Measurement basis split for pricing daylighting canopies (PC multiwall sheet / glass / stainless steel frame) by quota: the surface layer by area, independent supporting frame by mass
A daylighting canopy cannot be priced under one blanket basis; it splits into two layers: the surface layer (PC multiwall sheet, glass, metal sheet) applies the sunlight-sheet roof / daylighting roof items, measured in area (m2) on the dimensions shown on the drawings, with the attached framing already included in the item and not listed separately; the load-bearing steel columns, beams, trusses, monitor frames, supports and the like apply the metal structure works items, measured in mass (t) on the dimensions shown (no deduction for holes; welding electrodes, rivets and bolts add no mass). Paint and fireproofing coating are not in the metal member items and require the painting works items separately. The dividing test: frame members belonging to the daylighting item's attached framing merge into the surface layer by area; independent load-bearing structure is listed separately by mass. The national standard takes the same view - GB/T 50854-2024 Appendix J requires the roof trusses, purlins and other supporting structures of sunlight-sheet and GRP roofs to be itemised under Appendix F metal structure works and Appendix G timber structure works codes.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准(北京)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
- 江苏省建筑与装饰工程消耗量标准(2026版)
Scope of the question
When pricing daylighting canopies (stainless-frame canopies, PC multiwall sheet canopies, glass skylight roofs etc.), the panels and the supporting frame cannot share one measurement basis; they must be listed and priced in two layers - surface layer by area, independent supporting frame by mass. This card gives the basis, the dividing test and regional differences.
Core conclusions
1. Surface layer - by area (m2), framing included
- Quantity rule (Beijing DB11/T 2382-2024 Article 4.10.19 paragraph 2): sunlight-sheet roofs and daylighting roofs are measured in area on the dimensions shown on the drawings, without deducting single holes of 0.30 m2 or less.
- Framing attribution (Article 4.10.5): consumptions for sunlight-sheet roofs and daylighting roofs are determined per the drawings, including the framing (frame) work content; where the drawings require spider-fitting (point-fixed) installation, Articles 4.13.1 to 4.13.28 apply with labour x 0.90. That is, the framing attached to the surface layer is already inside the daylighting / sunlight-sheet roof (surface) items, taken together by area, not listed separately.
2. Independent supporting frame - by mass (t)
- Measurement rule (Article 4.7.17): steel members are measured in mass on the dimensions shown on the drawings, without deducting the mass of holes, welding electrodes, rivets and bolts adding no mass; steel columns (4.7.14), steel beams (4.7.15), steel roof trusses / bracing trusses / lattice trusses (4.7.13) and space trusses (4.7.12) are likewise measured in mass on the dimensions shown. Supporting frames such as steel monitor frames and steel supports follow this basis in t under the metal structure works items.
- Paint / fireproofing excluded (Article 4.7.11): metal member consumptions exclude paint and fireproofing coating; where the drawings require anti-corrosion or fire protection, Articles 4.15.1 to 4.15.10 apply - the painting works items are charged separately.
3. The national standard takes the same view GB/T 50854-2024 Appendix J (roofing and waterproofing works): the roof trusses, purlins and other supporting structures of sunlight-sheet and GRP roofs shall be itemised under the relevant codes of Appendix F metal structure works and Appendix G timber structure works - surface layer to roofing, supporting structure to metal structure, a nationwide split.
4. Where the line falls (against double counting) One-line test: is the steelwork part of the daylighting item's framing (frame)?
- Members attached to the surface layer (purlins / frames of small-section tube) - merge into the daylighting (sunlight-sheet roof) items, by area;
- Independent load-bearing structure (columns, main beams, trusses, monitor frames, floor-standing supports) - list separately under metal structure items by mass in t. The same logic appears in Article 4.10.3: entrance lobby and cantilever canopy consumptions should not include metal frames; where the drawings require them, Articles 4.7.1 to 4.7.18 apply.
5. Special note on stainless frames The Beijing 2024 metal structure items are all carbon steel; no dedicated stainless metal structure items exist. Common practice for stainless profile frames: borrow the steel member (steel support, steel monitor frame etc.) items measured in t, substitute stainless profiles as the main material priced at design quantity plus wastage at compilation-date market prices; where sizes or workmanship differ too far and no item fits, follow the supplementary quota procedure. The stainless / carbon steel price gap makes main-material adjustment the cost-sensitive point.
6. Regional differences Area bases vary in wording: Beijing measures on the dimensions shown; the Jiangsu consumption standard for building and decoration works (2026 edition) measures daylighting-sheet roofs and glass skylight roofs on the external surface area shown, without deducting holes up to 0.3 m2, while membrane roofs are measured on the horizontal projected area to be covered. For sloped or curved canopies, check whether the local rule takes the developed external surface or the horizontal projection.
Applicability limits
- The clause bases are Beijing DB11/T 2382-2024 (Section 4.7 metal structure works, Section 4.10 roofing and waterproofing works); local projects follow the current local quota and its rules, but the split principle - surface by area, independent frame by mass - holds at the national level (GB/T 50854-2024).
- Daylighting items including the framing (frame) work content means only the members attached to the surface layer; load-bearing structure standing on its own is outside that scope and must be listed separately to avoid double counting.
- Non-carbon-steel members without dedicated items, borrowed under carbon-steel items, require main-material adjustment as executed.
- The area basis for sloped / curved canopies (developed area vs horizontal projection) varies by locality - check local rules before pricing.
- This card settles the basis split (area or mass); item numbers, units and contents follow the quota version executed by the project.
Further reading
- Beijing DB11/T 2382-2024 Construction Consumption Standard, Articles 4.10.5, 4.10.3, 4.10.19 (Part 4 building and decoration works, 4.10 roofing and waterproofing works).
- Beijing DB11/T 2382-2024 Articles 4.7.11 to 4.7.17 (4.7 metal structure works).
- GB/T 50854-2024 Measurement Standard for Building and Decoration Works, Appendix J roofing and waterproofing works, Appendix F metal structure works, Appendix G timber structure works.
- Jiangsu consumption standard for building and decoration works (2026 edition), roofing works notes (area on the external surface).