Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-28

BOQ itemisation and quota application for preheat, post-heat and weld-joint heat treatment of industrial pipework: 030813008 and 030813009 measured per joint and banded by material and diameter x wall, electric-pad / induction / oxyacetylene items distinguished, hardness testing attribution, and the cost boundary against weld NDT

GB/T 50856-2024 Table H.13.1 (code 030813) lists preheat and post-heat as 030813008 and joint heat treatment as 030813009, both per 'joint', quantities per the code or design; NDT (030813001~030813007) lists separately. Pricing bands items by material and diameter x wall into quota items; electric pad, induction and oxyacetylene items differ and never interchange (GB 50236-2011 clause 7.4.11, 'post-heat and PWHT should use electric heating', grounds the electric items as the routine basis). Preheat followed directly by treatment still takes both items, the preheat labour x 0.87 (DB11/T 2382-2024 Table C.8.89-5 note). Hardness testing rides inside the treatment item only where the work content says so - the local PWHT item C3-7-54 includes 'hardness testing'; the preheat / post-heat and electric-pad joint items do not, and combine separately when the design requires.

Applicable Codes

  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. H Table H.13.1(code 030813)、H.15.13
  • 天津市安装工程工程量清单计价指引(2025)表H.13 无损检测与热处理(编码030813)
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) Table C.8.89-5、续Table C.8.90-2、续Table C.3.44-4
  • GB 50235-2010《工业金属管道工程施工规范》第6.0.10条
  • GB 50236-2011《现场设备、工业管道焊接工程施工规范》第7.4.2条、第7.4.11条、第7.4.14条

Positioning

BOQ itemisation and quota rules for preheat, immediate post-heat and joint heat treatment (PWHT) of industrial pipework: measurement per joint, banding by material and diameter x wall, the three heating-method item families (electric pad / induction / oxyacetylene), hardness-testing attribution, and the cost boundary against weld NDT.

Core conclusions

1) Three processes, three prices, never merged. GB/T 50856-2024 Appendix H Table H.13.1 'NDT and heat treatment (030813)' lists them apart: 030813008 'preheat and post-heat treatment', 030813009 'joint heat treatment'. NDT and spectral analysis run separately: 030813001 pipe-surface ultrasonic, 030813002 pipe-surface magnetic particle, 030813003 weld X-ray, 030813004 weld gamma, 030813005 weld ultrasonic, 030813006 weld magnetic particle, 030813007 weld penetrant, 030813010 spectral analysis, 030813011 inert-gas protection after pipe erection. Preheat / post-heat and PWHT are different processes: a joint needing both is two BOQ items and two quota items, never one price.

2) Descriptions, per-joint measurement and pricing items (Tianjin 2025 installation guide Table H.13, aligned with the national table):

  • 030813008: description = name, material, size and wall, pressure class, treatment method, hardness-test design requirement; unit = joint; rule = per the code or design; work = treatment, hardness testing; combinable base-price items = preheat / post-heat (guide 6-2612~2759), hardness testing self-combined.
  • 030813009: unit = joint; work = treatment (hardness testing self-combined); items = joint heat treatment (guide 6-2760~2887).
  • 030813005 weld ultrasonic: per joint, work includes making comparison blocks (self-combined); 030813003 weld X-ray per film / joint, description carrying film size and wall. Point: the BOQ counts joints (per code or design); pricing then lands on the quota band by material + outside diameter x wall + heating method - joint at list level, diameter x wall at item level.

3) Heating methods seat exactly; items never interchange. Quotas table items by method:

  • Induction: DB11/T 2382-2024 Table C.8.89-5 'high-pressure carbon steel, induction', banded by nominal diameter (C8-15-53 up to 300mm, C8-15-55 up to 400mm, per 10 joints), materials plastic tape, bare copper 120mm2, flanged stop valve, plant 100kW medium-frequency unit; work - preparation, fixing thermocouples, wrapping, wiring, powering and heating, stripping, recovery, clearing.
  • Electric pad: continuation C.8.90-2 (C8-15-119 up to 200mm, per 10 joints), materials high-silica cloth 25mm and 10kW pads, plant self-controlled unit; note - 'an added insulation layer per design takes the same cloth content, labour unchanged'.
  • Flame (oxyacetylene): some local quotas list flame separately as 'joint preheat and post-heat, low-alloy, oxyacetylene' by outside diameter x wall (e.g. 377x8~16, 426x8~18, 478x10~20, 530x10~20), per joint; PWHT bands by 'carbon steel, electric pad, diameter x wall'. Order: fix the method from design / scheme, then seat by material and diameter x wall. GB 50236-2011 clause 7.4.11 ('post-heat and PWHT should use electric heating') grounds the electric items as routine; flame needs scheme or design support - never swap for cheapness.

4) Preheat immediately followed by treatment - a factor, not a merger. Table C.8.89-5 note: 'where electric pad or induction preheat is followed immediately by treatment per design, the preheat item's labour is x 0.87.' Both items still apply; only the preheat labour drops - the quantified saving of continuous work on one joint, not a merger.

5) Hardness testing inside or outside - read the work content; never 'always separate' or 'always included'.

  • Included: DB11/T 2382-2024 continuation C.3.44-4 'local PWHT' (C3-7-54, plate to 50mm, per 10m) lists 'hardness testing' in its work content - never re-charged.
  • Excluded: the per-joint preheat / post-heat and electric-pad items (C.8.89-5, C.8.90-2 series) stop at 'powering, heating, stripping, recovery, clearing'; the list description's 'hardness-test design requirement' itself signals separate combination when required.
  • Code basis: GB 50235-2010 clause 8.5.1 - 'heat-treated welds and components shall be hardness-tested after treatment', over weld and heat-affected zones, dissimilar joints on both sides, on form A.0.15 - technically mandatory, but its pricing home follows the item's work content.

6) Boundary against NDT. List (the 030813 sub-items) and quota both keep them apart: treatment items exclude NDT, NDT items exclude treatment. Appendix H note H.15.13: 'the NDT items include fabrication and erection of the instrument stands' - stands live in NDT; thermocouples, pads and blankets live in the treatment items' materials. Film-count conversion and the itemisation for static equipment and water piping sit in the companion weld-NDT card.

Applicable boundaries

  • Codes per GB/T 50856-2024 Table H.13.1 (superseding GB 50856-2013); quota numbers are regional and version-specific - Tianjin 6-2612~2887, Beijing C8-15-53/55/119 and C3-7-54, Guangxi 2024 its own; never carry numbers across regions - check name and band in the local volume.
  • Per-joint counting presupposes the technical decision of which joints need what (GB 50235-2010 Table 6.0.10-1; GB 50236-2011 Table 7.4.2 and clause 7.4.14) - judge first, count second.
  • Descriptions state the treatment method and hardness requirement per the design; absent design, take them from scheme and code and record in the build-up notes.
  • Itemisation and application only, no prices; double application or cross-substitution of preheat and treatment is double pricing or wrong item.
  • Not for: static-equipment and process-metal-structure welds (Appendix C Table C.8.1, 030308), water / heating / gas piping (back to Appendix H codes); furnace whole-piece treatment is a works-level matter priced on special schemes.

Further reading

GB/T 50856-2024 Appendix H Table H.13.1 (030813001~030813011 in full) and note H.15.13; Tianjin 2025 installation guide Table H.13; DB11/T 2382-2024 Tables C.8.89-5 (C8-15-53/55), C.8.90-2 (C8-15-119), C.3.44-4 (C3-7-54) with the 0.87 note; Guangxi 2024 build-up tables 030813008 / 030813009; technical: GB 50235-2010 clauses 6.0.10 and 8.5.1; GB 50236-2011 clauses 7.4.2, 7.4.11, 7.4.14.

Keywords

  • 030813008
  • 030813009
  • 焊口热处理
  • 焊前预热后热
  • 电加热片
  • 电感应
  • 无损检测与热处理
  • 硬度测定