Scope of application, included/excluded cost boundaries, material and coefficient adjustment rules, and measurement basis of the pipeline (renewal) repair and fittings renewal repair line items in Volume 2 (water supply and drainage pipelines) of SJG 84-2020, the consumption standard for municipal maintenance works
The cost boundaries of the water supply and drainage maintenance line items in Volume 2 of SJG 84-2020 reduce to four sentences: valve closure and sealing with pumping of pit water, pipe segment length, and the influence of ordinary trench-wall retention and bracing are comprehensively allowed for, with no adjustment for actual differences; trench excavation and retention, obstruction demolition, minor trench excavation, foundations and bedding, formwork and scaffolding, well sealing and unsealing, dewatering and diversion, in-pipe CCTV inspection and removal of old fittings are priced separately under Chapter 7 of the Volume (plastering under Chapter 5, blind plates under Chapter 2); where pipe materials (internal/external diameter, wall thickness, segment length, material) differ from those assumed in the line item, only materials are adjusted and all else stands, coefficients applying only where the text expressly says so (labour cost and machine-shift consumption x 1.18 for concrete pipe laid directly on trench soil foundation; labour cost and machine-shift x 1.5 for full-wrap reinforced concrete encasement; labour cost x 1.1 for the connection working-pit earthwork and bedding; labour cost x 1.5 for connections to prestressed concrete trunk pipes); fittings renewal repair is measured per the quantities shown on the design drawings, counted by number with diameter classes - reducers follow the larger bore side and tees and crosses the trunk pipe diameter - with valves or flanges connected to discs counted separately.
Applicable Codes
- SJG 84-2020 市政维修工程消耗量标准 第二册 给水排水维修工程 第 0.2 节、册说明 0.4.6、0.4.16
- SJG 84-2020 第二册 第1章 1.1.4 给水排水管道维修子目使用原则
- SJG 84-2020 第二册 第2章 2.1.3、2.2.1 给水排水管道附件设施维修
- 深圳市安装工程消耗量定额
Scope of the Topic
Within Volume 2 of SJG 84-2020, the Consumption Standard for Municipal Maintenance Works (Water Supply and Drainage Maintenance Works): the principles of application, the boundaries between costs included and costs not included, the material and coefficient adjustment rules, and the measurement basis of the line items for water supply and drainage pipeline (renewal) repair, for fittings renewal repair, and for new-to-old pipe connections - used to judge, in maintenance settlement, which content is 'comprehensively included and not separately chargeable', which must instead be priced under the Chapter 5 or Chapter 7 items, and which adjusts only the materials without touching labour and plant.
Core Conclusions
I. Scope of application and the preliminaries boundary (Chapter 1, principles for the use of line items, Clauses 1 and 2, original text)
- 'The line items for renewal repair of water supply and drainage pipelines apply to the new pipeline laying and old pipeline replacement works corresponding to the maintenance classification standard in Section 0.2 of this Standard. The line items comprehensively allow for the ordinary situation where the residual water in the old pipe flows out after the valves are closed and the pipe sealed, include the corresponding pumping measures for removing water from the pit, and do not include measures such as trench excavation and retention. Where the works encounter water supply and drainage preliminary works, including obstruction demolition, minor trench excavation, retention and bracing, foundations, bedding, reinforcement (embedded parts), formwork and scaffolding, well sealing and unsealing, dewatering and diversion, and in-pipe CCTV inspection, the corresponding line items of Chapter 7 of this Volume, General and Preliminary Items for Water Supply and Drainage Maintenance, apply.'
- Temporary water supply pipes, staged interception and sealing of manholes, temporary pumping within manholes, and temporary diversion and transfer pipes: 'shall be priced separately as actually incurred per the approved project execution plan'; within that, pipe installation executes the pipe installation and replacement items of the Chapter at hand, and well sealing and unsealing, dewatering and diversion and the like execute the Chapter 7 items.
II. Content comprehensively included, not adjusted for actual differences (Clauses 3 and 4)
- 'The pipe segment length of the pipeline items is a comprehensive assumption; where the actual differs, the line item applies as it stands.'
- 'This Chapter comprehensively allows for the influence of ordinary trench-wall retention and bracing on pipe laying; where the actual differs, this Chapter applies as it stands. Retention and bracing may, per the design drawings or the approved project execution plan, be priced under the corresponding line items of Chapter 7 of this Volume, General and Preliminary Items for Water Supply and Drainage Maintenance.' -> The influence of ordinary retention is not separately charged; only the retention works themselves may be listed separately under Chapter 7 items.
III. The general conversion basis of adjusting materials only, all else unchanged (Clauses 5-7)
- Where the pipe specification and model (internal and external diameter, wall thickness, lined reinforced segment length) differs from that assumed in the line item -> 'the pipe materials may be adjusted as actually incurred; all else unchanged'.
- Rubber-ring joint items: 'where the pipe and the rubber ring are purchased together as a set, the rubber ring material in the line item is no longer charged.'
- The steel pipe installation and replacement items apply to the laying of welded steel pipes, including seamless steel pipe, (straight-seam) rolled-plate pipe and spiral pipe: 'the consumption of the line items is comprehensively assumed over the commonly used wall thicknesses for the same diameter; where the design actually adopts a different steel pipe wall thickness, the pipe materials may be adjusted as actually incurred, all else unchanged'.
- The items for steel-plastic (PE-lined) composite water supply pipe and plastic-sheathed (PE) thin-walled stainless steel pipe 'include the installation of the fittings, the consumption of fittings being comprehensively assumed; where the actual differs, the fitting materials may be adjusted as actually incurred, all else unchanged; the installation of the other pipes does not include the installation of tees, bends, reducers and other fittings, and the installation of such fittings executes the corresponding line items of Chapter 2 of this Volume, Maintenance of Water Supply and Drainage Pipeline Appurtenances'. Exposed stainless steel pipe may execute the pipe installation and replacement items for pumping stations in Chapter 4; where the items are insufficient, the corresponding line items and cost provisions of the Shenzhen Consumption Quota Manual for Installation Works may be borrowed, with the adjustment coefficient of Volume note 0.4.6 applied.
IV. New-to-old pipe connections (Clauses 9 and 10)
- 'The new-to-old pipe connection items comprehensively allow for the installation of fittings, valves, short pipes and related accessories; materials not listed in the items shall be priced separately as actually incurred; where the fittings, valves, short pipes and related accessories actually used differ from those of the item, including where the branch pipe diameter or the bore of the connected valve differs, the materials may be adjusted as actually incurred, all else unchanged.' The earthwork and bedding of the connection working pit execute the Chapter 7 items, and plastering executes the corresponding items of Chapter 5, Water Treatment Plant Maintenance, 'with the labour cost multiplied by a coefficient of 1.1'; blind-plate installation executes the Chapter 2 items.
- 'The water-shutdown connection items for new-to-old pipe connections do not include the water charge for the wastage from pipe cutting; where it actually arises, the corresponding water charge is calculated separately per the approved project execution plan.'
- Material conversion of the connection trunk pipe (the trunk pipe of the largest diameter): where it is a prestressed concrete pipe, execute the ductile iron pipe water-shutdown open-cut pipe-cropping connection (expansive cement joint) item, with the labour cost multiplied by a coefficient of 1.5, the fitting materials adjusted as actually incurred and all else unchanged; where the trunk pipe is a socket-connection plastic pipe, execute the ductile iron pipe water-shutdown open-cut pipe-cropping connection (rubber-ring joint) item; where the trunk pipe is a fusion- or electrofusion-jointed plastic pipe, execute the steel pipe new-to-old connection item, with the fitting materials and welding consumables adjusted as actually incurred; where a steel pipe (sleeve pipe) is connected to an old trunk pipe of another material and the joint is caulked with oil-hemp and expansive cement, execute the ductile iron pipe water-shutdown open-cut pipe-cropping connection (expansive cement joint) item, and where the connection trunk pipe is prestressed concrete the labour cost is multiplied by a coefficient of 1.5.
V. Socket-joint concrete pipe laying and replacement (Clause 13)
- The pipe material is assumed as Class I reinforced concrete pipe; where the design differs, the pipe material may be adjusted, all else unchanged.
- 'Where concrete pipe is laid directly on the soil foundation of the trench, the labour cost and the machine-shift consumption of the item are multiplied by a coefficient of 1.18.'
- Where full-wrap concrete reinforcement or cast concrete encasement is required, 'the concrete of the reinforced part shall have its quantities measured per the dimensions shown on the design drawings and execute the concrete pipe cradle item of Chapter 7 of this Volume, General and Preliminary Items for Water Supply and Drainage Maintenance, with the labour cost and the machine-shift consumption multiplied by a coefficient of 1.5'.
- The socket cement mortar joint items do not include internal joint pointing; where the design requires internal pointing, execute the corresponding cement mortar pointing item for the internal surface treatment of wells, basins and channels under Chapter 5, Water Treatment Plant Maintenance.
VI. The fittings renewal repair items and their measurement (2.1.3, 2.2.1)
- 'Fittings renewal repair is measured by the quantities shown on the design drawings, counted by number and by diameter class.'
- The items include the consumption of fittings, and the fitting length is comprehensively allowed for; where the actual differs, the fitting materials may be adjusted as actually incurred, all else unchanged.
- The ductile iron fittings and chemical-material fittings installation and replacement items assume bends; where the actual is a reducer, a tee or a cross, 'execute the corresponding item distinguished by material, the fitting materials being adjustable as actually incurred, all else unchanged'; the ductile iron fittings items comprehensively allow for socket, spigot and flanged (disc) connections, and the fitting materials are adjusted per the actual fitting type and the branch pipe diameter - 'valves or flanges connected to the disc shall be charged separately'.
- The steel pipe fitting bend (reducer) items assume bends; where the actual specification or wall thickness differs, or the fitting is a reducer, execute the item within the corresponding diameter step range, the materials being adjustable; 'reducer installation and replacement follows the pipe diameter on the larger-bore side, and tee and cross installation and replacement follow the diameter of the larger-bore trunk pipe, in the corresponding fittings renewal repair items'.
VII. Demolition of old fittings not included (Volume note 0.4.16)
'Unless otherwise stated, the installation, replacement and repair items of this Volume for pipelines, fittings, structures and water supply and drainage facilities do not include the cost of demolishing old fittings; where such cost arises, the corresponding items of the demolition works in Chapter 7 of this Volume, General and Preliminary Items for Water Supply and Drainage Maintenance, may be executed.'
Applicability Boundaries
- The card covers maintenance works within the scope of Volume 2 of SJG 84-2020 (water supply and drainage maintenance within municipal maintenance works) - new pipeline laying, old pipeline replacement, fittings replacement, new-to-old connections and the like; the quota systems of other regions serve only as methodological references, and their line item numbers, consumption values and coefficients must not be transplanted directly.
- 'Materials adjustable as actually incurred' is limited to the price and type of the material; labour, plant and other consumption are unchanged; coefficients apply only where the provisions expressly give one (1.18, 1.5, 1.1), and the base to which the coefficient is applied is as limited by the original text (labour cost, or labour cost and machine-shift consumption).
- Comprehensively included content (valve closure and sealing with pumping of pit water, pipe segment length, the influence of ordinary trench-wall retention and bracing) is not re-adjusted for differences in site actuals; the same preliminary content must not be double-counted against the Chapter 5 and Chapter 7 items.
- The line between maintenance and new build follows the maintenance classification standard of Section 0.2 of the Volume; new-build works beyond that definition do not fall under these items.
Further Reading
SJG 84-2020 Consumption Standard for Municipal Maintenance Works, Volume 2, Water Supply and Drainage Maintenance Works: Section 0.2, maintenance classification standard; Volume note 0.4.6 (adjustment coefficient for borrowing the Shenzhen Consumption Quota Manual for Installation Works); note 0.4.16 (demolition of old fittings); Chapter 1, Water Supply and Drainage Pipeline Maintenance, principles for the use of line items, Clauses 1-13 (1.1.4); Chapter 2, Maintenance of Water Supply and Drainage Pipeline Appurtenances, 2.1.3 principles for fittings renewal repair and 2.2.1 measurement rules; Chapter 4, pump station maintenance; Chapter 5, water treatment plant maintenance; Chapter 7, General and Preliminary Items for Water Supply and Drainage Maintenance (preliminaries, demolition, concrete pipe cradle items).