Quantity take-off and double-counting prevention for field joint coating and damage repair of factory-prefabricated anti-corrosion pipes: whole-pipe anti-corrosion quota line items must not be re-applied; joint coating counted by weld count (per joint/spot) with per-joint nominal length converted to area; damage repair graded by damage size; dual-track pricing of BOQ m2 versus quota joints
The factory-applied anti-corrosion coating cost is already inside the material price of finished coated pipes, so only field joint coating and damage repair may be counted on site; painting, anti-corrosion coating or coal-tar epoxy quota line items must not be applied again over the whole pipe length or surface (GB/T 50856-2024 clause 3.0.8 opens an exception only for painting the design expressly requires to be completed on site and for repainting in reconstruction or extension projects; DB11/T 2382-2024 clauses 7.4.52 and 7.4.53 confine field anti-corrosion to the joints - heat-shrink sleeves and three-layer polyethylene heat-shrink tape are measured by weld count, and coating-type joint methods take the same-scope line item with labour x 1.10). Joint coating count = number of girth welds (standard-length sections - 1, plus fittings, valves and tie-in joints); developed area per joint = pi x pipe OD x nominal length per joint (400 mm for OD no more than 426 mm, 600 mm for OD above 426 mm); the BOQ item is measured in m2 of design-shown surface area per GB/T 50856-2024 table M.9.1 (code 031209) while the quota counts per joint/spot, so units must be converted before pricing; damage repair is treated per spot, graded by damage depth and puncture size (GB/T 50538-2020 clause 8.5.1).
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 第3.0.8条、App. M Table M.9.1、K.9.4条
- DB11/T 2382-2024 建设工程施工消耗量标准 第7.4.50~7.4.54条
- GB 50840-2012 矿浆管线施工及验收规范 第10.3.3条
- GB/T 50538-2020 埋地钢质管道防腐保温层技术标准 第8.5.1条
- DB13(J)/T 8056-2019 市政给水管道工程施工质量验收标准 第5.3.7条、第6.1.2条
- SJG 111.4-2022 城市地下综合管廊工程消耗量标准(Vol. 4 入廊管线安装工程)第2.2.5条
Topic scope
Factory-prefabricated anti-corrosion (3PE / FBE / coal-tar epoxy) pipelines at field installation: the quantity rules and measurement units for joint coating and damage repair, and the double-counting tests and pricing split for 'which anti-corrosion content must not be counted a second time'.
Core conclusions
I. Negative test: whole-pipe anti-corrosion line items must not be re-applied to prefabricated coated pipes
- Work-content boundary of installation items (GB/T 50856-2024 clause 3.0.8): 'The work content of the equipment, piping and fittings installation items in this standard shall all include touch-up of primer and finish coats after installation is complete. Where the design notes require painting to be completed on site, or where existing equipment and piping in reconstruction or extension projects is repainted, items shall be coded and listed under the corresponding items of Appendix M, painting, anti-corrosion and insulation works.' The installation items thus open a gate only for 'touch-up / repair': a separate Appendix M listing is created solely where the design expressly requires on-site painting or repainting in reconstruction or extension - a finished prefabricated coated pipe is neither, so whole-pipe anti-corrosion must not be listed again.
- Field anti-corrosion is confined to the joints (DB11/T 2382-2024 clauses 7.4.52 and 7.4.53): '7.4.52 Field anti-corrosion of steel pipe should set corresponding items separately by pipe diameter for the different anti-corrosion materials; quantities of coal-tar epoxy glass cloth, inorganic zinc-rich paint, inorganic zinc-rich paint polyurethane composite and cement mortar anti-corrosion shall be calculated by length from the dimensions shown on the design drawings, and quantities of heat-shrink sleeve and three-layer polyethylene heat-shrink tape anti-corrosion shall be calculated by the number of welds.' '7.4.53 For field anti-corrosion at steel pipe joints (except heat-shrink sleeve and tape anti-corrosion), construction consumption follows the corresponding provisions of clause 7.4.52 of this standard, and labour consumption should be multiplied by 1.10.' Coating-type joint methods (coal-tar epoxy etc.) therefore take the same-scope line item of 7.4.52 with labour x 1.10; heat-shrink sleeve or tape is measured by weld count without the 1.10 factor.
- Joint insulation of prefabricated insulated pipes is already inside pipe installation (DB11/T 2382-2024 clause 7.4.44): 'Thermal pipelines should have items set separately by laying method (direct burial, square duct, tunnel) and by pipe diameter for bare steel pipe and prefabricated insulated steel pipe; construction consumption should include argon-arc root welding, joint insulation, pressure testing, flushing and one overall final pressure test, and quantity shall be calculated by the centre-line length shown on the design drawings, without deducting the lengths occupied by ancillary structures, fittings and valves.' The clause covers the insulation interface only - the outer jacket and anti-corrosion joint coating at the joints are still counted separately, and the two interfaces must not be mixed.
- Corroboration from finished-pipe wording (SJG 111.4-2022, Consumption Standard for Urban Underground Utility Tunnel Works, Volume 4): 'Pipe weld anti-corrosion applies to joint coating and damage repair at welds of factory-coated metal pipes and fittings. Where repair patches are used to repair welds, execute the line items for DN no more than 100 mm, converting the material, all else unchanged.'
- Wording history (a historical comparison, not a current pricing basis) - Jing Jian Fa [2012] No. 538, General Installation Volume 10 (gas pipelines), chapter note 3: 'The quotas for outdoor anti-corrosion steel pipe installation and laying and for anti-corrosion fitting installation do not include field anti-corrosion at joints; joint anti-corrosion cost is calculated separately or allowed for in the anti-corrosion steel pipe price.'
II. BOQ and quota run as two tracks with different units; convert before pricing
- BOQ layer (national standard): GB/T 50856-2024 table M.9.1 'pipe joint coating and repair works (code 031209)' - 'The item setting, item description content, measurement units and quantity take-off rules for the pipe joint coating and repair works BOQ items shall follow the provisions of table M.9.1'; joint coating and repair is measured in m2 of surface area shown on the design drawings.
- Quota layer (local, Beijing wording as the example): Jing Jian Fa [2021] No. 201, General Installation Volume 12, Chapter 5 'pipe joint coating and repair works' - chapter notes: the chapter covers painting, anti-corrosion and other pipe joint coating and repair, with 2 sections and 220 line items; it applies to anti-corrosion works for joint coating and repair of metal pipes; manual operation is assumed throughout, and the work content includes manual derusting. Quantity rule: 'pipe-end painting and pipe-end anti-corrosion are calculated by the number shown on the design drawings' - the quota unit is the joint, so pricing requires conversion at m2 per joint.
- Grading wording (chapter note 5; line items graded by pipe diameter x anti-corrosion class): chlorosulfonated polyethylene paint, coat 0.3-0.4 mm thick; coal-tar epoxy paint - normal class 0.3 mm (one primer coat, two finish coats), reinforced class 0.5 mm (one primer coat, three finish coats plus one layer of glass cloth), extra-reinforced class 0.8 mm (one primer coat, four finish coats plus two layers of glass cloth); polyethylene adhesive tape - normal class no less than 0.7 mm (inner tape lapped 50%), reinforced class no less than 1.0 mm (inner tape 50% + outer tape 10%), extra-reinforced class no less than 1.4 mm (both tapes 50%). Section 1, painting, starts at line item 5-1 (e.g. chlorosulfonated polyethylene paint, nominal diameter up to 100 mm, primer / intermediate / finish coats listed separately, unit: joint).
III. Joint count and area per joint
Chapter note 4: 'The nominal length of each pipe joint coating is 400 mm for pipes of outside diameter below 426 mm and 600 mm for pipes of outside diameter above 426 mm.'
- Developed area per joint = pi x pipe OD (m) x nominal length per joint (m)
- Joint coating count = girth weld count = number of standard-length sections - 1, plus the joints at fittings, valves and tie-ins (counts taken from the welding tally)
- Worked example (DN300, pipe length 1000 m, standard length 12 m): sections = ceil(1000/12) = 84, girth welds = 84 - 1 = 83 joints; OD 0.325 m, area per joint = pi x 0.325 x 0.6 = 0.613 m2, total joint coating area = 83 x 0.613 = 50.85 m2; against the whole-pipe outer surface of pi x 0.325 x 1000 = 1021.02 m2, joint coating is about 4.98%. DN200 (OD 0.219 m, 0.4 m per joint): 0.275 m2 per joint, 83 joints = 22.84 m2.
IV. Damage repair per spot, graded by damage depth and puncture size (GB/T 50538-2020 clause 8.5.1)
For repair of anti-corrosion insulated pipes with polyethylene protective coating: 1 where the scratch depth in the protective coating is greater than 1/10 but less than 1/3 of the wall thickness, a hot-melt repair stick should be used; 2 where there are punctures, holidays or scratches deeper than 1/3 of the protective coating thickness, and the puncture area is no more than 100 mm x 100 mm, a repair patch should be used, sized so that its edge is no less than 100 mm from the puncture edge, and a small amount of adhesive should squeeze out evenly around it after installation; 3 where the axial length of the damage is less than the joint-coating width, repair should follow the joint-coating requirements for the polyethylene protective coating; 4 where the axial length of the damage exceeds the joint-coating width, the protective coating should be remade; 5 where the insulation layer is damaged deeper than 10 mm, insulation repair should be carried out and completed before outer-jacket repair; polyurethane foam insulation damage should first be trimmed to a regular shape, then inlaid with prefabricated polyurethane insulation blocks or filled by foaming in place, and the surface trimmed flush.
V. Material wording for joint coating and repair
Main materials such as heat-shrink sleeves (tape), repair patches and repair sticks are counted separately at their actual specifications; the other material consumption in the line item is unchanged and only the main material is converted (the SJG 111.4-2022 wording for repair patches is 'convert the material, all else unchanged'); heat-shrink sleeves are counted per piece - 'radiation cross-linked polyethylene heat-shrink sleeve anti-corrosion is counted per piece, one piece per weld' - that is, one sleeve corresponds to one weld.
VI. Double-counting checks (pricing split points)
(1) The joint count follows the welding (weld) tally, never an estimate of 'pipe length x an experience factor'; cross-check against the back-calculation from standard lengths: girth welds = ceil(total length / standard length) - 1, plus fittings, valves and tie-in joints. (2) The joint coating / repair area must not be priced alongside the whole-pipe outer surface area; the whole-pipe surface serves only as a comparison and plausibility check (for prefabricated pipes of the same specification the joint coating area is typically on the order of 5% of the whole-pipe area - a large deviation calls for re-checking the weld tally). (3) Joint insulation (already included in pipe installation under DB11/T 2382-2024 clause 7.4.44) and the joint outer jacket / anti-corrosion coating must not be mixed. (4) Repainting in reconstruction or extension and on-site touch-up are listed separately under GB/T 50856-2024 clause 3.0.8, apart from joint coating on new pipelines.
Applicable boundaries
- Applies to field joint coating and damage repair of factory-prefabricated coatings on steel (metal) pipes; plastic and other non-metallic pipes and lined pipes are outside this wording.
- The 'nominal 400 mm / 600 mm per joint' and '2 sections, 220 line items' follow the Beijing 2021 budget consumption standard, General Installation Volume 12; other provinces and industry quotas must be checked against their own editions, as a different nominal length directly changes the area conversion.
- 'Joint coating count = weld count' holds only for heat-shrink sleeve / tape (pieces = welds) or coating-type methods priced per joint; where local wording sets measurement by length (e.g. coal-tar epoxy glass cloth anti-corrosion calculated by the design-shown dimensions as a length), conversion must follow that rule - not per joint by default.
- BOQ table M.9.1 is measured in m2 and the quota in joints / spots; the two cannot be mixed directly, and unit conversion with a retained conversion sheet must be completed before pricing.
- Jing Jian Fa [2012] No. 538 is the 2012 edition and serves only as a wording-history reference; current pricing should follow Jing Jian Fa [2021] No. 201.
Further reading
- GB/T 50856-2024 'Quantity Take-off Standard for General Installation Works', clause 3.0.8; Appendix M 'Painting, Anti-corrosion and Insulation Works', table M.9.1 pipe joint coating and repair works (code 031209).
- DB11/T 2382-2024 'Consumption Standard for Construction Works', clauses 7.4.44, 7.4.52 and 7.4.53 (municipal pipe networks, X waterproofing, derusting and painting, anti-corrosion insulation, cathodic protection); clauses 6.10.34~6.10.38 (gas pipelines).
- GB/T 50538-2020 'Technical Standard for Anti-corrosion and Insulation Coatings of Buried Steel Pipelines', clause 8.5.1 (joint coating and repair).
- SJG 111.4-2022 'Consumption Standard for Urban Underground Utility Tunnel Works (Volume 4, In-tunnel Pipeline Installation Works)', gas works 2.1.9 (weld anti-corrosion and repair patches) and 2.2.5 (heat-shrink sleeve counted per piece, one piece per weld).
- Jing Jian Fa [2021] No. 201, General Installation Volume 12, 'Painting, Anti-corrosion and Insulation Works', Chapter 5 pipe joint coating and repair works: chapter notes 1-5, the quantity take-off rules, section 1 painting (from 5-1) and section 2 anti-corrosion (coal-tar epoxy normal / reinforced / extra-reinforced).
- The industry budget quota GYD-211-2000 series volume 'Painting, Anti-corrosion and Insulation Works' also carries a pipe joint coating and repair chapter; check the line-item numbers and measurement units against the edition in use before applying.
Keywords
- 补口补伤
- 预制防腐管
- 防重复计量
- 接口防腐
- 热缩套按焊口数量
- 每口取定长度
- 补伤片搭接宽度
- 人工系数1.10