Pricing yardstick of the railway works budget quota manual for demolition works: counting only labour and machine-shift consumption multiplied by demolition coefficients by object category, excluding material cost, plus operating-height adjustment coefficients
The railway quota system sets no separate demolition line items: the corresponding installation line item is taken and multiplied by a demolition coefficient. The Volume 8 (Power Works) preamble Table 3 of TB/T 10829-2024 multiplies both labour and machine-shift consumption by 0.40 for lighting fittings, transformer and distribution boxes, control/power/lighting packaged cabinets (boxes), cable brackets, cable troughs and trays; 0.75 for concrete poles and foundations; 0.80 for angle-steel towers, steel-tube towers, beacon towers, light bridges, steel columns, busbar structures and their foundations; 0.50 for overhead lines and cables; 0.65 for underground cable routes. The information works and signal works volumes under Guotie Kefa [2017] No. 33 give 0.7 for wiring systems and outdoor/indoor cables and 0.5 for equipment and materials, and expressly count 'only labour and machine-shift consumption (excluding instruments and meters)' with no material cost.
Applicable Codes
- TB/T 10829-2024 · Budget Quota of Railway Engineering (Volume 8: Power Works) 册说明 表3
- TB/T 10827-2024 · Budget Quota of Railway Engineering (Volume 6: Signaling Works)
- 国铁科法〔2017〕33号《铁路工程预算定额》信息工程册、信号工程册 综合说明
- TB 10012 · Code for Geological Investigation of Railway Engineering
- TZJ 2005—2017《铁路工程预算定额 第五册 通信工程》
Topic positioning
How the railway works budget quota system prices demolition: no separate demolition line items are compiled; the corresponding installation line item is taken and its labour and machine-shift consumption multiplied by a demolition coefficient by object category, with material cost excluded; plus coefficient adjustment for operating height. It contrasts with the independent demolition line items of local building repair quota manuals.
Core conclusions
I. Power works: TB/T 10829-2024 'Railway Works Budget Quota Manual, Volume 8: Power Works', volume preamble, Table 3 - adjustment coefficients of labour and machine-shifts for demolition works
| Demolition item | Labour consumption | Machine-shift consumption |
|---|---|---|
| Cross-arms, overhead line attachments, cable brackets, cable troughs, hangers, cable chases, trays, lighting fittings, transformer and distribution boxes, control / power / lighting packaged cabinets (boxes), photovoltaic power generation, automation system equipment and materials | 0.40 | 0.40 |
| Concrete poles and foundations | 0.75 | 0.75 |
| Angle-steel towers, steel-tube towers, beacon towers, light bridges, steel columns, busbar structures and their foundations | 0.80 | 0.80 |
| Overhead lines and cables | 0.50 | 0.50 |
| Underground cable routes | 0.65 | 0.65 |
(Rock and soil classification in that volume refers to the Code for Geological Investigation of Railway Engineering, TB 10012.)
II. Information works: Guotie Kefa [2017] No. 33 'Railway Works Budget Quota Manual', information works volume, general description
- Applies to new and rebuilt (extended) railway information works; the operating height (vertical distance from ground to the base or bottom edge of the object handled) is considered within 6 m; beyond it the quota labour and machine-shift consumption is adjusted by coefficient: up to 10 m x 1.25, up to 20 m x 1.4.
- Item 6: 'When this volume is used for demolition works, labour and machine-shift consumption (excluding instruments and meters) is adjusted by the coefficients listed in Table 2, and no material cost is charged.' Table 2 demolition coefficients: wiring systems, labour 0.7 / machine-shift 0.7; equipment and materials, labour 0.5 / machine-shift 0.5.
III. Signal works: Guotie Kefa [2017] No. 33, signal works volume, general description
- 'When this volume is used for demolition works, only labour and machine-shift consumption is listed (excluding instruments and meters). Labour and machine-shift consumption is determined by adjustment under the demolition coefficients listed in Table 1.' Outdoor and indoor cables 0.7 / 0.7; equipment and materials 0.5 / 0.5.
- Non-standard materials of unfixed quantity (such as assemblies, relays and the materials required for ZPW-2000 track circuits and their coding) already carry the labour and machine-shift consumption for installation inside the quota line items, but exclude the material consumption itself; when used, such materials are listed separately at design quantity.
- Optical cable laying and equipment-room environmental monitoring, not covered, may use the relevant line items of the 'Railway Works Budget Quota Manual, Volume 5: Communication Works' (TZJ 2005-2017).
IV. Borrowing rules for content not covered by the information works volume: trench digging, outdoor optical (power) cable laying, optical (power) cable jointing and testing, protection of optical (power) cables, terminal and branching device installation, power supply and equipment-room environmental monitoring systems, video surveillance systems, installation and commissioning of power and lightning-protection equipment, spliced-screen cabinet installation, plastic wire chases, coaxial cable and power cable laying, etc. should adopt the relevant quota line items of the 'Railway Works Budget Quota Manual, Volume 5: Communication Works' (TZJ 2005-2017); the equipment installation and commissioning line items of Chapters 3 to 10 all include the work of software installation and commissioning.
Applicable boundaries
- The demolition-coefficient method holds only inside the railway works budget quota system, and the coefficients stand as a package with 'excluding instruments and meters' and 'no material cost'; railway coefficients must not be applied directly to the independent demolition line items of local building repair quota manuals (where demolition already stands as its own line item, no coefficient applies).
- Coefficients are taken by object category: different objects (lines vs pole foundations vs towers/structures and their foundations vs underground cables) take different coefficients, never a uniform lowest or single coefficient; coefficients must not be borrowed across work categories (power / information / signal) or across volumes.
- Residual value and recovery of demolished objects, and the hauling and disposal of demolition debris, lie outside the quota work content and must be handled separately; the operating-height coefficients of the information works volume (1.25 / 1.4) target installation above 6 m only and are not mixed with demolition coefficients.
- Quota consumption must not be adjusted for site differences such as construction organisation or plant model unless expressly provided.
Further reading
- TB/T 10829-2024 'Railway Works Budget Quota Manual, Volume 8: Power Works', volume preamble: Table 3, adjustment coefficients of labour and machine-shifts for demolition works; rock and soil classification per TB 10012 'Code for Geological Investigation of Railway Engineering'.
- TB/T 10827-2024 'Railway Works Budget Quota Manual, Volume 6: Signal Works': scope of application, separate listing of non-standard materials, separate listing of bracketed materials, and the supporting demolition coefficients.
- Guotie Kefa [2017] No. 33 'Railway Works Budget Quota Manual', 'Part One: General Description' of each volume: information works volume Table 1 (operating-height adjustment coefficients) and Table 2 (demolition coefficients); signal works volume Table 1 (demolition works coefficient table).
- 'Railway Works Budget Quota Manual, Volume 5: Communication Works' (TZJ 2005-2017) - the borrowing source for items missing from the railway information and signal volumes.
Keywords
- 拆除系数
- railway works budget quota manual (China Railway)
- 不计材料费
- 电力工程
- 信息工程
- 信号工程
- 操作高度调整系数