Rules for determining unit prices of construction water and power in railway estimates and budgets (China Railway system) (TB 10811-2024 Clauses 2.2.4/2.2.5)
Construction water base-period price 0.55 yuan/t (covering only pumping within 20 m head); general-region compilation-period = base + water resource fee, special water-scarce/difficult-intake regions analysed according to the water supply scheme; construction power base-period price 0.47 yuan/kWh, compilation-period by local power source (Y-local = Y-base x (1 + 7%) + 0.03 yuan/kWh), centralized/distributed diesel generation, or composite price (weighted by consumption) — all prices exclude deductible input VAT, with base-to-compilation differences booked as price differences.
Applicable Codes
- TB 10811-2024 第2.2.4、2.2.5条
- TB 10801-2024 第3.2.5、3.2.6条
Topic Positioning
How to determine unit prices of construction water and construction power in the compilation of railway estimates and budgets (China Railway system) (TB 10811-2024 Clauses 2.2.4, 2.2.5) — supporting unit-price parameters of the material-cost chapter, applied together with norm-based material prices for estimating per TB 10811 (TB 10801-2024 Clause 3.2.6).
Core Conclusions
Construction water: base-period price 0.55 yuan/t, covering only pumping costs at heads of 20 m and below; general-region compilation-period price = base-period price + water resource fee charged per national or provincial rules. In water-scarce or difficult-intake regions, the tax-exclusive compilation-period price may be analysed according to the water supply scheme in the project execution plan (construction methodology and site organization), with related large temporary works included (water supply mains, deep wells, etc.); where tap water must be used, analyse per local regulations. Construction power: base-period price 0.47 yuan/kWh. Compilation-period prices by supply scheme in three types: (1) local source, Y-local = Y-base x (1 + c) + f1, c = 7% (wastage rate of transformation/distribution equipment and lines), f1 = 0.03 yuan/kWh (amortization of repair, installation, removal of transformation/distribution equipment and line operation and maintenance); (2) centralized diesel generation, covering generator-shift costs of various types with usage rate R = 5%, cooling water cost S = 0.02 yuan/kWh, shift-hour utilization factor B = 0.8, output factor M = 0.8; (3) distributed diesel generation, weighted by shift output of various generators. Where local and self-generated power are used together, weight-average by consumption proportion. All prices exclude deductible input VAT, with compilation-period vs base-period differences booked as price differences.
Applicable Boundaries
Applies only to compilation of railway estimates and budgets (China Railway system); base-period prices are unified code parameters, and compilation-period prices must be set per the project location's supply scheme and market surveys; fuel price differences for construction machinery are included in the price differences for plant and small tools cost, not here.
Further Reading
See TB 10811-2024 'Norms for on-costs and expenses for design estimates (budgets) of railway capital construction projects' Clauses 2.2.4, 2.2.5 and formulas (2.2.5-1)~(2.2.5-3); TB 10801-2024 'Measures for compiling design estimates (budgets) of railway capital construction projects' Clauses 3.2.5, 3.2.6; for material base-period prices see TB/T 10813-2024.
Keywords
- 工程用电单价
- 工程用水单价
- 地方电源
- 自发电
- 综合电价
- 基期单价
- 编制期单价
- 水电单价