Pricing and measurement of CCTV/QV/sonar in-pipe inspection: extended metres along the centre line of the pipe or culvert without deducting manholes, line items banded by diameter and inspection method, working conditions (water level, clearing and cleaning) and excluded work charged separately
CCTV in-pipe inspection of pipelines is measured in metres (m) by the extended length of the centre line of the pipe or culvert as designed (actually inspected), without deducting the length occupied by fittings or manholes; the CCTV line items are banded by internal diameter or height of the pipe, with 100m as the line-item unit, and QV and sonar likewise. The line items comprehensively allow for differences of pipe type, material and age, but exclude pipe plugging and reinstatement, desilting, culvert-wall washing, dewatering, and image analysis and assessment, digital mapping and archiving, and compilation of inspection deliverables, which are charged separately when they occur; desilting for the inspection and repair categories is charged at the labour, material and plant of the corresponding items multiplied by a factor of 1.5.
Applicable Codes
- 湖南省2025《市政排水设施维护工程消耗量标准》第一章管道检测(说明及工程量计算规则)、第二章说明第六条
- SJG 84-2020《市政维修工程消耗量标准 第二册 给水排水维修工程》第7.1.24条、第7.2.19条
- DB42/T 1615-2021《城镇排水管道检测与评估技术标准》第7.1.2条
- DB37/T 5298-2024《城镇雨污分流改造技术标准》第6.1.11条
- http://www.ccgp.gov.cn/cggg/dfgg/gzgg/201801/t20180108_9449748.htm
- http://changd.ccgp-hunan.gov.cn/f/m/pkg_detail/pkg_31707
Positioning
How CCTV (closed-circuit television) in-pipe inspection, QV (quick-view periscope) inspection and sonar inspection of pipelines are measured and priced, which quota line items they correspond to, and how the working conditions of the inspection affect the pricing boundary.
Core conclusions
1. Measurement basis: extended metres along the centre line, manholes not deducted.
- The consumption standards for municipal drainage facility maintenance (pipe inspection chapter) state: the chapter comprises 5 line items - manual pipe inspection, closed-circuit television inspection (CCTV), quick-view inspection (QV), sonar inspection and toxic gas testing; it applies to survey inspections of operating pipelines, emergency inspections under special circumstances, and completion inspections required by the employer. "This chapter does not include pipe flushing, clearing, plugging, flow diversion, desilting and off-site transport of silt, which are charged separately when they occur." Measurement rules: "Pipe inspection is computed by the length of the design pipe centre line in 'm', without deducting the length occupied by manholes"; "toxic gas testing is computed by the number of tests in 'occasions'". The CCTV line item is measured per 100m, with work content of "opening and closing covers, forced ventilation, equipment setting-up, lowering the inspection equipment, pipe inspection, image interpretation, retrieving the equipment, equipment cleaning, transport, completing the assessment report, etc.".
- The parallel items in the municipal maintenance works consumption standards carry the same basis: "CCTV (television) in-pipe inspection of pipes and culverts is computed, by internal diameter or height, by the extended length of the centre line of the pipe or culvert actually inspected as shown on the drawings, in metres, without deducting the length occupied by fittings or manholes. QV (quick-view) and sonar in-pipe inspection of pipes and culverts is likewise computed by the extended length of the centre line actually inspected, in metres, without deducting the length occupied by fittings or manholes."
- Summary: CCTV, QV and sonar are all measured by the extended metres of the section actually inspected (not the full network length; sampling is measured on the sampled sections), the lengths of manholes and fittings are not deducted, line items are banded by inspection method plus diameter (internal diameter or height), and the line-item unit is commonly 100m.
2. Principles for selecting line items (the three inspection types must not be mixed). The patrol-inspection item for wells and culverts, the in-pipe manual inspection item and the in-pipe endoscope inspection items observe the following principles: 1 the patrol-inspection item applies to general condition surveys of pipes and culverts and does not include in-pipe manual inspection below ground; 2 the in-pipe manual inspection item applies to personnel descents undertaken for pipe repair or clearing and does not include the various in-pipe endoscope inspections; 3 the in-pipe endoscope inspection items apply to detailed surveys before pipe repair, monitoring during the works and quality inspection after the works using dedicated instruments and equipment; 4 the items already allow comprehensively for differences of pipe type, material and age, and do not include pipe plugging and reinstatement, desilting, culvert-wall washing or dewatering, nor image analysis and assessment, digital mapping and archiving, or compilation of inspection deliverables and other analytical work - these are charged separately when they occur.
3. Associated costs must be listed separately and cannot be absorbed into the inspection items.
- Desilting: clearing box culverts, open channels and pipes and diver-assisted clearing do not include silt bagging (charged under the manual silt-bagging item); "for desilting of the inspection and repair categories, the labour, material and plant of the standard's items are multiplied by a factor of 1.5".
- Plugging and flow diversion, water transfer, dewatering, culvert-wall washing and off-site transport of silt are all outside the inspection chapter and are charged under the corresponding items or as incurred.
- Image analysis and assessment, defect grading, 3D/digital modelling and archiving of deliverables: some standards include these in the CCTV work content (including "image interpretation, completing the assessment report"), others expressly exclude them; this must be judged from the chapter notes of the standard in force at the place of execution and must not be applied across regions.
4. Pricing method. The mainstream method is an all-in unit rate per extended metre (covering equipment, labour, travel and the report), banded by diameter and inspection method (CCTV / QV / sonar); only where a single section is so short that mobilisation and set-up dominate do market or contract terms add mobilisation and set-up charged "per section (machine-shift / occasion)" - a contractual pricing arrangement that does not change the quota's basic metre-based measurement. Toxic gas testing is charged "per occasion" as a separate item.
5. Working conditions directly determine whether the item applies. DB42/T 1615-2021 Technical Standard for Inspection and Assessment of Urban Drainage Pipelines, clause 7.1.2, original text: "CCTV inspection shall comply with the following: a) television inspection shall not be carried out in water; the water level in the pipe shall be ensured to be no more than 20% of the pipe diameter and no more than 300mm; b) before structural inspection the pipe shall be cleared and cleaned; c) inspection shall be suspended where any of the following occurs: 1) the crawler cannot travel in the pipe or the push rod cannot advance; 2) the lens is fouled; 3) the lens is immersed in water; 4) the pipe is full of mist affecting image quality; 5) inspection cannot proceed normally for other reasons." The commentary notes: the in-pipe water level is the depth of water above the invert; the lower the better, but dewatering gets harder - the limits of no more than 20% of the diameter and no more than 300mm deep "can solve over 90% of pipe defect inspection problems, at an acceptable cost". Hence lowering the water level (plugging and diversion, dewatering) and clearing and cleaning are preconditions of inspection whose costs must be listed separately in pricing and must not be treated as included in the per-metre rate of the inspection item.
Applicable boundaries
- The measurement rules above come from local consumption standards (municipal drainage facility maintenance, municipal maintenance works); item banding and whether image interpretation and reporting are included must be checked against the current standard at the place of execution and must not be cross-applied between provinces.
- The measured length is the design centre-line length of the section actually inspected; for sampling or re-inspection, measure on the commissioned sections and state the scope and basis (completion inspection, defect re-check, before/after repair comparison).
- Whether CCTV inspection of new pipelines before handover is within the contract price is a contract-and-specification question, separate from the measurement rules here.
- Quota line items settle consumption and measurement only, not prices; rates should use the published price information or market price enquiry of the period of preparation - this card offers no rate conclusions.
- Where an inspection fails and repair and re-inspection follow, the measurement basis is as above; who bears the cost follows the allocation of responsibility.
Further reading
- Hunan 2025 Consumption Standard for Municipal Drainage Facility Maintenance Works, chapter 1 "pipe inspection" notes (5 items, scope, exclusions) and measurement rules; chapter 2 "pipe and culvert clearing" note 6 (desilting for the inspection and repair categories x 1.5).
- SJG 84-2020 Consumption Standard for Municipal Maintenance Works, Volume 2 Water Supply and Drainage Repair Works, clause 7.1.24 (selection principles and exclusions of the three inspection items), clause 7.2.19 (CCTV/QV/sonar measured by extended metres of the centre line, manholes not deducted).
- DB42/T 1615-2021 clause 7.1.2 and commentary (water level, clearing and cleaning, suspension conditions).
- DB37/T 5298-2024 Technical Standard for Urban Rain-Sewer Separation Works, clause 6.1.11 (CCTV inspection and image archiving before new pipes are commissioned).
- Public procurement pages for checking the BOQ itemisation and measurement units of inspection services: http://www.ccgp.gov.cn/cggg/dfgg/gzgg/201801/t20180108_9449748.htm ; http://changd.ccgp-hunan.gov.cn/f/m/pkg_detail/pkg_31707