BOQ attribution and quota measurement rules for conductor crossings of obstacles on overhead power lines: measured 'per crossing', the 50 m spacing test for same-type obstacles within one span, and the 4.0 coefficient for live-line crossings
Conductor crossings of obstacles are not listed as separate BOQ items - 'crossing type (rivers, gorges, highways, railways, houses, etc.)' is an item description of the conductor stringing item; on the quota side, conductor crossing erection is measured 'per crossing': within one span, several adjacent obstacles of the same type spaced no more than 50 m apart count as one crossing, more than 50 m as two; several types of obstacles within one span are counted by their number. Crossings of power lines and low-voltage (telecommunication) lines are compiled by default on an outage basis; where a live-line crossing is required, the labour and plant consumption is multiplied by the 4.0 coefficient; the river crossing items apply only to rivers (or lakes) with water, and rivers within 20 m are not treated as crossings.
Applicable Codes
- GB/T 50856-2024 App. D Table D.11.1 及 D.17.14 第4款
- TB/T 10829-2024 铁路工程预算定额 Vol. 8 电力工程 Ch. 1 架空电力线路 说明五、六
Topic positioning
How crossings of highways, railways, rivers, power lines, houses and other obstacles are handled on both the BOQ side and the quota side for overhead distribution/power lines: where they sit in the BOQ, how the count of 'crossings' is determined on the quota side, and which situations take coefficients - the basis for deciding the common dispute of 'crossing charges claimed as extra'.
Core conclusion
1. BOQ side: crossings are not separate items; they are an item description of conductor stringing. GB/T 50856-2024 Appendix D, Table D.11.1, notes (D.17.14), item 4: 'The crossing type means crossing obstacles such as rivers, gorges, highways, railways and houses' - 'crossing type' appears as item description content of the conductor stringing BOQ item, on which the all-in unit rate depends; no separate 'crossing' BOQ item should be created, otherwise it double counts with conductor stringing.
2. Quota side: conductor crossing erection is measured 'per crossing'; the test in three sentences (TB/T 10829-2024 Volume 8, Note 6, original text):
The conductor crossing erection items are measured 'per crossing': 'where one span contains several adjacent obstacles of the same type, obstacles of the same type spaced equal to or less than 50 m apart count as one crossing; more than 50 m counts as two crossings. Where one span contains several types of obstacles, they are counted by the number of obstacles.'
Unpacked into three rules:
- Several same-type adjacent obstacles within one span, spacing no more than 50 m -> count 1 crossing;
- Same situation, spacing more than 50 m -> count 2 crossings (beyond two, keep judging pairwise between adjacent obstacles);
- Several types of obstacles within one span -> counted by the number of obstacles (obstacles of different types are not merged).
3. Coefficients and limits of use (TB/T 10829-2024 Volume 8, Note 5, original text):
- The '10 kV overhead power line crossing' and '35 kV overhead power line crossing' items for power lines and low-voltage (telecommunication) lines are compiled assuming the crossed power line is de-energised. Where a live-line crossing is required, the labour and plant consumption shall be multiplied by the 4.0 coefficient.
- The river crossing erection items apply only to rivers (or lakes) with water; rivers within 20 m are not treated as crossings.
That is: the crossing items for power/telecommunication lines are compiled by default on an outage basis; where a live-line crossing is unavoidable, labour and plant consumption x 4.0. The river (or lake) crossing items are only for rivers/lakes with water; rivers of 20 m or less are not counted as crossings.
4. Edition/regional comparison note: local consumption standards may not list 'crossing' items separately. For example, the overhead distribution line chapter set up under DB11/T 2382-2024 clause 6.4.1 has five sections - 'pole erection, cross-arm assembly, conductor stringing, pole-mounted equipment, live-line work' - with no separate crossing items; in such regions the crossing goes into the item description and rate build-up of conductor stringing, and where an item is genuinely missing it is handled as a supplementary quota item; the crossing items of other industries must not be borrowed without conversion.
Applicability boundaries
- The 'per crossing' rule comes from the railway works budget quota system (TB/T 10829-2024 Volume 8, Power Works); for building and municipal installation works whose local quota sets no crossing measurement rule, it may serve as a methodological reference, but the consumption and on-costs must be converted to the local pricing basis - no direct application.
- The 50 m spacing test applies only to same-type, adjacent obstacles within one span; obstacles of different types are not merged.
- The 4.0 coefficient only scales the labour and plant costs of the crossing items for power lines and low-voltage (telecommunication) lines in the live-line crossing case; it does not scale materials.
- Rivers within 20 m are not counted as crossings, but crossings of other obstacles (highways, railways and the like) are not subject to the 20 m limit.
- Outage construction is the default premise of the items, hence no coefficient; whether the crossing is live-line must follow the approved construction scheme/outage plan, not be chosen at will.
Further reading
- GB/T 50856-2024 Appendix D, Table D.11.1 and its notes (D.17.14) item 4 - definition of the crossing type and its BOQ attribution.
- TB/T 10829-2024 'Railway Works Budget Quota Manual, Volume 8, Power Works', Chapter 1 Overhead Power Lines: Note 1 (this chapter includes the 'overhead power line crossing of obstacles' items), Note 5 (the 4.0 coefficient for live-line crossings; no crossing for rivers within 20 m), Note 6 (the three tests for measuring 'per crossing'); the volume's general notes on scope of application and the bracketed main-material provisions are covered under the same standard's scope and application rules.