TB/T 10823-2024 bridge volume over-water construction definition: by construction method, not water depth (vessel work/trestle/island building); depth only sets the drilling platform step

The "over-water" definition in TB/T 10823-2024 Volume 2 looks at construction method with no numeric depth boundary: over-water quotas apply to works designed to be executed from vessels and to works on over-water trestles not connected to land; where the trestle connects to land, concrete switches to land mixing and transport, concreting and rebar adjust vessel counts per the project execution plan (construction methodology and site organization), and river flats and mid-water islands use land quotas. Depth only sets the over-water drilling platform step: QY-219 dia <=2.0 m depth <=5 m; QY-220 dia <=3.5 m depth <=10 m; QY-221 dia <=3.5 m depth <=20 m; QY-218 platform on steel cofferdam. At equal diameter and stratum, over-water drilling costs about 2.2x land; the gap is mainly vessel plant + about 40% more labor + shaped-steel positioning materials; underwater concreting is about 4.4x; over-water also needs the working platform — the largest single share of the total gap.

Applicable Codes

  • TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程(册综合说明第二条;Ch. 1第四节钻孔桩与挖孔桩 (九)水上钻孔工作平台 QY-218~QY-221)

Topic Positioning

The rules defining "over-water construction" in TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works" (by construction method, not depth), the role of depth (only the drilling-platform step), and the composition of over-water versus land price differences for the same pile — directly usable in railway bridge and culvert cost compilation and audit.

Core Conclusions

  1. Over-water/land boundary — by construction method, not depth. Volume General Notes, item 2, as written: "The over-water quotas apply to works designed to be executed by vessels and to works on over-water trestles not connected to land. Over water, where a trestle, trestle-plus-platform, or embankment is used (the trestle being connected to land), concrete works use land mixing-plant mixing and transport, and vessel counts for concreting, rebar, and other over-water works are adjusted per the project execution plan; embankments or trestles are booked separately per Chapter 1 or Chapter 5 of this volume. Construction on river flats and mid-water islands uses land quotas." Decision rules: (1) vessel execution per design (drilling/concreting from vessels) -> over-water quotas; (2) over-water trestle not connected to land -> over-water quotas; (3) trestle / trestle-plus-platform / embankment (trestle connected to land) -> concrete mixed and transported as land, concreting and rebar vessel counts adjusted per the project execution plan, trestle/embankment booked separately; (4) river flats, mid-water islands -> land quotas. The volume has no numeric "X m of water = over-water" boundary; depth only affects platform step selection.

  2. Role of depth — the over-water drilling platform steps by pile diameter + depth (unit 100 m2): QY-218 platform on steel cofferdam (lowest step, about half of QY-219); QY-219 drilling platform, dia <=2.0 m, depth <=5.0 m; QY-220 dia <=3.5 m, depth <=10 m; QY-221 dia <=3.5 m, depth <=20 m (about 1.8x the <=5 m step).

  3. Composition of the over-water vs land gap (dia <=1.25 m, sandy gravel, impact drill): (1) Drilling (10 m): over-water about 2.2x land. Composition: labor up about 40% (class III labor 19.570 -> 27.814 shifts — lower efficiency working from vessels); impact-hole-making rig shifts roughly equal; vessel plant unique to over-water and the largest share (diesel tugs, transport barges, diving boats, work barges); cranes one size up (land <=25 t truck crane -> <=50 t crawler crane); materials: land includes 7.134 t of slurry water, over-water has no "water", bentonite up about 190 kg, plus channel/angle steel, plate, and galvanized wire for rig positioning and platform stiffening. (2) Underwater concreting (10 m3, placing only; concrete materials separate): over-water about 4.4x land, machinery changing from a single truck crane to a floating-crane, barge-crane, concrete pump, placer, transport barge, tower crane, and tug combination. (3) Over-water piles also need items land piles do not: the over-water drilling platform (QY-219/220/221 by depth step) or the cofferdam platform (QY-218); the trestle scheme books trestle items (single step, depth <=10 m). This far exceeds the drilling difference itself — the largest share of the over-water vs land total gap.

  4. Compiling tip: price each over-water pile by split BOQ items: (1) drilling (over-water step by stratum/diameter) (2) working platform (step by depth <=5/10/20 m) (3) concreting (over-water) (4) steel casings, rebar-cage making/erection, and transport (rebar quotas exclude transport of formed rebar from the central yard — book per the basic quotas). Where the drawings show island-building or shore-connected trestle schemes, use land quotas + separate trestle/embankment items.

Applicable Boundaries

  • Applies to budget/estimate compilation and audit under TB/T 10823-2024 Volume 2; the volume covers inland railway bridges and culverts.
  • Over-water/land is judged by the designed construction method, never by depth alone; depth only selects the over-water drilling-platform step (<=5/<=10/<=20 m).
  • Quota base prices are base-period; adjust differences per the price-difference rules at compilation period (adjust prices, not quantities; consumptions must not be altered); this display card carries no figures — price by the quota volume itself.
  • For road-rail bridges, the highway deck may use highway quota items other than the cable-stayed composite slab and wet joints (unrelated to this volume's over-water rules).

Further Reading

See TB/T 10823-2024 "Railway works budget quota, Volume 2: bridge and culvert works": Volume General Notes item 2 (over-water/land general rule; note also auxiliary structures amortized in, rebar inclusive of waste and couplers, prestressing tendons inclusive of 4% waste (9% when working length excluded), precast element transport booked separately, etc.); Chapter 1 Section 4 "(9) over-water drilling platform" QY-218~QY-221 (platform on steel cofferdam, and the three steps dia <=2.0 m depth <=5.0 m, dia <=3.5 m depth <=10 m, dia <=3.5 m depth <=20 m); drilling items land QY-95 and over-water QY-151 (dia <=1.25 m sandy gravel) and over-water QY-148 (dia <=1.25 m soil); concreting items QY-204 (land non-pump) and QY-208 (over-water impact drill). Trestles/embankments per Chapter 1 or Chapter 5 of this volume; formed-rebar and cage transport and precast element transport per the basic quotas.