BOQ itemisation and quantity take-off of non-destructive testing of pipe welds: 030813 non-destructive testing and heat treatment, 030308 non-destructive inspection, and the number of radiographic films derived from the 250mm effective film length

Non-destructive testing of pipe welds must be a separate BOQ item, not merged into pipe installation: industrial pipework per GB/T 50856-2024 Appendix H Table H.13.1 (code 030813, non-destructive testing and heat treatment); static equipment and process metal structures per Appendix C Table C.8.1 (code 030308, non-destructive inspection); heat treatment and NDT of water supply and drainage, heating and gas pipework revert to the corresponding Appendix H codes. The number of radiographic films = the total length of welds to be inspected computed per the design / the effective film length, the effective film length being taken as 250mm where the design is silent. Inspection cost is built up by fixing the physical quantity as method x ratio x base - not estimated as a percentage of the pipe cost.

Applicable Codes

  • GB/T 50856-2024 通用安装工程工程量计算标准 App. H Table H.13.1(code 030813 无损检测与热处理)
  • GB/T 50856-2024 App. C Table C.8.1(code 030308 无损检验)
  • GB/T 50856-2024 App. K 第K.9.2条

Positioning

Where non-destructive testing of pipe welds sits in the bill of quantities and how its quantities are computed: industrial pipework under Appendix H code 030813, static equipment and process metal structures under Appendix C code 030308, utility pipework (water, heating, gas) under Appendix H; and the rule for the number of radiographic films.

Core conclusions

1. Industrial pipework: GB/T 50856-2024 Appendix H (industrial pipework works) provides that the item setting, item-description content, unit of measurement and measurement rules for "non-destructive testing and heat treatment" follow Table H.13.1, whose item code is 030813. Weld NDT is thus not merged into the pipe installation item but listed separately under 030813, with the item description fully stating the testing method, ratio and acceptance class on which pricing depends.

2. Static equipment and process metal structures: Appendix C provides that item setting, item-description content, unit and measurement rules for "non-destructive inspection" follow Table C.8.1, code 030308.

3. Computing the number of films: in Table C.8.1 (code 030308), the number of films is the total length of welds to be inspected computed per the design divided by the effective film length; where the design does not specify, the effective film length is taken as 250mm.

4. Utility pipework: GB/T 50856-2024 Appendix K states that "pipe heat treatment and non-destructive testing shall be itemised under the corresponding item codes of Appendix H, industrial pipework works, of this standard" - i.e. no separate code is created within Appendix K; itemisation and pricing return to Appendix H (030813).

5. Pricing logic: the inspection cost is fixed as method x ratio x base into a physical quantity, then priced under the corresponding 030813/030308 item - not estimated as a percentage of the pipe works cost. Two bases for the physical quantity:

  • Weld count (joints) as base: the inspection-class ratio of GB 50184-2011 Table 8.2.1 x the number of welds in the batch; for DN under 500, ring-weld sampling is at least 1 ring weld with fixed-position welds at least 40% of the sample; for DN of 500 and over, local examination of each ring weld covers at least 150mm of weld length.
  • Film count as base (radiography): total length of inspected welds / effective film length (250mm where the design is silent). The higher the ratio (e.g. 100% radiography, 100% ultrasonic double testing) or the more methods (radiography + ultrasonic + magnetic particle / penetrant), the larger the billed quantity and cost; re-testing after repair re-runs the original method, and whether its quantity is inside the all-in unit rate must be agreed.

Applicable boundaries

  • This card only fixes how to itemise and how to compute the physical quantity - no all-in unit rates or regional consumption levels; rates follow the contract or the current local pricing bases.
  • The 250mm effective film length is the value "where the design is silent"; where the design specifies, the design governs.
  • The film-count rule comes from Table C.8.1 (NDT of static equipment and process metal structures); when pipe welds are radiographed and a film count is needed, the same "total length / effective film length" algorithm may be referenced, but the item code stays 030813.
  • The full item setting, units and rules of Tables H.13.1 and C.8.1 must be read from the tables themselves; this card does not restate every sub-item.

Further reading

  • GB/T 50856-2024 General Installation Works Standard, Appendix H Table H.13.1 (NDT and heat treatment, code 030813) and its notes.
  • GB/T 50856-2024 Appendix C, Table C.8.1 (non-destructive inspection, code 030308) and its statement on film count and the 250mm effective film length.
  • GB/T 50856-2024 Appendix K, clause K.9.2 (pipe heat treatment and NDT itemised under Appendix H codes).
  • Governing rules on ratios and acceptance classes: GB 50184-2011 Tables 8.1.1 and 8.2.1; GB 50683-2011 clause 8.3.1.

Keywords

  • 无损检测与热处理
  • 030813
  • 无损检验
  • 030308
  • 拍片张数
  • 胶片有效长度250mm
  • 探伤工程量
  • 清单列项