Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-11

Where waterproofing primers (cold primer oil / primer coat / substrate treatment agent) sit in membrane waterproofing quotas: included in the membrane items or to be itemised separately

The test is not the operation's name but whether the executed membrane item's work content states brushing the primer and its consumption table lists the primer material: stated and listed means included - no separate itemisation, which would double count. The railway TB/T 10831-2024 Volume 10 roofing membranes FY-983 to FY-1000 and basement / kitchen / bathroom membranes FY-941 to FY-957 all list brushing primer in the work content - included, not recharged; TB/T 10834-2024 Volume 13 station works notes state that membrane seams, edge terminations and screed joint sealing are already in the quota while the cement mortar screed itself is not (screed chargeable, its sealing included). Beijing DB11/T 2382-2024 membrane items include brushing primer and set no separate cold-primer item; a few systems do set one (Jiangsu 2026 items 9-132 / 9-133 cold primer oil, first and each additional coat; Shenzhen SJG 181.5-2024 dedicated primer under other waterproofing), used only where the quota excludes it or the design requires separate application.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(FY-941~FY-957、FY-983~FY-1000)
  • TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程 册说明Ch. 2
  • DB11/T 2382-2024 建设工程施工消耗量标准 App. A A.9 屋面及防水工程(A-9-189、A-9-225、A-9-235)
  • SJG 181.5-2024 市政工程消耗量标准 Vol. 5 水处理工程 1.3.19 防水工程
  • GB 50108-2008 地下工程防水技术规范 第4.3.15条
  • DB33/T 1147-2018 建筑防水工程技术规程 第4.8.6条
  • JC/T 1069 沥青基防水卷材用基层处理剂
  • 江苏省建筑与装饰工程消耗量(2026版)9-132、9-133 冷底子油
  • 陕西新编消耗量定额(征求意见稿)9-32~9-35

Scope of the question

Where the primer brushed before membrane waterproofing (cold primer oil, primer coat, substrate treatment agent) sits in budget quotas - inside the membrane waterproofing items or itemised separately. For waterproofing pricing and review under railway, building, municipal or local consumption standards.

Core conclusions

Headline: the test is not whether the primer counts as an operation, but whether the executed membrane item's work content states brushing primer and its consumption table lists the primer material - stated and listed means included; no separate item, which would double count.

1. Railway TB/T 10831-2024 Volume 10 Buildings

  • Roofing membranes FY-983 to FY-1000, work content: cleaning the base, sealing division joints, brushing the primer, laying additional layers, applying adhesive, laying the membranes, terminating edges.
  • Basement, foundation, kitchen and bathroom membranes FY-941 to FY-957, work content: cleaning the base, sealing division joints, brushing the primer, laying additional layers, applying adhesive and membranes, terminating edges. Primers / adhesives enter the item's material costs (some items carry polyurethane coating, No. 401 adhesive etc.), not recharged.

2. Railway TB/T 10834-2024 Volume 13 Station and Yard Works, volume notes (verbatim)

    1. The waterproofing quota does not include the cement mortar screed; where needed, charge per the relevant quotas.
    1. Waterproofing works not compiled here may use the relevant items of Volume 10 Buildings.
    1. The seams and terminations of the membranes and the sealing of the screed are already in the quota and shall not be recharged. That is: the screed itself is chargeable, but its sealing and the membrane seams and terminations are included, not rechargeable.

3. Beijing DB11/T 2382-2024

  • A-9-225 SBS modified bitumen membrane (torch-on), raft, single layer; A-9-235 EPDM membrane (cold-adhered), flat, single layer - work content: cleaning the base, brushing the primer, laying additional layers and membranes, seams, terminations etc. (Table A.9.5-1 foundation membrane waterproofing).
  • A-9-189 EPDM membrane (cold-adhered), single layer - work content: cleaning the base, brushing adhesive (or primer), laying (torch-on) additional layers and membranes, edge finishing etc. (Table A.9.4-1 floor membrane waterproofing).
  • No separate cold-primer / primer item exists; some items' material tables fold the primer into other materials (1.5%) - not a ground for separate certification.

4. Jiangsu 2026 consumption standard

  • Membrane items carry the note: for wet-laid application, deduct the cold primer oil and add 0.206 m3 of 901-adhesive cement slurry, other contents unchanged - being deductible from the item shows the default includes it.
  • Separate items 9-132 / 9-133 cold primer oil, first / each additional coat (unit 10 m2; consumption 4.85 / 3.64 kg; labour 0.030 general + 0.080 / 0.060 skilled workdays) - used only where the quota excludes it or the design requires separate application.

5. Shaanxi new quota (consultation draft) Items 9-32 to 9-35 SBS modified bitumen membranes, work content: cleaning the base, brushing the primer, edge fixing battens etc., the full operation; the material table lists cold primer oil at 48.480 kg per 100 m2 (flat and vertical alike).

6. Shenzhen SJG 181.5-2024 Volume 5 Water Treatment Works Membrane work contents generally include brushing the primer; but under 4 other waterproofing sits a separate dedicated primer item - the typical separate-listing construct, matching design-required special substrate treatment.

7. Technical basis (compatibility, not pricing) GB 50108-2008 Technical Code for Waterproofing of Underground Works, Article 4.3.15: before laying membranes the base shall be clean and dry and brushed with primer; on wet bases use moisture-curing adhesive or a damp-interface isolating agent. The primer shall be compatible with the membranes and their adhesives, sprayed or brushed evenly without bare patches, and dry before laying. DB33/T 1147-2018 Technical Specification for Building Waterproofing, Article 4.8.6: primers for bituminous membranes - colloquially the primer or cold primer oil - work with bituminous membranes to improve bond, per JC/T 1069.

Applicability limits

  • Precondition: the item's work content plus consumption table of the executed quota version is the sole test. Different quotas (railway / building / municipal / local), versions and volumes differ - conclusions do not travel across quotas.
  • Not applicable / rechargeable: 1 the design requires additional primer treatment (moisture-curing on wet bases, dedicated impermeable primers); 2 the quota itself sets a separate primer item (Shenzhen other-waterproofing, Jiangsu 9-132 / 9-133) and the case is one of exclusion or separate design requirement; 3 the executed item's work content omits brushing primer and the table lists no primer (check first whether it folded into other material costs - folded means no separate certification).
  • Boundary: the screed itself chargeable, its sealing and the membrane seams and terminations included (railway station volume notes 2 and 4); where the waterproofing quota is uncompiled, borrow the Volume 10 items.
  • Base prices and consumptions change with versions; execute the current effective version.

Further reading

  • TB/T 10831-2024 Volume 10 Buildings, Chapter 1 civil works: item 8 basement, foundation, kitchen and bathroom waterproofing (2) membranes FY-941 to FY-957; item 9 roofing waterproofing (2) membranes FY-983 to FY-1000 (work contents and labour / material / plant base-price tables).
  • TB/T 10834-2024 Volume 13 Station and Yard Works, volume notes Chapter 2 masonry and movement joints, damp-proofing and waterproofing, items 2-4.
  • DB11/T 2382-2024 Appendix A building and decoration works, A.9 roofing and waterproofing: Table A.9.4-1 (A-9-189), Table A.9.5-1 (A-9-225, A-9-235).
  • Jiangsu consumption standard (2026): separate primer items 9-132, 9-133 and the wet-laid conversion note.
  • Shaanxi new quota (2024 consultation draft): membrane division 9-32 to 9-35.
  • SJG 181.5-2024 Volume 5 Water Treatment Works, 1.3.19 waterproofing (membrane / other waterproofing work contents).
  • GB 50108-2008 Article 4.3.15; DB33/T 1147-2018 Article 4.8.6 and JC/T 1069 primers for bituminous membrane waterproofing.

Keywords

  • 基层处理剂
  • 冷底子油
  • 底涂
  • 卷材防水定额
  • 工作内容
  • double counting
  • 屋面防水卷材
  • 湿铺法