Four-step back-calculation of the minimum acceptable profit rate for bid pricing, and the statutory floor
The minimum acceptable profit rate is back-calculated from corporate individual cost: minimum bid P_min = corporate individual cost C + minimum acceptable profit pi_min, rate r_min = pi_min / P_min. pi_min comprises financing cost (interest on advances/deposits), risk premium (changes, material inflation, lump-sum risks), allocated fixed costs (head-office overhead), and the strategic floor. Statutory floors: the bid must not be below cost nor above the maximum bid price (GB/T 50500-2024 Article 6.1.3); below-cost bids shall be rejected at evaluation, obviously lower bids require written cost justification. The cost basis is corporate individual cost (measured via corporate quotas); calculation worksheets must be retained.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第6.1.3条
- 招标投标法实施条例 第51条
- 住建部令第43号(2018修正) 第42条
- 建筑工程施工发包与承包计价管理办法(建设部令第107号) 第五条
- DBJ/T 15-115-2016 广东省建设工程交易规范 第5.3.3条
Topic Positioning
This card covers quantifying the "minimum acceptable profit rate" for bid pricing—back-calculating the minimum acceptable bid and profit rate from corporate individual cost—and the statutory floors that must be held. For setting price floors before bid decisions.
Core Conclusions
Four-step back-calculation: (1) compile a cost budget with corporate (private) quotas to get corporate individual cost C (labor/materials/equipment + site management + fees and taxes; under the 2024 edition, fees are already embedded in all-in unit rates); (2) add financing cost: interest on advances = advance amount x financing rate x occupation period (performance deposits and delayed progress payments likewise); (3) add risk premium: per contractual risk allocation (lump sum/unit rate), material inflation risk at experienced rates; (4) add allocated fixed costs (head-office overhead and bidding costs spread over annual target output) and the strategic floor (minimum shareholder return / new-market entry, may approach zero). Sum to pi_min; minimum bid P_min = C + pi_min; r_min = pi_min / P_min x 100%; compare against the maximum bid price—when margin inside the ceiling is insufficient, either cut cost or walk away. Statutory red lines: bids must not be below cost or above the maximum bid price; below-cost bids shall be rejected by the evaluation committee; obviously low bids require written cost-calculation justification, and those demonstrated as below corporate cost are not recommended for award.
Applicable Boundaries
"Cost" means corporate individual cost (measured via corporate quotas/actual cost data), not social average cost or quota base prices—the enterprise must produce cost calculation worksheets for the written justification. Industry experience values (gross margin 3%-5%, net margin 1%-3%) are references only; with wide variance in advance capacity and management levels, measure your own. What truly decides whether a project is worth bidding is often cash flow, not profit rate: a project with poor collections can lose money despite a high profit rate. Strategic underpricing (below cost) is unlawful—not an option.
Further Reading
GB/T 50500-2024 Article 6.1.3 (bid not below cost, not above maximum bid price); Implementation Regulations of the Bidding Law, Article 51 (below-cost rejection); MOHURD Order No. 43 (2018 revision), Article 42 (written justification for obviously low prices); Measures for Pricing of Construction Contracting (MOHURD Order No. 107), Article 5 (cost = direct + indirect; two pricing methods: unit-rate-of-labor-material and all-in unit rate); local trading standards (e.g., DBJ/T 15-115-2016 Article 5.3.3) contain similar restrictions.
Keywords
- 最低可接受利润率
- 投标报价利润测算
- 企业个别成本
- 资金成本
- 风险溢价
- below-cost tendering
- 投标报价策略