The building repair works quota (railway 2024 building volume): scope of application, auxiliary work already included (30m haul, vertical transport, propping and watch), and the quantity rules of demolition and strengthening items
The 'repair works' section of the railway 2024 building quota applies to piecemeal demolition and structural strengthening of buildings - not to whole-building demolition. The items already include propping and strengthening of the building and adjoining parts, site watching, hauling reusable material and debris to designated points within 30m, vertical transport, and clearing, stacking and tidying. Demolition always measures 'as actually removed': roofing by removed area; masonry by removed volume (holes up to 0.03m2 not deducted); ceilings by horizontal projected area (interior columns not deducted); floors by horizontal projected area (skirtings merged in); concrete and reinforced members by removed volume. Static cutting measures the cut face area; where cut blocks need breaking, the concrete demolition item applies x 0.80. Steel demolition measures mass from the drawings (no deduction for holes, cropped limbs or edges; electrodes, rivets and bolts add no mass); steel-plate and carbon-fibre strengthening measure the actually bonded area (laps included).
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(册说明 第九节 修缮工程;Ch. 1 土建工程 第九节 修缮工程)
Positioning
The scope boundary of the building repair (piecemeal demolition, structural strengthening) quota, where 'included' ends, and the quantity rules of demolition and strengthening items - for judging, when pricing existing-building refurbishment budgets, whether a task is a separate item and on what unit.
Core conclusions
1. Scope (the red line) This section applies to piecemeal demolition and structural strengthening of buildings - not whole-building demolition.
2. Included content (no separate items) Propping and strengthening of the building and adjoining parts, site watching, hauling reusable and waste materials to designated points within 30m, vertical transport, clearing and stacking. That is: haulage within 30m, propping and watching, and post-demolition clearing are all inside; only haulage beyond 30m is charged separately.
3. Trade boundaries of demolition items (deciding separate items)
- Tiled roof demolition includes battens, reed mats, bricks, stone slabs and everything above the substrate;
- whole door-and-window removal includes frame and leaf; roof-light removal includes the roof-light timber, finish and roofing;
- ceiling removal includes hangers, framing and finish;
- floor removal excludes bedding demolition (bedding is a separate item);
- concrete member removal includes cutting rebar, chiselling and dropping; large members (beams, columns, slabs, trusses) needing gin poles and derricks - erect and dismantle separately;
- truss removal includes cutting anchors, wind and horizontal bracing and all attachments.
4. Conversions and banding of strengthening items
- Static cutting items divide by blade position into horizontal and vertical, compiled for concrete; cutting brick masonry etc. takes the item x 0.60.
- Concrete strengthening excludes rebar, embedded plates and mesh; the enlarged-section item suits encasing concrete on retained structure, its consumption already covering the levelling fill for hack-chamfered surfaces.
- Narrow steel bonding and narrow carbon-fibre sheets are compiled for widths under 150; wide carbon-fibre over 150; double-layer bonded steel takes the sum of both plate thicknesses.
- Carbon-fibre items already include lap and wastage.
- Post-installed rebar items exclude the rebar itself; chemical-anchor items include anchors and caps.
5. Quantity rules (original wording)
- Roof demolition: actually removed area.
- Masonry demolition: removed volume, holes and members up to 0.03m2 not deducted.
- Ceiling demolition: horizontal projected area, interior columns not deducted.
- Floor demolition: horizontal projected area, skirtings merged.
- Concrete and reinforced member demolition: removed volume.
- Static cutting: cut-face area; oversize cut blocks needing breaking take the concrete demolition item x 0.80.
- Steel demolition (stairs and rails apart): mass per the drawings, holes, cropped limbs and edges not deducted, electrodes, rivets and bolts not added.
- Steel and carbon-fibre strengthening: actually bonded area, laps included.
- Masonry mesh-and-mortar strengthening: strengthened area, quantities tied into floors and walls included.
Applicable boundaries
- Piecemeal demolition and strengthening only; whole-building demolition is out of scope - price it under demolition quotas or whole-building terms.
- Demolition quantities are always 'as actually removed' (removed area / volume / horizontal projection) - unlike new works 'per design drawings'; never mix the two.
- 30m haul, vertical transport, propping and watching, clearing and stacking are inside the items - charging them again is double pricing; debris haulage beyond 30m follows the transport items.
- Floor demolition excludes bedding; large-member lifting gear is extra - the two most frequent omission / duplication points.
- Conversion factors (masonry cutting x 0.60, breaking after cutting x 0.80) must be noted against the item number; unnoted means unconverted.
- Item numbers and work contents change with the edition - check the current volume notes across versions.
Further reading
- TB/T 10831-2024 Volume 10 (building works), volume note section 9 'repair works': rule 1 (scope), rule 2 (included), rules 3-9 (trade boundaries), rules 10-13 (strengthening conversions and main materials), rule 14 (nine quantity rules).
- The same volume chapter 1 section 9 demolition and strengthening items; debris haulage beyond 30m under the civil-engineering transport items.
Keywords
- 修缮工程定额
- 房屋拆除
- 拆除工程量计算规则
- 静力切割
- 碳纤维布加固
- 粘钢加固
- 零星拆除
- 30m运距