc.; item 6 "economic comparison of design alternatives"; item 7 "statistics of comprehensive technical-economic indicators and comparison of quantities and costs between this and the preceding stage".
  5. Commentary supplement to the general provisions: with multi-section compilation, project costs other than the works shall be computed on the basis of the sectional total norm-based cost of works (preventing duplicated or omitted bases from separate sectional charging).

Applicable Boundaries

  • Applies to highway estimates and budgets (JTG 3830-2018); sectional or part-wise compilation must be summarized — submitting only each section's form 01 without form 01-1 is not allowed.
  • The compiling unit is the "one construction project" as a whole; where sections are undertaken by several design institutes, each is responsible for its section's quality and the summarizing unit for the unified principles and inter-stage comparison.
  • The feasibility-stage cost estimate is governed by JTG 3820-2018 and does not directly use these form numbers; other industries (e.g., TB 10811) have their own summary and comparison rules — no mixing.

Further Reading

See JTG 3830-2018: Clause 1.0.6 (general), Clause 2.3.3 (contents of the explanatory notes), Clause 2.3.5 (document composition and sectional compilation), Figure 2.3.6 (computation sequence and relations: form 01 -> 01-1, form 02 -> 02-1), Appendix A (groups A/B and the styles and filling notes of forms 01-1 and 02-1), and the commentary on the general provisions; read with JTG 3820-2018 for the "feasibility-stage cost estimate -> design estimate -> budget" stage control chain.