Estimating project investment by the production capacity index method: the formula C2 = C1 x (Q2/Q1)^X x f, variable definitions, computation order, choosing the index, and the division of use against the coefficient, ratio and indicator methods

The production capacity index method estimates C2 = C1 x (Q2/Q1)^X x f (X is the n of the textbooks; the standard prescribes 0<=X<=1): first the capacity ratio to the nth power, then x the investment C1 of the built similar project, lastly x the composite adjustment factor f. n and f are independent - n reflects the non-linear scale-investment relation, f the difference of quota levels, equipment and material prices between periods and places, and may be above or below 1, multiplying only outside the bracket. T/ZBD 100.2-2022 clause 4.1.3 warns that the result is highly sensitive to the index and the method should generally not be used on a whole project - apply it to the process equipment of the production system; DB42/T 823-2021 clause 5.2.2 prescribes the indicator method for feasibility-stage estimates.

Applicable Codes

  • T/ZBD 100.2-2022 建设项目投资估算编制作业指引 第4.1.3条
  • DB42/T 823-2021 建设工程造价咨询质量控制规范 第5.2.2条、第6.2.3条
  • GB/T 50875-2013 工程造价术语标准 第3.1.2条

Positioning

The production capacity index method estimates a project's investment from the capacity and investment of a built similar project where design depth is insufficient. This card gives the formula and variables, the step order, how to choose the index, and the division of use against the coefficient, ratio, indicator and hybrid methods.

Core conclusions

1. Definition. GB/T 50875-2013 clause 3.1.2: "Production capacity index method: a method of estimating the investment of a proposed project from the capacity and investment of completed similar projects."

2. Formula and variables (T/ZBD 100.2-2022 clause 4.1.3 item 1; the standard writes X, textbooks n - equivalent):

C2 = C1 x (Q2/Q1)^X x f

  • C2 - investment of the proposed project;
  • C1 - investment of the completed similar project;
  • Q2 - capacity of the proposed project;
  • Q1 - capacity of the completed similar project;
  • X - the capacity index (0<=X<=1);
  • f - "a composite adjustment factor for differences of quota level, equipment purchase and construction material prices, and cost changes arising from different construction periods and locations".

n and f are independent - no substitution, no compounding. n carries the non-linear scale-investment relation (economies of scale: doubling capacity does not double investment); f carries the time-and-place difference of price and cost levels, converting the built project's price level to the estimate year and location of the proposed one, and may exceed or fall below 1. f multiplies outside the bracket - never (Q2/Q1)^(n.f), and never reuse f as a scale correction.

3. Step order (must not be inverted): 1) capacity ratio Q2/Q1; 2) its nth power; 3) x C1; 4) x f. With a ratio of 2 and n = 0.8, 2^0.8 is about 1.741, so C2 = about 1.741 x C1 x f - doubling capacity raises investment to about 1.74x (not 2x): economies of scale.

4. Choosing n (by how capacity is expanded):

  • Larger equipment size (capacity): n = 0.6~0.7 (unit-capacity investment of large single machines falls faster; strong scale effect);
  • More units of the same size: n = 0.8~0.9 (single-unit efficiency unchanged, near parallel replication; investment near-linear in capacity). The clause itself only bounds 0<=X<=1; the bands above are industry practice - use the sector's estimating indicators, association data or regression on the firm's own projects, and state the basis in the estimate notes.

5. Applicability and the standing warning (clause 4.1.3 item 1): "Applied mainly where design depth is insufficient, the proposed project differs in scale from similar built projects, the design is standardised and serialised, and the sector's indexes and coefficients are complete." The same clause warns: "as the capacity index is highly sensitive to the result, fix it on the basis of deep study. For most projects with similar works or similar works costs to refer to, whole-project use of the capacity index method is generally inappropriate; it is recommended only where the production system has no defined product, taking the process equipment of the production system as the object."

6. Division against other methods (clause 4.1.3):

  • Coefficient method: base E on the main works cost or main process equipment cost, percentages P1, P2, P3 of E for auxiliary and ancillary works, price/cost differences corrected by f1, f2, f3, plus case-specific other capital costs I. For "insufficient design depth, high weight of the main works or main process equipment, complete sector coefficients".
  • Ratio (Lange) method: from K, the share of main process equipment investment in total project investment; estimate equipment from quantities Qi and delivered prices Pi of n equipment types, then back out the total: C = sum(Qi x Pi)/K. Same applicability; reliability rests on K's stability.
  • Indicator method: quantities of unit works or elements x corresponding indicators of similar built projects, plus other costs, contingency, construction-period interest and working capital to the total. "The indicator method is the most reliable, relatively accurate" - but only with a truly matching benchmark project: identical parts use its indicators directly, differing parts (ancillary works or unit works within the main works) must be corrected.
  • Hybrid: combine two or more methods by design stage and depth, national / regional / sector indicators and the consultant's own database - typically indicators for building works and the capacity index method for equipment that cannot be quoted.

7. Stage selection (DB42/T 823-2021 clause 5.2.2): "At the project proposal stage the estimate may use the capacity index, coefficient, ratio, indicator or hybrid methods; at the feasibility study stage the indicator method is preferred." The same code requires: methods may be single or combined; the cost breakdown must satisfy its clause 6.2.3; "coefficients and indicator price and cost levels shall be adjusted to the actual level of the project location and the estimate year"; boundary-condition differences (land, access, utilities, municipal provision) unlinked to the main production content shall be corrected case by case.

Applicable boundaries

  • Prefer the capacity index method where comparable built projects exist, the capacity gap is quantifiable and sector indexes are complete; not applicable otherwise.
  • Not for whole projects: narrow it to the process equipment of the production system; with ample similar costs, switch to the indicator method.
  • It is a rough estimate: tiny index errors are amplified through the power - the basis and source of X must be stated in the estimate notes.
  • The coefficient and ratio methods presuppose high works or equipment shares and complete sector coefficients; the ratio method further needs a stable, comparable K.
  • The indicator method needs a genuinely matching benchmark with item-by-item correction of time, place and scope differences - otherwise its "high accuracy" does not hold.
  • f corrects only price and cost levels - not scale, process or product-mix changes; f = 1.0 only means the price levels match.
  • The 0.6~0.7 / 0.8~0.9 bands are experience, not normative values - cite the basis when used in deliverables.

Further reading

  • T/ZBD 100.2-2022 clause 4.1.3 items 1-5 (five methods, formulas and applicability).
  • DB42/T 823-2021 clauses 5.2.2 (method choice) and 6.2.3 (cost breakdown).
  • GB/T 50875-2013 clause 3.1.2 (terminology).
  • Scale-index values: the investment estimate compilation and review rules system and sector indicator notes.